About this file

This document contains a solicitation for demolition services related to Project 520-22-170 at the Biloxi, MS Veterans Medical Center. The solicitation seeks bids to furnish all labor, tools, materials, equipment and supervision necessary to perform demolition and removal work of buildings, utilities, structures and debris from trash dumps as specified. Eligible offerors must have the capability to complete demolition and legally dispose of all removed materials in accordance with applicable federal, state and local permits, rules and regulations. The work includes safely demolishing and removing designated outside utility lines and abandoned lines interfering with new construction. Upon completion, the site must be left in a clean condition satisfactory to the Contracting Officer Representative. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.

View the file

Other files

File Type Posted
Bldg 19 - Floor Plan.pdf PDF
Bldg 30 - Crawl Space Piping Area A.pdf PDF
Bldg 17 - Basement Piping.pdf PDF
010000 GENERAL REQUIREMENTS.docx DOCX document
Bldg 2 - Crawlspace Piping.pdf PDF
Bldg 14 - 1st Floor Piping.pdf PDF
096800 CARPET and FLOORING.doc DOC document
260533 - Raceway and Boxes for Electrical Systems.doc DOC document
36C25622R0089 EXHIBIT B R1.docx DOCX document
Bldg 3 - Basement Piping.pdf PDF
262726 WIRING DEVICES.doc DOC document
Bldg 2 - Floor Plan.pdf PDF
013323 Samples and Shop Drawings.doc DOC document
Bldg 25 - Sump Pump-Pit Detail.pdf PDF
Bldg 2 - Crawlspace Piping Original.pdf PDF
VHA Supplemental Contract Requirements for Combatting COVID-19.docx DOCX document
Bldg 53 - Floor Plan.pdf PDF
260511 - Requirements for Electrical Installations.doc DOC document
Bldg 14 - Sump Pump-Pit Detail.pdf PDF
Bldg 15 - Floor Plan.pdf PDF
Bldg 5 - Floor Plan.pdf PDF
36C25622R0089 Solicitation.pdf PDF
Bldg 28 - 1st Floor Piping.pdf PDF
P09 Final SOW 520-22-170 Repair Elevators Multiple Bldgs.docx DOCX document
Bldg 15 - Foundation Piping.pdf PDF
Bldg 1 - Basement Piping Area C.pdf PDF
Bldg 1 - Basement Piping Original.pdf PDF
36C25622R0089 EXHIBIT A R1.docx DOCX document
Bldg 30 - Sump Pump-Pit Detail.pdf PDF
Bldg 53 - Basement Piping.pdf PDF
Bldg 3 and 30 - Floor Plan.pdf PDF
078400 FIRE STOPPING.doc DOC document
Bldg 17 - Floor Plan.pdf PDF
Bldg 1 - Floor Plan.pdf PDF
220511 COMMON PLUMBING WORK RESULTS.doc DOC document
013526 Safety Requirements.doc DOC document
Bldg 30 - Crawl Space Piping Composite.pdf PDF
Bldg 30 - 1st Floor Piping Area A.pdf PDF
Bldg 30 - 1st Floor Piping Area B.pdf PDF
Bldg 1 - Basement Piping Area A-B.pdf PDF
260521 - Low Voltage Conductors and Cables.doc DOC document
Bldg 1 - 1st Floor Piping Area A-B.pdf PDF
Bldg 19 - 1st Floor Piping Original.pdf PDF
079200 JOINT SEALANTS.doc DOC document
Bldg 25 - 1st Floor Piping Area A.pdf PDF
Bldg 28 - Sump Pump-Pit Detail.pdf PDF
Bldg 5 - 1st Floor Piping.pdf PDF
ICRA - Contracting Only.pdf PDF
265100 INTERIOR LIGHTING.doc DOC document
Bldg 30 - 1st Floor Piping Composite.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

520-22-170

Section 024100

DEMOLITION

PART 1 ‑ GENERAL

1.1 DESCRIPTION:

This section specifies demolition and removal of buildings, portions of buildings, utilities, other structures and debris from trash dumps shown.

1.2 RELATED WORK:

A.

Safety Requirements: Section 01010, GENERAL REQUIREMENTS.

B.

Disconnecting utility services prior to demolition: Section 01010, GENERAL REQUIREMENTS.

C.

Reserved items which are to remain the property of the Government: Section 01010, GENERAL REQUIREMENTS.

1.3 PROTECTION:

A.

Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures.

B.

Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations.

C.

Provide enclosed dust chutes with control gates from each floor to carry debris to truck beds or trash dumps and govern flow of material into truck or trash dumps. Provide overhead bridges of tight board or prefabricated metal construction at dust chutes to protect persons and property from falling debris.

D.

Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum.

E.

In addition, to previously listed fire and safety rules to be observed in performance of work, include following:

1.

No wall or part of wall shall be permitted to fall outwardly from structures.

2.

Wherever a cutting torch or other equipment that might cause a fire is used, provide and maintain fire extinguishers nearby ready for immediate use. Instruct all possible users in use of fire extinguishers.

3.

Keep hydrants clear and accessible at all times. Prohibit debris from accumulating within a radius of 4500 mm (15 feet) of fire hydrants.

1.4 UTILITY SERVICES:

A.

Demolish and remove outside utility service lines shown to be removed.

B.

Remove abandoned outside utility lines that would interfere with installation of new utility lines and new construction.

PART 2 - PRODUCTS (Not Used)

PART 3 – EXECUTION

3.1 DEMOLITION:

A.

Completely demolish and remove all appurtenances related or connected thereto, as noted below:

B.

Debris shall become property of Contractor and shall be disposed of by him, off the Medical Center.

C.

Remove and legally dispose of all materials, from trash dumps required. Materials removed shall be disposed of in compliance with applicable federal, state or local permits, rules and/or regulations.

3.2 CLEAN‑UP:

On completion of work of this section and after removal of all debris, leave site in clean condition satisfactory to Contracting Officer Representative. Clean‑up shall include off the Medical Center disposal of all items and materials not required to remain property of the Government as well as all debris and rubbish resulting from demolition operations.

‑ ‑ ‑ E N D ‑ ‑ ‑