West Side Bicycle Boulevards Project - Special Provisions Summary
This document comprises the Special Provisions for the West Side Bicycle Boulevards project, a City of Tucson Department of Transportation roadway improvement contract (Plan No. I-2024-018) designed to develop protected bicycle facilities across four separate boulevard segments. The project encompasses the Golden Hills Bicycle Boulevard (Greasewood Road to Riverview Boulevard, 1.9 miles), El Rio-Dragoon Bicycle Boulevard (Dragoon Avenue to Speedway Boulevard, 1.4 miles), Menlo Park Bicycle Boulevard (Speedway Boulevard to Bonita Avenue, 2.0 miles), and Ontario-Mecedora Bicycle Boulevard (Cholla Boulevard to Diamond Street Loop, 1.7 miles). Improvements include traffic calming features (speed humps and cushions, traffic circles), BikeHAWK signals at six intersections, thermoplastic and preformed pavement markings, signage, concrete curbs, sidewalks, curb access ramps, drainage modifications, utilities coordination, and extensive landscaping with a 24-month establishment period. The contractor is required to complete the construction phase within 150 calendar days of the Notice to Proceed, with landscape establishment comprising an additional 12-month period (365 consecutive calendar days). Critical project milestones restrict construction activities during the Gem and Mineral Show (late January to mid-February), Pima County Fair (late April), and designated seasonal utility windows, with no arterial or collector street restrictions permitted during peak traffic hours (7-9 a.m. and 4-6 p.m., Monday-Friday). The contractor must submit detailed traffic control plans at least five working days prior to construction commencement and provide weekly updated schedules documenting two-week look-ahead activities.
The contract requires the contractor to assume full responsibility for mobilization, demobilization, quality control testing, traffic control, utility coordination, environmental compliance (including stormwater management and erosion control), and maintenance of public access throughout construction. Liquidated damages apply if substantial completion is not achieved within the contract period, with retention of 10 percent of all non-landscape establishment items (minimum $2,000) through the 12-month landscape establishment phase. The contractor must obtain all applicable permits (air quality, water quality, excavation, storm water) at its own cost and coordinate extensively with utility providers including Tucson Water, Pima County Regional Wastewater Reclamation Department, Southwest Gas, Tucson Electric Power, and telecommunications providers. Special provisions mandate weekly quality control reports, certified payrolls, and contractor-provided testing by ADOT-approved laboratories; delinquent reports result in $2,500 monthly deductions from progress payments. The contractor bears all costs for construction water (from metered sources only), debris disposal, temporary erosion control, dust suppression, dewatering permits, survey monument preservation or replacement, and landscape establishment including hand watering, weed control, graffiti removal, and plant replacement. No separate compensation is provided for numerous incidental items including flagging coordination, temporary fencing, minor alterations under $10,000 (paid through ITEM 9300111), or various traffic control elements beyond predetermined rates detailed in Section 701.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WEST SIDE BICYCLE BOULEVARDS
GOLDEN HILLS BICYCLE BOULEVARD
GREASEWOOD RD TO RIVERVIEW BLVD
EL RIO-DRAGOON BICYCLE BOULEVARD
DRAGOON AVE TO SPEEDWAY BLVD
MENLO PARK BICYCLE BOULEVARD
SPEEDWAY BLVD TO BONITA AVE
ONTARIO-MECEDORA BICYCLE BOULEVARD
CHOLLA BLVD TO DIAMOND ST LOOP
Roadway Improvements
SPECIAL PROVISIONS
COT Plan No. I-2024-018
Final Submittal
October 2025
Special Provisions West Side Bicycle Boulevards
Plan I-2024-018
SP-2 of 124
CONTRACT SPECIAL PROVISIONS FOR:
WEST SIDE BICYCLE BOULEVARDS
GOLDEN HILLS BICYCLE BOULEVARD
GREASEWOOD RD TO RIVERVIEW BLVD
EL RIO-DRAGOON BICYCLE BOULEVARD
DRAGOON AVE TO SPEEDWAY BLVD
MENLO PARK BICYCLE BOULEVARD
SPEEDWAY BLVD TO BONITA AVE
ONTARIO-MECEDORA BICYCLE BOULEVARD
CHOLLA BLVD TO DIAMOND ST LOOP
COT PLAN NO. I-2024-018
PROFESSIONAL SEALS
These specifications were prepared under the direction of the following individuals:
Matthew P. Kershner, PE, AECOM Sheets 1-73
Laura Mielcarek, RLA, Wheat-J2 Design Sheets 74-80
Their seals, affixed above, attest that those portions of these specifications which relate to the plan sheets numbers appearing next to the seal were prepared under their direction.
C
E R
IFICATE
N O
S A
R e g i s t e r e d P ro fes sionalEng in e e r
C i v il
U
D A
T E
SIGNEDA
RIZON
40990
MATTHEW P.
5 KERSHNER
Plan I-2024-018
SP-3 of 124
TABLE OF CONTENTS
SPECIFICATIONS AND DETAILS
PROPOSED WORK
GENERAL PROVISIONS
SECTION 101 - ABBREVIATIONS AND DEFINITIONS
SECTION 102 – BIDDING REQUIRMENTS AND CONDITIONS
SECTION 103 - AWARD AND EXECUTION OF CONTRACT
SECTION 104 - SCOPE OF WORK
SECTION 105 - CONTROL OF WORK
SECTION 106 - CONTROL OF MATERIAL
SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC
SECTION 108 - PROSECUTION AND PROGRESS
SECTION 109 - MEASUREMENT AND PAYMENT
SECTION 201 - CLEARING AND GRUBBING
SECTION 202 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
SECTION 206 - FURNISH WATER SUPPLY
ITEM 4060200 ASPHALTIC CONCRETE (SPEED HUMP)
ITEM 4060201 ASPHALTIC CONCRETE (SPEED HUMP) (BICYCLE FRIENDLY SPEED
CUSHION – OM BB ONLY)
SECTION 509 - SANITARY SEWER MANHOLES
SECTION 510 - POTABLE WATER SYSTEMS
ITEM 5103101 POTABLE WATER, ADJUST VALVE BOX AND COVER
SECTION 515 - UTILITY IMPACTS
ITEM 5150005 UTILITY POTHOLING, DEPTH LESS THAN TWELVE FEET
(12’) 58
ITEM 5150007 UTILITY POTHOLING, DEPTH TWELVE FEET (12’) AND
GREATER 58
SECTION 607 - SIGN SUPPORTS
ITEM 6070010 SIGN POST (PERFORATED) (SINGLE)
ITEM 6070110 FOUNDATION FOR SIGN POST (PERFORATED)
ITEM 6070220 REMOVE AND RELOCATE SIGNS
ITEM 6072001 SIGN MOUNT ASSEMBLIES (POLE MOUNTED) (BIKE BOULEVARD SIGN)
SP-4 of 124
SECTION 608 - SIGN PANELS
SECTION 701 - MAINTENANCE AND PROTECTION OF TRAFFIC
SECTION 704 - THERMOPLASTIC STRIPES AND MARKINGS
ITEM 7040121 THERMOPLASTIC (PREFORMED) (0.12”) (BIKE GREEN)
SECTION 705 - PREFORMED PLASTIC PAVEMENT MARKING
SECTION 706 - RAISED PAVEMENT MARKERS
SECTION 707 – TUBULAR MARKER (FLEXIBLE)
SECTION 708 - PAINTED PAVEMENT MARKINGS
SECTION 730 - GENERAL REQUIREMENTS FOR TRAFFIC SIGNAL AND STREET
LIGHTING SYSTEMS
SECTION 732 - ELECTRICAL MATERIAL AND SERVICE
ITEM 7320020 ELECTRICAL CONDUIT (2”) (PVC)
ITEM 7320025 ELECTRICAL CONDUIT (2 1/2”) (PVC)
ITEM 7320030 ELECTRICAL CONDUIT (3”) (PVC)
ITEM 7320040 ELECTRICAL CONDUIT (4”) (PVC)
ITEM 7320800 SERVICE PEDESTAL CABINET
ITEM 7320890 ELECTRICAL SERVICE INSTALLATION
SECTION 733 - SIGNAL INDICATIONS AND MOUNTING ASSEMBLIES
SECTION 734 - TRAFFIC SIGNAL CONTROLLER ASSEMBLY
SECTION 735 - DETECTORS
SECTION 736 - STREET AND SIGN LIGHTING
SECTION 737 - INCIDENTAL ELECTRICAL WORK
SECTION 802 - LANDSCAPE GRADING
SECTION 803 LANDSCAPE BORROW AND PLATING MATERIAL
SECTION 806 - TREES, SHRUBS, AND PLANTS
ITEM 8061700 LANDSCAPE PRUNING
SECTION 807 - LANDSCAPING ESTABLISHMENT
ITEM 8070012 MISCELLANEOUS WORK (LANDSCAPE ESTABLISHMENT
MAINTENANCE)
SECTION 908 - CONCRETE CURBS, GUTTERS, SIDEWALKS AND DRIVEWAYS 112
SECTION 909 - SURVEY MONUMENTS
ITEM 9130009 RIPRAP (HAND PLACED) (GROUTED)
SECTION 924 - CONTRACTOR QUALITY CONTROL
ITEM 9240170 CONTRACTOR QUALITY CONTROL
SP-5 of 124
SECTION 930 - INCIDENTAL ITEMS
ITEM 9300111 MISCELLANEOUS WORK (MINOR ALTERATIONS IN DETAILS OF
CONSTRUCTION)
SECTION 1005 - BITUMINOUS MATERIALS FOR SURFACING
SECTION 1006 – PORTLAND CEMENT CONCRETE
SP-6 of 124
SPECIFICATIONS AND DETAILS
The work embraced herein shall be performed in accordance with the requirements of the following separate documents:
Specifications
Pima Association of Governments (PAG), Standard Specifications for Public Improvement, 2015 Edition, Volume 1 (typically referenced as “Standard Specifications” unless otherwise specified).
http://apps.pagnet.org/standardspecifications
Details
City of Tucson Department of Transportation, Access Ramp Details, September 2025.
https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/curb_access_ramp_sep2025.pdf
City of Tucson Department of Transportation, Speed Hump & Table Detail, October 2024.
https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/speed-hump-table-detail_oct2024.pdf
City of Tucson Department of Transportation, Traffic Circle Detail, November 2024.
https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/traffic_circle_cot_std_dtl_110_nov_2024.pdf
City of Tucson Department of Transportation, Street Name Sign Layouts for Signalized and Unsignalized Intersections.
https://www.tucsonaz.gov/files/transportation/Signalized_07-30-10.pdf https://www.tucsonaz.gov/files/transportation/Unsignalized_07-30-10.pdf
Pima Association of Governments (PAG), Standard Details for Public Improvements, 2015 Edition, Volume 2.
http://apps.pagnet.org/standardspecifications/
Arizona Department of Transportation, Highways Division, Traffic Signals and Lighting Standard Drawings, December 2012 and current revisions.
http://www.azdot.gov/business/engineering-and-construction/traffic/signals-and-lighting-standard-drawings
Manuals
U.S. Department of Transportation, Federal Highway Administration, Manual on Uniform Traffic Control Devices for Streets and Highways, December 2009 and amendments.
http://mutcd.fhwa.dot.gov/pdfs/2009/pdf_index.htm
SP-7 of 124
Arizona Supplement to the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition (January 2012) http://www.azdot.gov/Highways/Traffic/Standards.asp
2015 Edition of the Additions by the City of Tucson to the Manual on Uniform Traffic Control
Devices, for Temporary Traffic Control http://www.tucsonaz.gov/tdot/traffic-engineering-resources
City of Tucson Department of Transportation, Traffic Signal Design Manual, May 2003 and current revisions.
https://www.tucsonaz.gov/files/transportation/Design_Manual.pdf
Pima County and City of Tucson Departments of Transportation, Signing & Pavement Marking Manual, 2020 First Edition https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Transportation/Roadway %20Design/FINAL-Pima-County_City-of-Tucson-Signing-and-Pavement-Marking-Manual- 2020-First-Edition_linking_nocomments-12_21.pdf
Other Specifications and Details
Pima County Regional Wastewater Reclamation Department, Design Standards, Specifications & Details, 2012 Edition:
http://webcms.pima.gov/government/wastewaterreclamation/designstandards
Tucson Water Specifications and Details, 2017 Edition:
https://azdot.gov/sites/default/files/media/2019/11/2008-standards-specifications-for-road-and-bridge-construction.pdf
City of Tucson DTM Standard Details.
https://www.tucsonaz.gov/Departments/Transportation-Mobility/DTM-Engineering
These Special Provisions and Bid Schedule.
SP-8 of 124
PROPOSED WORK
The Golden Hills proposed work is located within Sections 2, 3 and 4, Township 14 South, Range
13 East of the Gila and Salt River Base and Meridian, within the City of Tucson, Pima County, Arizona.
The El Rio-Dragoon proposed work is located within Section 3, Township 14 South, Range 13
East and within Section 34, Township 13 South, Range 13 East of the Gila and Salt River Base and Meridian, within the City of Tucson, Pima County, Arizona.
The Menlo Park proposed work is located within Sections 10 and 11, Township 14 South, Range
13 East of the Gila and Salt River Base and Meridian, within the City of Tucson, Pima County, Arizona.
The Ontario-Mecedora proposed work is located within Sections 9, 10 and 11, Township 14 South, Range 13 East of the Gila and Salt River Base and Meridian, within the City of Tucson, Pima
County, Arizona.
This project provides for the roadway improvements consisting of traffic calming, BikeHAWK signals, signing, pavement markings and landscaping. The limits of construction along the Golden
Hills Bicycle Boulevard begin at Greasewood Road and extend to Riverview Boulevard, a total of
1.9 miles. The limits of construction along the El Rio-Dragoon Bicycle Boulevard begin at the north end of Dragoon Avenue and extend to Speedway Boulevard, a total of 1.4 miles. The limits of construction along the Menlo Park Bicycle Boulevard begin at Speedway Boulevard and extend to Bonita Avenue, a total of 2.0 miles. The limits of construction along the Ontario Mecedora
Bicycle Boulevard begin at Cholla Boulevard and extend to Diamond Street Loop, a total of 1.7 miles. The project consists of furnishing all labor, materials, equipment and supervision necessary for the roadway improvements.
The work also includes, but is not limited to, construction of speed humps, speed cushions, traffic circles, concrete curb, concrete sidewalk, curb access ramps, concrete driveway aprons, traffic signals and traffic signal modifications, pavement markings and signing, landscaping and other related incidental work as shown on City of Tucson Plan No. I-2024-018.
SP-9 of 124
GENERAL PROVISIONS
For the purpose of these Special Provisions, the terms Agency, Department, City, City of Tucson, and Engineer are synonymous.
1. Project Objectives
The objective of this contract is to complete construction as quickly as possible while minimizing the impact to the Stakeholders. The Stakeholders are, but not limited to, the adjacent businesses, commuters, buses, emergency services, pedestrians, bicyclists, and adjoining neighborhoods. As such, this work will be accomplished in an orderly manner as defined herein.
Driver and pedestrian/access shall be maintained during the construction of improvements.
Temporary paved access shall be provided at all times to meet the Americans with Disabilities Act
(ADA) requirements. The contractor is advised that an approved construction sequencing scheme meeting the intent of the project objectives will need to be followed. The contractor shall propose a construction phasing plan for the Engineer’s approval prior to beginning work. Once approved, the contractor shall follow the phasing plan unless modified by the Engineer in writing.
2. Project Limits and Restrictions
The contractor shall perform all work within the public right-of-way, legally obtained easements including temporary construction easements (TCEs), legally obtained rights-of-entry (ROE), and legally acquired property by the City of Tucson. The contractor shall assume all responsibility and liability for any encroachment upon private property. The use of private property for construction yards will be allowed only if zoning requirements allows its use for this purpose. See Section 106-
9 of the Standard Specifications for further details regarding temporary construction yards. The cost of the construction yard is considered incidental to the project. Under no circumstances shall any equipment, vehicles or other construction items that are not specifically required or needed for the immediate construction at hand be stored or left on private property without the express written permission of the property owner.
The contractor shall field verify all existing conditions shown on plans and specified herein prior to beginning construction. Any significant deviations to the conditions that may affect the timely construction of improvements shall be brought to the attention of the Engineer within 24 hours of discovery. Prior to delivery of any equipment, materials or supplies to the site of any work, or the beginning of any construction work, it is strongly recommended that the contractor take pre-construction photos or videos as deemed appropriate for establishing the conditions existing in all the areas that may be affected by the construction.
A. Construction Scheduling
SP-10 of 124
Various activities within the community must be considered in the project scheduling to provide the most effective and least impacting effort. The following dates are provided for information and shall be referred to when planning work and lane restrictions:
Christmas Retail Season .......................................................... Thanksgiving Day to Jan 1st
Gem and Mineral Show ....................................................................... Late Jan to Mid Feb.
Pima County Fair .................................................................................................. Late April
Tucson Water Department Restrictions ............................................... April 1st to Sept. 30th
SWG Construction Restrictions .................................................... October 1st to March 30th
TEP Construction Restrictions ........................................................... May 1st to August 30th
School Session ................................................................................... Late July to Late May
The contractor shall factor these events into his construction schedule. The contractor may do incidental work during these restrictions to complete areas that are not specifically described herein if no additional impacts to commuters, businesses, and residents are imposed and the work is previously approved by the Engineer.
Due to the nature and location of this project, it will be necessary to provide accurate information regarding construction activities on a consistent and regular basis. Business owners, nearby residents and commuters traveling through the area will rely upon accurate construction activity information to maintain their daily business. Since construction activities have such a significant impact upon these operations, the following requirement is set forth:
- The contractor shall provide the Engineer with a written, detailed work schedule at each weekly construction meeting.
- Minutes to the meeting shall be taken by the contractor.
- A copy of each week’s minutes shall be provided to the Engineer and affected individuals attending each meeting.
- The schedule shall document the anticipated construction activities for the upcoming, two-week look ahead period.
It is also important that construction activities should be coordinated with the U.S. Post Office
(access for mail delivery services), the City of Tucson Environmental Services Department (access for trash pickup services), and Fire Department and Police Department (access for emergency services). There will be no separate measurement and payment to the contractor in assisting these agencies with the service they provide to the affected parcels along all streets, as shown on the plans, during construction. Such cost will be included in the overall cost of the project.
Access into and out of residential driveways shall always be maintained during construction. If these conditions cannot be met due to actual work occurring at the driveway, the contractor shall provide a means of pedestrian ingress and egress at no cost to the City; driveway closure shall not exceed thirty-six (36) hours at any one time. The contractor is required to give notice to the affected parcel regarding the status of the driveway prior to the work commencing and provide a written schedule as to when the work is scheduled to be completed.
SP-11 of 124
Work requiring lane restrictions beyond the minimum stated herein shall be done at night unless approved by the Engineer.
The intent of this project is to complete the work as quickly as possible to minimize any inconvenience to the traveling public, or adjacent stakeholders. To that end, the contractor is strongly encouraged to consider working weekends, double shifts, or as often as necessary to complete the work by the specific milestones. Lost time due to little or no work being performed shall not be considered when applying for a contract time extension.
B. Construction Sequencing
The contractor shall account for construction sequencing and work hour restrictions when scheduling and prosecuting the work as described in Subsection 108-4 of these Special Provisions.
All decisions regarding construction sequencing and work hour restrictions shall be made upon meeting the project objectives. Any alternate construction sequencing plan proposed by the contractor must meet the requirements specified in the notes of the construction sequencing sheets of the project plans, the PAG Standard Specifications for Public Improvements (latest edition), and these Special Provisions.
The contractor’s attention is drawn to the construction sequencing sheets included in the project plans and Subsection 108-4 of these Special Provisions. The sequencing plan depicted is intended to provide just one approach to constructing the major features of the project. Upon consideration and approval by the City of Tucson Department of Transportation & Mobility (DTM), the contractor is free to propose and follow his/her own sequencing approach of the roadway, drainage and construction features execution timeline. Alternative sequencing options will be considered based on approval by the Engineer.
3. Contract Time
Once the contract has been awarded and signed, the contractor shall be issued a Notice to Proceed
(NTP). This will begin Phase 1 of the project, the construction phase, and the contractor shall have
150 calendar days to complete this work as shown on the project plans and specified herein.
Phase 2 of the contract shall encompass the 12-month (365 consecutive calendar days) Landscape
Establishment period as detailed in Section 807 of the PAG Standard Specifications. All other items of work shall be completed and accepted (via acceptance of the roadway and/or drainage phase of the work) by the Engineering Representative prior to the commencement of Phase 2. The contractor shall obtain the acceptance of the previous phase(s) following a Final Inspection of that phase. If the Final Inspection should reveal work that is not completed or is unacceptable to the
Engineer for any reason, a "punch list" of these items shall be generated and provided to the contractor. Substantial completion (for the purpose of stopping the contract time) will be granted in accordance with Section 105-21 of the Standard Specifications. Once substantial completion is granted, the contractor shall actively work to achieve final acceptance of the construction phase of the contract within 15-calendar days from the substantial completion date of that phase. Failure to prosecute the remaining work within this time period will result in the resumption of time
SP-12 of 124 charges and the application of liquidated damages from the date scheduled for final acceptance.
When the work on this list has been satisfactorily completed, final acceptance of the phase(s) shall be given for all items of work other than Landscape Establishment. At this time the Landscape
Establishment period shall begin, and the monies retained for all items of work other than
Landscape Establishment (ITEM 8070001) shall be released. Through the duration of the
Landscape Establishment period, the Agency shall retain 10% of the cost of the aforementioned items of work or a minimum of $2,000.00, whichever is greater. (The amount retained for ITEM
8070001 shall not exceed 5% of the total contract bid amount). Upon completion of the Landscape
Establishment period, a final inspection will be held with Engineering and Streets Division staff to ensure that all plants are healthy and acceptable.
4. Maintenance & Protection of Traffic
The contractor shall be responsible for all construction zone traffic control and shall provide a traffic control plan in accordance with Section 701 of the Standard Specifications and these Special
Provisions and shall be approved by the Engineer prior to construction.
The traffic control plans shall meet the conditions and requirements described in Subsection 104-
5 of these Special Provisions.
The contractor shall not allow any work to commence unless the conditions and requirements of Subsection 104-5 Maintenance of Traffic are adhered to. If the contractor fails to abide by the conditions and requirements of this specification section, it shall be considered sufficient grounds for the City to suspend the contractor’s work.
5. Permits
Before undertaking any of this contract work at any location covered by this project, the contractor shall obtain all applicable business licenses and permits, including but not limited to: water quality permits, air quality permits, traffic control and street closure permits, excavation/construction in the public rights-of-way permits, storm water pollution prevention plan, and any other permits required by ordinance and/or state and federal law.
The contractor shall be pay for all necessary fees, taxes and other costs associated with obtaining and securing all permits, including plan review. The costs associated with obtaining permits shall be considered incidental and inclusive with the associated items of work. No additional compensation will be provided.
Excavation permits for excavation/construction in the public rights-of-way will not be required when the work is administered by the Agency.
No separate payment shall be made for preparation of the traffic control plans, and the costs shall be included in the overall cost of the project. The overall cost shall also include applicable plan review and permit fees.
SP-13 of 124
Prior to any ground disturbing activity, the contractor shall obtain an Activity Permit from the
Pima County Department of Environmental Quality. The contractor shall implement the standard specifications for dust suppression.
The contractor will be required to relocate certain water distribution facilities owned by Tucson
Water and modify certain sanitary sewer system facilities owned by Pima County Regional
Wastewater Reclamation Department (PCRWRD) as shown on the plans and hereinafter specified. The contractor shall obtain all construction permits required for this work. During construction operations, all contact between the contractor and Tucson Water or PCRWRD personnel will be through the Engineer. The contractor shall give all notices to the Engineer two
(2) working days in advance of the notice periods required by Tucson Water and PCRWRD.
6. Storm Water/Ground Water Management
It shall be the responsibility of the contractor to allow for any subsurface groundwater and storm water runoff during the time of project construction. The contractor shall not divert or impound water in such a manner as to flood adjacent homes, facilities, or roadways. No additional compensation shall be provided for dewatering or diversion structures required for constructing or protecting the work, the cost being considered incidental to the project.
Dewatering may be done by the contractor by permit only. No measurement or direct payment will be made for dewatering groundwater or channelizing surface water required during the course of construction, including all permits. A contractor’s licensed well driller is required for conducting any dewatering operation, and all costs for dewatering shall be considered incidental to the contract unit cost of the bid items requiring dewatering. The contractor shall apply to the Arizona
Department of Water Resources for the Dewatering Permit in a timely manner. The contractor shall note that up to approximately 90 days may be required for the approval of the Dewatering
Permit.
The contractor’s attention is also directed to Section 810 of these Special Provisions and the
Stormwater Pollution Prevention Plan for the project regarding the requirements for temporary and permanent erosion control.
7. Construction Survey and Layout
Construction survey and layout will be provided by the City of Tucson.
8. Existing Vegetation
Clearing limits must be approved in advance by the Engineer. Grading and construction near and around vegetation that is to be preserved-in-place may be required. The Engineer may require that specific vegetation remain within the construction limits in addition to what is shown in the project plans. The contractor and the Engineer shall tour the project site prior to any construction beginning and together verify what specific vegetation shall be preserved in place.
SP-14 of 124
The contractor shall prune existing trees to remain in place and provide fencing as described in
Sections 201 and 806 of these Special Provisions or as directed by the City Landscape Architect.
Existing project vegetation on this project shall not be disturbed by the contractor beyond those limits actually needed for the contractor’s construction purposes. Those items unnecessarily damaged by the contractor shall be repaired or replaced at the contractor’s expense.
9. Disposal of Materials
All construction debris, rubble, excess, surplus and unsuitable materials structures and obstructions, except as hereafter specified, shall be removed from the job site and disposed of by the contractor at a site previously secured by the contractor, and done in a manner approved by the
Engineer.
Disposal shall be the responsibility of the contractor. However, the contractor shall, with each and every disposal site arranged for (other than commercial waste sites), provide the Engineer with a copy of the written approval of the property owner indicating that the property owner is fully aware of what the material consists. The contractor shall also provide a letter to the Engineer from the
City or County (whichever has jurisdiction), giving site approval for materials disposal at each site to be used. The approval letter shall be received and approved by the Engineer prior to the disposal of any materials at any site.
Costs associated with the disposal of these materials shall be incidental to the related items of work. Fees associated with the disposal of these materials shall be paid by the contractor.
All material removals shall be transported and legally disposed of from the project site the same day they are removed. Stockpiling of removed materials within the public rights-of-way shall not be allowed unless previously approved and directed by the Engineer. The location of the disposal site shall be the responsibility of the contractor and the contractor shall identify in writing the quantity of materials removed and disposed of to that location.
Upon removal, existing material, including existing guardrail, anchors, breakaway cable terminals, posts, and hardware, shall become the property of the contractor unless otherwise specified in the project plans, or in these Special Provisions, or by the Engineer.
Upon removal, disposal of the existing asphaltic concrete shall be the responsibility of the contractor. When approved by the Engineer, the contractor may stockpile and use it as recycled asphaltic concrete or dispose of it at an approved site. No measurement or direct payment will be made for disposal. The cost of disposing the removed AC pavement shall be incidental and considered as included in the cost of contract items.
If in good condition as determined and approved by the Engineer, removal of existing fence and gate material along the project limits may be salvaged and used for reconstruction of fence and gates at necessary locations.
SP-15 of 124
10. Contract Administration
Prior to submittal of contract administration documents, examples of which are listed below, the contractor shall review all documentation for accuracy and compliance with the contract. Any variance from the plans and specifications shall be clearly noted and is subject to approval by the
Engineer. A contractor’s transmittal letter shall accompany all submittals and shall include certification as to accuracy and compliance with the plans and specifications.
Contract administration submittals shall include, but are not limited to, the following examples:
escrow agreements; subcontracts; purchase orders; certified payrolls for contractor and subcontractors; force account billings; equal employment opportunity reports for contractor and subcontractors; trainee preconstruction information; proof of apprenticeship; weekly individual training reports; rental equipment invoices; material invoices showing all unit prices; pay estimates; affidavit of certification of payments to small business enterprise firms; requested lien releases; and consent from surety.
Monthly meetings may be scheduled with the contractor at the discretion of the Engineer to discuss and resolve any problems associated with contract administration submittals. The monthly meetings shall be held at a location agreed upon between the Agency and the contractor. Meetings shall continue on an accelerated basis after project construction completion until all contract administration issues are resolved.
Submittals that are not certified, or are incomplete, will be returned to the contractor unprocessed for proper resubmittal and may result in payment delays, or partial payment, as deemed appropriate by the Engineer.
11. Work Hours/Noise Abatement Ordinance
The Contractor shall adhere to the requirements of the City of Tucson Noise Ordinance No. 6593
(Section 16-31) with respect to hours of construction activity.
Construction noise abatement and start/stop times shall be in accordance with the Arizona
Department of Transportation Standard Specifications for Road and Bridge Construction, Section
104.08 (2008 Edition), and the City of Tucson Code 16-31(b)(5) which prohibits construction noise between the hours of 8:00 p.m. through sunrise, Mondays through Saturdays, and at any time on Sundays and legal holidays.
12. Shoring and Bracing
All contractor construction shall be conducted in conformance with the details shown on the project plans and these Special Provisions, with appropriate soil stabilization and bracing measures as previously approved by the Engineer. No measurement or direct payment will be made for
SP-16 of 124 shoring and/or bracing, unless shown as a line item(s) in the bidding schedule. Contractor shoring and/or bracing is considered incidental to the cost of the other bid items.
Appropriate soil stabilization and bracing measures as previously approved by the Engineer for the protection of utilities and private facilities shall be implemented by the contractor. No measurement or direct payment will be made for contractor soil stabilization and bracing measures, it will be considered incidental to the cost of the project.
13. Archeological Features
If human remains, including human skeletal remains, cremations, and/or ceremonial objects and funerary objects are found during excavation or any activity related to construction in any part of the project area, ground disturbing activities must cease in the immediate vicinity of the discovery.
Should artifacts or human remains be uncovered, the area will be taped off and the City of Tucson
Engineer notified. The City of Tucson Engineer will immediately contact the City of Tucson
Historic Preservation Department (520.837.6968) and arrange for the proper treatment of those resources. State laws ARS 41-865 and ARS 41-844 require that the Arizona State Museum (520-
621-4795) be notified of the discovery by the contractor so that cultural groups who claim cultural or religious affinity to them can make appropriate arrangements for the repatriation and reburial of the remains. The human remains will be removed from the site by a professional archaeologist pending consultation and review by the Arizona State Museum and the concerned cultural groups.
The work is subject to delay in that location pursuant to ARS 41-844 while an examination takes place.
14. Hazardous Materials
If suspected hazardous materials are encountered during construction, work shall cease at the location and the Engineer shall be notified immediately to arrange for proper assessment, treatment, or disposal of those materials. The area will be taped off, and further investigation and clean up by the City of Tucson will follow. No adjustments will made due to work shut down. If potentially hazardous or contaminated materials are encountered, the contractor shall stop work and remove all workers within the contaminated area. For life threatening situations, follow the procedures in the Safety Plan, as specified in Subsection 107-7.02.
15. Contractor’s Staging or Storage Yard
No contractor’s staging area or storage yard has been identified for this project. The contractor shall stage within the existing right-of-way, on a paved surface, owned by the City of Tucson. The contractor shall coordinate with the City of Tucson representatives to determine the most appropriate locations available and it is the responsibility of the contractor to obtain all applicable and necessary permits for all staging areas or storage yards. The contractor’s cost of the construction yard is considered incidental to the project. The contractor shall provide and maintain temporary fencing around the equipment yard and field office for the duration of the contract; the cost being incidental and considered as included in the cost of contract items.
SP-17 of 124
The contractor shall coordinate with the City of Tucson representatives to determine the most appropriate locations available and it is the responsibility of the contractor to obtain all applicable and necessary permits for all staging areas or storage yards. The contractor’s cost of the construction yard is considered incidental to the project. The contractor shall provide and maintain temporary fencing around the equipment yard and field office for the duration of the contract; the cost being incidental and considered as included in the cost of contract items.
The use of private property for contractor construction yards will be allowed only if zoning requirements allows its use for this purpose.
The contractor shall identify his/her equipment, materials storage/stockpiling and contractor/Sub-
Contractor parking. The contractor shall provide the Engineer with a copy of the written approval of the property owner indicating that the property owner is fully aware and agreeable to said equipment, materials storage/stockpiling and contractor/Sub-Contractor parking. This contractor written approval shall to be provided to the Engineer by the contractor prior to commencement of any work.
16. Construction Water/Dust Control
The contractor shall provide potable water for use in construction, compaction and dust control.
Reclaimed water may only be used if there is no discharge of this water to surface waters of the
U.S. and the reclaimed water remains on-site. The contractor shall notify the Arizona Department of Environmental Quality (ADEQ) for all discharges of reclaimed water to surface waters of the
U.S. or off-site.
Fugitive dust generated from construction activities will be controlled in accordance with the Pima
County Department of Environmental Quality (PCDEQ) requirements.
For milling activities, the roadway surface preceding the milling machine shall be kept sufficiently wet so as to prevent the generation of any visible fugitive dust particles, but not so wet as to cause excess runoff from the roadway surface onto the roadway shoulder.
17. Utility Relocation
Utility relocation work both shown and not shown on the project plans or noted in these Special
Provisions will be the responsibility of the appropriate utility. All efforts have been made to avoid utility conflicts and assure as much of the utility work as possible was completed prior to the start of this project. If any relocation work is necessary due to additional conflicts, the utility companies will perform the relocation work during the project construction phases unless otherwise noted on the project plans. The contractor is hereby notified that the utility companies, in conjunction with the contract work, will perform their own utility relocation work. The contractor shall make every effort to cooperate fully with each utility company and acknowledges and agrees that delays to his operations may necessarily occur. Due to these delays that are anticipated by the utility companies, the Engineer will consider requests by the contractor for contract time extensions if necessary. The
SP-18 of 124 contractor will also acknowledge and agree that no monetary compensation will be given to the contractor by the Agency as a result of the impacts on the construction operations that are caused by the utility companies due to their anticipated work or delay. The contractor is also referred to
Section 105-6 of the Standard Specifications, Cooperation With Utility Companies.
The contractor shall consider the extent of utility work in preparing the contract bid and project schedule. It will be the contractor’s responsibility, prior to bidding, to contact the appropriate utilities to obtain additional information such as relocation record drawings and/or as-builts, relocation sequencing, utility windows, construction time frames, and identification of areas requiring subgrade preparation by the contractor prior to the start of utility work.
At least two (2) working days prior to commencing excavation, the contractor shall call the Blue
Stake Center, between the hours of 7:00 a.m. and 4:30 p.m., Monday through Friday for information relative to the location of buried utilities. The number to call is: Tucson and Pima
County 1-800-STAKE-IT.
It shall be the responsibility of the contractor to contact the utility companies in order for them to determine if there is a need for any overhead protection, bracing or shoring necessary during the construction of this project. If overhead protection, bracing or shoring is necessary, the contractor shall conduct this work to the satisfaction of the utility. No measurement or direct payment will be made for overhead protection, bracing or shoring, the cost being considered as incidental.
It shall be the responsibility of the contractor to verify and locate all existing overhead and underground utilities whether shown on the plans or not. The contractor is advised that the placement of a utility on the project plans is in no way meant to indicate its exact location. Utility locations shown on the plans are approximate, and all utilities located within the project limits may not necessarily be shown. The absence of a utility from the plans does not necessarily indicate that it is not present.
The possibility of conflicts with existing utilities-in-service always exists. If conflicting utilities interfere with the normal progress of the contractor towards completion of this project, the
Engineer may, with the prior written approval of the owner of the utility to be relocated, authorize the contractor to relocate said conflicting utilities by Force Account (see Section 515 of these
Special Provisions).
The contractor shall take full responsibility of costs incurred due to damage to utilities as a result of construction, grading or excavation operations. If any utilities are damaged, the contractor shall repair or replace the damaged utility at his sole expense.
The contractor shall coordinate with affected utilities, so the utilities can notify affected customers of service interruptions. All utility relocations that were deemed necessary and were already known to have been in conflict with the project improvements have been completed. The contractor is also referred to Section 107-21 of these special provisions for more specific details.
SP-19 of 124
All discarded matter (including but not limited to trash, garbage, oil drums, fuel, ashes, equipment, concrete, and chemicals) that is generated by contractor construction activities shall be removed or disposed on a daily basis according to state and federal regulations. Contractor’s construction areas shall be maintained in a sanitary condition at all times.
Storage areas for petroleum products and other chemicals used by the contractor shall be located or protected in such a manner that any spills will not enter stream channels or impact groundwater.
18. Erosion Control Measures
The contractor’s attention is directed to the requirements of Section 810 of the specifications for detailed discussion of erosion control measures.
The contractor shall phase or sequence construction activities to minimize the area of disturbance at any one time. Sediment and erosion control measures shall be installed before upgradient land is disturbed. Once an area of the project has been cleared, the contractor is responsible for documenting in the SWPPP book all erosion control measure activities by the contractor or others in the area that has been cleared.
Once the project reaches final stabilization, the contractor shall remove, dispose or realign temporary erosion control measures as directed by the Engineer. Subsequent removal, disposal or realignment of temporary erosion control measures will be incidental to the respective work item and no additional payment will be made.
19. Record Drawings
The contractor is responsible for keeping a set of record project pans on site for the annotation of changes in detail, location, and depth of all items constructed which vary from the contract documents that are made during the construction. The record project plans shall include any revised or added plan sheets. The cost of furnishing record drawings shall be considered as included in the overall cost of the project.
Upon completion of the work, the contractor shall transfer the annotated information to a clean set of the project plans. The dimensions and notations provided on the record project plans shall be complete, clear, and legible. No later than 60 calendar days after acceptance of the project or as directed by the Engineer, the contractor shall submit the dated record set of project plans along with a transmittal letter to the Engineer for review and acceptance. Final retention shall not be released until the record project plans are accepted by the Engineer. The contractor’s failure to furnish this item may delay the contract close-out.
20. Saw Cutting
The contractor’s work shall consist of saw cutting and/or wheel cutting the existing pavement where new asphaltic concrete (AC) and Portland cement concrete pavement (PCCP) is to match existing pavement surfaces. The contractor’s work shall also include saw cutting and/or wheel
SP-20 of 124 cutting existing Portland cement driveways, sidewalks, and curbs where new construction shall match the grade of these existing surfaces. Saw cuts shall be made to a minimum depth of 1½ inches and in all cases, deep enough to insure a neat vertical joint. Portland cement concrete that is damaged by the contractor’s saw cutting shall be replaced in kind at the contractor’s expense.
No measurement or direct payment will be made for saw cutting and/or wheel cutting, the cost being considered as included in the price of other contract items.
21. Proposition 407 Construction Signs
Two Proposition 407 signs shall be required to be installed at the beginning limits of each project segment prior to the start of work. Signs shall be provided by TDTM; however, it is the
Contractor’s responsibility to pick them up at the City’s storage yard, maintain the signs, and relocate them to each project segment. The Contractor shall be responsible for replacing any damaged or lost signs at no cost to the Department. There shall be no payment for the installation and removal of these signs. The Contractor shall deliver the signs back to the City upon Final
Acceptance of the contract. The work associated (including the time to pick-up, maintenance, relocate to each project segment, and return the signs to the City) shall be incidental to the cost of the work. Sign stands for these signs shall be reimbursed under Item 7010006.
22. Miscellaneous Removal, Relocation, and/or Salvage Work
The contractor shall remove, relocate and/or salvage, as directed by the Engineer, all mailboxes, fences, gates, signs, posts, pipes, etc., within the right-of-way and construction easement areas.
The cost of this work shall be considered as incidental to ITEM 2020001 - REMOVAL OF
STRUCTURES & OBSTRUCTIONS, except when the bidding schedule contains specific items on a unit basis.
All materials identified on the plans to be salvaged as part of this project shall be delivered to a location as directed by the Engineer.
Signs and posts shall be removed and salvaged by the contractor in accordance with the signing plans and these Special Provisions. Signs and posts shall be delivered by the contractor to the Sign
Shop, 4004 S. Park Avenue, Building 6 (west end). The contractor shall coordinate the delivery of signs and posts with April Ormsby, 520-837-6814.
The contractor shall be responsible for loading and unloading all salvaged materials at the location specified. No measurement of direct payment will be made for this work, the cost being considered as included in the price of contract items.
23. Survey Monuments
Prior to removing any existing survey monuments, the contractor shall obtain approval from the
Engineer. The decision whether to preserve or replace a monument will be based on the condition of the monument and whether it is in direct conflict with construction. If a monument is removed or damaged by the contractor without authorization from the Engineer, the contractor shall be
SP-21 of 124 responsible for the cost to replace the monument. There will be no measurement or direct payment made for this coordination effort, the cost being incidental to the project cost.
24. Material Sources
No Agency designated materials source has been identified for use on this project. Contractor material sources shall be as specified in Section 1001 of the Standard Specifications.
25. Public Relations
Public relation services required for this project above and beyond what is specified in the Standard
Specifications will be provided by the City of Tucson. The contractor shall work with the City of
Tucson and its Public Relations firm for the duration of the contract to provide accurate and specific project schedule information needed to be communicated to the public.
This includes details of, but not limited to: lane restrictions, driveway and access closures, lane travel switches, detours, emergency closures, temporary closures, mailbox locations, postal delivery, trash collection, newspaper delivery, and for all other services.
Communication to the stakeholders will be conducted in several ways. Contractor resident notifications shall advise of temporary work affecting access and/or utility service with start and end dates. Message boards shall be used by the contractor to advise the traveling public of changes to the work zone. The contractor shall provide variable message boards at each entrance of the project work zone a minimum of seven (7) working days prior to starting work indicating the start of a different construction phase where travel times are affected or as directed by the Engineer.
The contractor shall participate in a “Construction Public Meeting” prior to the start of construction. Meeting date is to be set by the City of Tucson. The contractor shall, no later than seven (7) days prior to start of construction, distribute to all residents and businesses abutting the project rights-of-way notices informing them of the intent by the City of Tucson to begin construction of this project. Such notices shall be furnished to the contractor by the office of the
City Engineer. Notices are not to be placed in mailboxes. Where there is no response or there is no answer at the door, the notice is to be left in the door/screen door. There shall be no separate pay item for the cost of the construction public meeting or notification letters. Cost shall be included as part of the overall job.
26. Curb Ramps
All curb ramp and sidewalk work must comply with the PROWAG Accessibility Guidelines for
Pedestrian Facilities in the Public Right-of-Way Final Rule and be supervised by a licensed
Arizona Concrete (CR-9) contractor.
SP-22 of 124
SECTION 101 - ABBREVIATIONS AND DEFINITIONS
101-3 Terms: of the Standard Specifications is modified to add:
Major Items - A major item is an item whose total cost, determined by multiplying the bidding schedule quantity and the contract unit price, is equal to or greater than the amount indicated below.
A major item will remain a major item unless it is completely eliminated.
When the original total and including:
contract amount is from A major item shall be equal to or greater than the following amount:
o r
$ 0.00 $ 100,000 $ 5,000
100,001 200,000 10,000
200,001 450,000 15,000
450,001 750,000 25,000
750,001 1,100,000 35,000
1,110,001 1,500,000 45,000
1,500,001 2,000,000 55,000
2,000,001 2,500,000 65,000
2,500,001 3,000,000 75,000
3,000,001 5,000,000 85,000
5,000,001 7,000,000 120,000
7,000,001 10,000,000 150,000
10,000,001 25,000,000 250,000
25,000,001 50,000,000 350,000 over 50,000,000 500,000
Minor Item - A minor item is any item which is not a major item.
SECTION 102 – BIDDING REQUIRMENTS AND CONDITIONS
102-4 CONTENTS OF BID DOCUMENT: the second paragraph of the Standard
Specifications is modified to add:
It is the contractor’s responsibility to include and execute all necessary bid forms.
SP-23 of 124
SECTION 103 - AWARD AND EXECUTION OF CONTRACT
103-6 CONTRACTOR’S INSURANCE; INDEMNIFICATION: of the Standard
The contractor shall additionally indemnify and hold harmless the Regional Transportation
Authority (RTA) in Pima County, Arizona, its board, committees, regional partners, officials, officers, and employees, individually and collectively.
SECTION 104 - SCOPE OF WORK
104-2 ALTERATIONS OF CONTRACT
104-2.01 By the Agency: of the Standard Specifications is revised to read:
It is the contractor's obligation to notify the…