I.B.08 Attachment 2 - Quality Assurance Surveillance Plan.pdf

PDF 226 KB Posted

Attached to
FRP Pacific Region MATOC Federal contract opportunity
Solicitation number
W912DY20R0034
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This document outlines a Quality Assurance Surveillance Plan (QASP) for demolition and abatement services under a Federal Acquisition Regulation-based Multiple Award Task Order Contract (MATOC) solicited by the U.S. Army Corps of Engineers Engineering Support Center Huntsville. The QASP defines performance standards for required services including preparation and submittal of project documents, mobilization and demobilization, and establishes methods for monitoring performance such as inspection of deliverables and work processes. It describes incentives and disincentives tied to contractor performance ratings in areas like on-time delivery and revision requirements. Failure to meet standards may result in actions including work stoppages, withdrawn work, task order or basic contract termination. The related federal contract opportunity provides additional context, soliciting proposals under W912DY20R0034 for small to large facility demolition and abatement services across the Pacific Region, including environmental assessments, regulated materials abatement and disposal, and site restoration.

View the file

Other files for this federal contract opportunity

Other files attached to FRP Pacific Region MATOC, newest first.
File Type Posted
I.B.08 FRP Pacific Region SYNOPSIS-Amendment 1- W912DY20R0034 - 9 September 2020.pdf PDF
I.B.08 FRP Pacific Region RFP MOD - 11 September 2020.pdf PDF
I.B.08 Attachment 16 - Sample Task Order Rev 01 - Dated 9 September 2020.pdf PDF
I.B.08 Attachment 19 - Questions- Dated 9 September 2020.pdf PDF
I.B.08 Attachment 17 - Sample Task Order Attachment B Rev 01 - Dated 9 September 2020.xlsx XLSX spreadsheet
I.B.08 FRP Pacific Region RFP Conform - 11 September 2020.pdf PDF
I.B.08 Attachment 1 - Performance Requirements Summary.pdf PDF
I.B.08 Attachment 15 - Descriptive Data for ECPs and REAs.pdf PDF
I.B.08 Attachment 12 - Demolition and Recycling Final Report.pdf PDF
I.B.08 Attachment 17 - Sample Task Order Attachment B.xlsx XLSX spreadsheet
I.B.08 Attachment 6- Letter of Commitment (Key Subcontractor).pdf PDF
I.B.08 Attachment 8 - Monthly Progress Report Format.pdf PDF
I.B.08 Attachment 16 - Sample Task Orderr.pdf PDF
I.B.08 FRP Pacific Region SYNOPSIS W912DY20R0034 - 26 AUG 2020 - FINAL.pdf PDF
I.B.08 Attachment 7 - FRP Small Business Decision Matrix.pdf PDF
I.B.08 Attachment 5 - Small Business Participation Commitment.pdf PDF
I.B.08 Attachment 18 - Estimated Quantities.xlsx XLSX spreadsheet
I.B.08 Attachment 4- Past Performance Questionnaire.pdf PDF
I.B.08 Attachment 11 - Safety and Health Program Requirements.pdf PDF
I.B.08 Attachment 13 Specification Guide 02220 - Demolition.pdf PDF
I.B.08 FRP Pacific Region RFP W912DY20R0034 - 26 AUG 2020 - FINAL.pdf PDF
I.B.08 Attachment 10 - Accident Prevention Plan Checklist.pdf PDF
I.B.08 Attachment 3 - Experience Reporting Form.pdf PDF
I.B.08 Attachment 14 Specification Guide 02221 - Ex-Back-Site.pdf PDF
I.B.08 Attachment 9 - Work Plans, Sub-Plans, and Appendices.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2 – Quality Assurance Surveillance Plan

1. Performance Requirements Summary

The table on the following page lists the PWS requirements/deliverables that the Government shall monitor. The absence of any contract requirement from the PRS/QASP must not detract from its enforceability nor limit the rights or remedies of the Government under any other provision of the contract, including the clauses entitled “Inspection of Services” and “Default.” The table defines the standard for each listed PWS service, cites the respective specification, provides the method of surveillance, and describes disincentives for not meeting acceptable standards.

2. Government Quality Assurance

The Contracting Officer (CO) has overall responsibility for overseeing the Contractor’s performance. The CO shall monitor day-to-day contract compliance and administration. The

COR shall assist the CO with their duties and is responsible of technical administration of the project. The COR also assures proper Government surveillance of the Contractor’s performance and shall monitor, record, and report on the technical performance of the Contractor on a day-today basis. The COR, along with USACE subject matter experts, shall assure the Contractor is meeting contract PWS standards, as well as all Federal, state, and local regulatory requirements.

The Government intends to use the following methods to monitor standards:

Inspection and review of all required documents and submittals.

Periodic inspection of work processes or output.

100% inspection at the completion of key work segments and deliverables.

Customer feedback.

3. Performance Evaluation

The Government shall evaluate Contractor performance to determine if its performance meets the requirements of the contract. The COR shall evaluate and report Contractor performance to the

Contracting Officer at each milestone and delivery per the project schedule. Contractor shall submit progress inspection reports as required. When the performance requirement is not met, the

Contracting Officer shall issue a contract discrepancy report (CDR) to the Contractor. The

Contractor must respond to the CDR and return it to the contracting officer within five (5) calendar days of receipt. Failure to meet acceptable performance standards may result in one or all of the following actions:

Temporary work stoppage awaiting corrective action.

Withdrawal of work

Terminate the task order.

Terminate the MATOC (basic) contract.

Required Service Paragraph

Number

Standard Method of

Surveillance

Incentive/Disincentive

Preparation and submittal of required project documents, forms, permit requests, and notifications.

6.5 Contractor shall

submit 90% of reports on time, with less than

10% requiring more than one revision.

100% inspection

CPARS Rating:

Exceptional = 100% of reports on time requiring zero revisions.

Unsatisfactory = less than 80% of reports on time and/or more that

20% requiring more than two revisions.

Submittals that do not meet acceptable performance standards may be rejected in whole or in part.

Contractor must resolve and correct deficiencies in reasonable time or will be subject to issuance of show cause and possible termination

Mobilization/demobil ization and work site setup, to include protection of personnel, xxx, land, and water resources.

6.5.3 Accomplish 90%

of mobilization/de mobilization tasks within timeframe allotted in project schedule

Periodic progress inspection

CPARS Rating:

Exceptional = 100% of project milestones completed by

Contractor within project milestone schedule.

Unsatisfactory = less than <80% of project milestones completed by Contractor within project milestone schedule.

Failure to perform work according to project execution schedule could result in assessment of liquidated damages for schedule delays, and may result in the issuance of show cause and/or possible contract termination.

Removal, capping, rerouting of all affected utilities

6.5.5 Meets site-

specific utility owner standard

Periodic progress inspection

Failure to correctly perform this service may disrupt installation utility services and negatively impact operations. Such an incident could result in assessment of liquidated damages for outages, and may result in the issuance of show cause and/or possible contract termination.

Abatement of

ACM/ORM

6.5.6, 6.5.7 No exceptions to reported

ACM/ORM

removal

100% inspection

Failure to perform this service in compliance with Federal, State, and local environmental, health, and safety regulations, will result in a less than satisfactory CPARS rating and/or a stop work order. Contractor must resolve and correct deficiencies in reasonable time or will be subject to issuance of show cause and possible termination for cause.

Demolition performed in accordance with accepted work plan

6.5.9 100% work required by PWS

100% inspection

Failure to perform this service in compliance with Federal, State, and local environmental, health, and safety regulations, will result in a less than satisfactory CPARS rating and/or a stop work order. Contractor must resolve and correct deficiencies in reasonable time or will be subject to issuance of show cause and possible termination for cause.

Debris disposal, diversion, and recycling

6.5.10 Meets material

handling and disposal requirements based on waste stream characterization

Periodic progress inspection

Failure to perform this service in compliance with Federal, State, and local environmental, health, and safety regulations, will result in a less than satisfactory CPARS rating and/or a stop work order. Contractor must resolve and correct deficiencies in reasonable time or will be subject to issuance of show cause and possible termination for cause.

Site Restoration 6.5.11 Meets requirements of

PWS and

SWPPP.

100% inspection

Failure to perform this service in compliance with Federal, State, and local environmental, health, and safety regulations, will result in a less than satisfactory CPARS rating and/or a stop work order. Contractor must resolve and correct deficiencies in reasonable time or will be subject to issuance of show cause and possible termination for cause.

Recurring

Deliverables/Submitt als

(daily/weekly/monthl y)

6.5.12 Contractor shall

submit 90% of reports on time, with less than

10% requiring more than one revision.

100% inspection

CPARS Rating:

Exceptional = 100% of reports on time requiring zero revisions.

Unsatisfactory = less than 80% of reports on time and/or more that

20% requiring more than two revisions.

Submittals that do not meet acceptable performance standards may be rejected in whole or in part.

Contractor must resolve and correct deficiencies in reasonable time or will be subject to issuance of show cause and possible termination