I.B.08 Attachment 7 - FRP Small Business Decision Matrix.pdf

PDF 214 KB Posted

Attached to
FRP Pacific Region MATOC Federal contract opportunity
Solicitation number
W912DY20R0034
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This document contains a small business decision matrix and details of a related federal contract opportunity. The small business decision matrix evaluates project complexity, size, and risk factors to determine whether opportunities will be set aside for small businesses or competed unrestricted. Complexity is weighted at 40%, size at 20%, and risk at 40%. Opportunities receiving a combined rating of 5 or below from evaluations of these factors on a 1-10 scale will be considered for small business competition.

The related federal contract opportunity is a multiple award task order contract solicitation from the Department of the Army Corps of Engineers Engineering Support Center Huntsville. Services sought under the contract include demolition, deconstruction, abatement of facility contaminants such as asbestos and lead, environmental assessments, hazardous materials transportation and disposal for small to very large facilities across the Pacific region. Responses to the solicitation are due on the listed date, with awards to be made thereafter. Pricing will be established at the task order level.

View the file

Other files for this federal contract opportunity

Other files attached to FRP Pacific Region MATOC, newest first.
File Type Posted
I.B.08 Attachment 19 - Questions- Dated 9 September 2020.pdf PDF
I.B.08 Attachment 17 - Sample Task Order Attachment B Rev 01 - Dated 9 September 2020.xlsx XLSX spreadsheet
I.B.08 FRP Pacific Region RFP Conform - 11 September 2020.pdf PDF
I.B.08 FRP Pacific Region SYNOPSIS-Amendment 1- W912DY20R0034 - 9 September 2020.pdf PDF
I.B.08 FRP Pacific Region RFP MOD - 11 September 2020.pdf PDF
I.B.08 Attachment 16 - Sample Task Order Rev 01 - Dated 9 September 2020.pdf PDF
I.B.08 Attachment 8 - Monthly Progress Report Format.pdf PDF
I.B.08 Attachment 13 Specification Guide 02220 - Demolition.pdf PDF
I.B.08 FRP Pacific Region RFP W912DY20R0034 - 26 AUG 2020 - FINAL.pdf PDF
I.B.08 Attachment 10 - Accident Prevention Plan Checklist.pdf PDF
I.B.08 Attachment 3 - Experience Reporting Form.pdf PDF
I.B.08 Attachment 14 Specification Guide 02221 - Ex-Back-Site.pdf PDF
I.B.08 Attachment 9 - Work Plans, Sub-Plans, and Appendices.pdf PDF
I.B.08 Attachment 16 - Sample Task Orderr.pdf PDF
I.B.08 FRP Pacific Region SYNOPSIS W912DY20R0034 - 26 AUG 2020 - FINAL.pdf PDF
I.B.08 Attachment 5 - Small Business Participation Commitment.pdf PDF
I.B.08 Attachment 18 - Estimated Quantities.xlsx XLSX spreadsheet
I.B.08 Attachment 4- Past Performance Questionnaire.pdf PDF
I.B.08 Attachment 11 - Safety and Health Program Requirements.pdf PDF
I.B.08 Attachment 1 - Performance Requirements Summary.pdf PDF
I.B.08 Attachment 15 - Descriptive Data for ECPs and REAs.pdf PDF
I.B.08 Attachment 12 - Demolition and Recycling Final Report.pdf PDF
I.B.08 Attachment 2 - Quality Assurance Surveillance Plan.pdf PDF
I.B.08 Attachment 17 - Sample Task Order Attachment B.xlsx XLSX spreadsheet
I.B.08 Attachment 6- Letter of Commitment (Key Subcontractor).pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 7 – Small Business Decision Matrix Project: Example Project

Risk Factors:

Size/Dollar Value:

Multiple Mobilizations, varying site restorations, long duration

$1,581,842

Complexity - 40% Risk - 40%

Examples (or similar complexities) Rank Examples (or similar risk) Rank

337 Development Services 1 Short duration, adequate infrastructure 1

ACM/ORM Assessment

Location, close to large city, airports, easy access to material and personnel

ACM/ORM Assessment + Medical Level 1 Assessment

Short duration without adequate infrastructure

ACM/ORM Assessment + Medical Level 2 Assessment

Long duration with adequate infrastructure

Demolition of simple structures with complete ACM/ORM Assessment already completed

0-6 months fieldwork duration without adequate infrastructure

ACM/ORM Assessment and Demolition of Simple Structures

6-12 months fieldwork Long duration with adequate infrastructure

Demolition of complex structures with complete ACM/ORM Assessment and or Medical Assessment already completed

Over 12 months fieldwork Long duration with adequate infrastructure, multiple mobilizations

ACM/ORM Assessment, Medical Assessment, and Demolition of Complex Structures

Negative publicity, High political visibility, reporting

Demolition of "Hardened" Structures 9 Remote locations with complex logistics 9

Demolition of extremely complex, damaged, and or hazardous, structures

Remote locations with complex logistics

Rank Evaluation

Composite Rank

6.2 Resulting decision is - Unrestricted

Process:

* Requirements will be reviewed to determine if they will be competed as Small Business or Unrestricted

* Complexity (40%), Size (20%), and Risk (40%) will be considered

* Each factor will receive a rating from 1 – 10

* Any requirement that receives a combined factor rating of 5 or below will be considered for competition by Small Business

* After the current year, the PDT may adjust the decision point either up or down

Size - 20%

Examples Rank

< 50k 1

< 100k

< 250k

< 600k

< 750k

< 1M

< 1.5M

< 2M

< 3M 9

>4M