Questions and Answers_Gdansk_Round 3.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
S&RTS, Gdansk, Poland
Solicitation number
HTC711-26-R-E135
Issued by

About this file

This is a Questions and Answers log documenting contractor inquiries and government responses for Round 3 of solicitation HTC71126RE135 regarding Stevedoring and Related Terminal Services (S&RTS) at the Port of Gdansk, Poland. The log, updated June 4, 2026, addresses two substantive corrections to the Schedule of Rates document. The first question, received June 2 and answered June 3, corrected the Period of Performance from the initially stated 28 May 2026 through 27 November 2031 to the accurate dates of 28 November 2026 through 27 May 2032, as indicated in the original Statement of Requirements (SOR). The second question, also received June 2 and answered June 3, identified calculation errors in the Schedule of Rates, specifically that Category Total in Cell N31 failed to incorporate Line Items 1-15 and Cell N66 failed to incorporate Line Items 34-42; the government corrected the spreadsheet to include all line items in the respective category totals. Both questions resulted in amendments to the RFQ, with the corrected Schedule of Rates document reissued to all potential bidders.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Round 3

SOLICITATION Q&A LOG

HTC71126RE135 Gdansk S&RTS UPDATED: 04 June 2026

QUESTION #DATE RECEIVEDDATE OF REPLYGOVERNMENT'S RESPONSEAMEND RFQ?
12-Jun-26On the schedule of rates document, the Period of Performance (Excel Line 2) now reflects 28 May 2026 through 27 November 2031. Could you please correct the dates to display 28 November 2026 through 27 May 2032 as indicated in the original SOR?3-Jun-26The schedule of rates has been corrected to incorporate the correct period of performance of 28 Nov 26 - 27 May 2032.Yes
22-Jun-26We respectfully highlight that the Category Total in Cell N31 does not incorporate Line Items 1 – 15. As well, Cell N66 does not incorporate Line Items 34 – 42.3-Jun-26The schedule of rates has been corrected to incorporate all line items in the category totals.Yes