About this file

This document is an Infection Control Risk Assessment (ICRA) permit for repair work on elevators at multiple buildings. The project involves medium risk Group 2 construction activities requiring Class III precautions. The contractor must isolate HVAC systems, implement barrier methods, maintain negative air pressure with HEPA filtration, thoroughly clean the work area after completion, and ensure workers receive TB screening if working in negative pressure rooms housing TB patients.

The related federal contract opportunity is solicitation number 520-22-3-7072-0001 from the Department of Veterans Affairs for furnishing all labor, tools, materials, equipment, and supervision to complete project number 520-22-170 involving elevator repairs at multiple buildings in Biloxi, Mississippi.

View the file

Other files

File Type Posted
Bldg 19 - Floor Plan.pdf PDF
Bldg 30 - Crawl Space Piping Area A.pdf PDF
Bldg 17 - Basement Piping.pdf PDF
010000 GENERAL REQUIREMENTS.docx DOCX document
Bldg 2 - Crawlspace Piping.pdf PDF
Bldg 14 - 1st Floor Piping.pdf PDF
096800 CARPET and FLOORING.doc DOC document
260533 - Raceway and Boxes for Electrical Systems.doc DOC document
024100 Demolition.doc DOC document
36C25622R0089 EXHIBIT B R1.docx DOCX document
Bldg 3 - Basement Piping.pdf PDF
262726 WIRING DEVICES.doc DOC document
Bldg 2 - Floor Plan.pdf PDF
013323 Samples and Shop Drawings.doc DOC document
Bldg 25 - Sump Pump-Pit Detail.pdf PDF
Bldg 2 - Crawlspace Piping Original.pdf PDF
VHA Supplemental Contract Requirements for Combatting COVID-19.docx DOCX document
Bldg 53 - Floor Plan.pdf PDF
260511 - Requirements for Electrical Installations.doc DOC document
Bldg 14 - Sump Pump-Pit Detail.pdf PDF
Bldg 15 - Floor Plan.pdf PDF
Bldg 5 - Floor Plan.pdf PDF
36C25622R0089 Solicitation.pdf PDF
Bldg 28 - 1st Floor Piping.pdf PDF
P09 Final SOW 520-22-170 Repair Elevators Multiple Bldgs.docx DOCX document
Bldg 15 - Foundation Piping.pdf PDF
Bldg 1 - Basement Piping Area C.pdf PDF
Bldg 1 - Basement Piping Original.pdf PDF
36C25622R0089 EXHIBIT A R1.docx DOCX document
Bldg 30 - Sump Pump-Pit Detail.pdf PDF
Bldg 53 - Basement Piping.pdf PDF
Bldg 3 and 30 - Floor Plan.pdf PDF
078400 FIRE STOPPING.doc DOC document
Bldg 17 - Floor Plan.pdf PDF
Bldg 1 - Floor Plan.pdf PDF
220511 COMMON PLUMBING WORK RESULTS.doc DOC document
013526 Safety Requirements.doc DOC document
Bldg 30 - Crawl Space Piping Composite.pdf PDF
Bldg 30 - 1st Floor Piping Area A.pdf PDF
Bldg 30 - 1st Floor Piping Area B.pdf PDF
Bldg 1 - Basement Piping Area A-B.pdf PDF
260521 - Low Voltage Conductors and Cables.doc DOC document
Bldg 1 - 1st Floor Piping Area A-B.pdf PDF
Bldg 19 - 1st Floor Piping Original.pdf PDF
079200 JOINT SEALANTS.doc DOC document
Bldg 25 - 1st Floor Piping Area A.pdf PDF
Bldg 28 - Sump Pump-Pit Detail.pdf PDF
Bldg 5 - 1st Floor Piping.pdf PDF
265100 INTERIOR LIGHTING.doc DOC document
Bldg 30 - 1st Floor Piping Composite.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

“CONTRACTING ONLY”

Adapted with permission V Kennedy, B Barnard, St Luke Episcopal Hospital, Houston TX, Forms modified and provided courtesy of Judene Bartley, ECSI Inc Beverly Hills MI 2002 Reviewed 2005 1

Infection Control Construction Permit-ICRA Project Title: Repair Elevators, Multiple Buildings Permit No: 520-22-170 Location of Construction: Multiple Buildings Project Start Date TBD Project Coordinator/COTR: Brandon O’Neal Estimated Duration:

Contractor Performing Work: TBD Permit Expiration Date: TBD Supervisor: TBD Telephone:

YES NO CONSTRUCTION ACTIVITY YES NO INFECTION CONTROL RISK GROUP

TYPE A: Inspection, non-invasive activity GROUP 1: Low Risk TYPE B: Small scale, short duration, moderate to high levels x GROUP 2: Medium Risk x TYPE C: Activity generates moderate to high levels of dust, requires greater 1 work shift for completion

GROUP 3: Medium/High Risk

TYPE D: Major duration and construction activities Requiring consecutive work shifts

GROUP 4: Highest Risk

CLASS I 1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Minor Demolition for Remodeling

CLASS II

1. Provides active means to prevent air-borne dust from dispersing into atmosphere

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents.

5. Wipe surfaces with disinfectant.

6. Contain construction waste before transport in tightly covered containers.

7. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

8. Place dust mat at entrance and exit of work area.

9. Remove or isolate HVAC system in areas where work is being performed.

CLASS III

X

1. Obtain infection control permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

6. Vacuum work with HEPA filtered vacuums.

7. Wet mop with disinfectant

8. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

9. Contain construction waste before transport in

4. Maintain negative air pressure within work site utilizing

HEPA equipped air filtration units.

5. Do not remove barriers from work area until complete project is thoroughly cleaned by Facilities Management Service.

tightly covered containers.

10. Cover transport receptacles or carts. Tape covering.

11. Remove or isolate HVAC system in areas where work is being performed/ Initial

CLASS IV

1. Obtain infection control permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

4. Maintain negative air pressure within work site utilizing

HEPA equipped air filtration units.

5. Seal holes, pipes, conduits, and punctures appropriately.

6. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site.

7. All personnel entering work site are required to wear shoe covers

8. Do not remove barriers from work area until completed project is thoroughly cleaned by the Environmental Service Dept.

9. Vacuum work area with HEPA filtered vacuums.

10. Wet mop with disinfectant.

11. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

12. Contain construction waste before transport in tightly covered containers.

13. Cover transport receptacles or carts. Tape covering.

14. Remove or isolate HVAC system in areas where work is being performed.

Date

Initial

Construction taking place in negative pressure rooms where TB patients are housed or work with exhaust to these rooms? ___Yes X__No If yes, the contractor must provide written certification that all employees assigned to the work site have a negative TB screening within 90 days prior to assignment to work area.

Additional Requirements:

Infection Control: Tanya Chandler COTR:

Safety:

File details come from the government source that posted it. Updated .