Questions and Answers_Malaysia_as of 19 Feb 26.xlsx
XLSX spreadsheet 15 KB Posted
- Solicitation number
- HTC711-26-Q-E119
About this file
This is a Questions and Answers log for Round 2 of the Stevedoring & Related Terminal Services (S&RTS) solicitation for Ports in Malaysia (HTC711-26-Q-E119). The document contains nine substantive questions and answers received between February 5-18, 2026, addressing operational and logistical requirements for the contract.
Key clarifications include: vessel agents will coordinate port services directly with port authorities, but the contractor is responsible for all cargo-related tariffs while vessel port call costs are excluded; 1,400 square meters of yard space is estimated for staging vehicles; contractors must address all seven designated ports (Penang, Klang, Bintulu, Johor, Kuantan, Labuan, and Tanjung Pelepas) in their proposals; the USG will not reimburse customs duties, taxes, or staging fees; cargo will move under a free time agreement (5-7 days) established between the USG and Malaysian Port Authority; typical Ro-Ro vessels are approximately 200 meters length overall with 21,232 MT deadweight; chartered carriers will appoint their own ship agents; transport frequency depends entirely on mission requirements; detailed cargo specifications including dangerous goods, size/weight ranges, and container certifications will be provided per mission through cargo manifests; facility requirements are 3,000-5,000 square meters for short-term use during operations only, with office space ordered as-needed; no MPL platform or IT integration with TRANSCOM is required. The RFQ submission deadline was extended from February 27, 2026 to March 11, 2026 at 12:00 PM CT to accommodate the Lunar New Year period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Synopsis of Award_Malaysia.pdf | ||
| Malaysia PWS 17 March.docx | DOCX document | |
| Solicitation Amendment HTC71126QE1190004 SF 30.pdf | ||
| Questions and Answers_Malaysia_as of 17 Mar 26.xlsx | XLSX spreadsheet | |
| Solicitation Amendment HTC71126QE1190003 SF 30.pdf | ||
| Solicitation Amendment HTC71126QE1190002 SF 30.pdf | ||
| Attachment 4 - RFQ Information and General Compliance Worksheet_Rev. 4 Feb 2026.xlsx | XLSX spreadsheet | |
| Questions and Answers_Malaysia_as of 4 Feb 26.xlsx | XLSX spreadsheet | |
| Solicitation Amendment HTC71126QE1190001 SF 30.pdf | ||
| Attachment 1 - Performance Work Statement.pdf | ||
| Attachment 2 - Schedule of Rates.xlsx | XLSX spreadsheet | |
| Attachment 4 - RFQ Information and General Compliance Worksheet.xlsx | XLSX spreadsheet | |
| Solicitation - HTC71126QE119.pdf | ||
| Attachment 3 - Mission Essential Plan.docx | DOCX document | |
| Attachment 5 - Technical Worksheet.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Round 2
SOLICITATION Q&A LOG
HTC71126QE119 Ports of Malaysia S&RTS UPDATED: 19 February 2026
| QUESTION # | DATE RECEIVED | PROSPECTIVE VENDOR'S QUESTION | DATE OF REPLY | GOVERNMENT'S RESPONSE | AMEND RFQ? |
| 3 | 5-Feb-26 | 1. | Are there any chartering party (charterers) involved (who are representing the ships' owners)? |
| 2. | Will those charterers engage those ports via separate shipping agents for tugs, pilotage, line-handlers and thence, applicable for Port Dues which are billed separately to the shipping agents assigned by those charterers? | |
| - Merchant Ships owned by private owners and may have charterers involved who engage separate shipping agents for port related charges (tugs, pilotage, line-handlers and Port Dues). | 19-Feb-26 | 1. There will always be an agent representing the vessel (Commercial or U.S Government) |
| 2. Yes. The vessel agents will coordinate directly the port authority for berthing, piloting, and other vessel services. Contractor is responsible for the payment of all tariffs, fees, and duties directly associated with the handling, clearance, and processing of the cargo. The Contractor's financial responsibility excludes costs related to the vessel's port call. Ref - PWS 4.1.2.1 | No | ||
| 4 | 10-Feb-26 | 1. Yard Space Requirements. |
Several ports have requested an estimate of the yard space needed by USTRANSCOM to stage vehicles prior to pickup and delivery. Could you please advise the required yard space (in square feet or square meters) for planning and quotation purposes?
2. Port Coverage Requirements.
For proposal compliance, is it mandatory to provide solutions for all ports listed in the RFP, or may we submit options only for specific ports aligned with our operational capabilities and available yard capacity? 19-Feb-26 1. Based on an analysis of missions conducted over the preceding five years, the estimated requirement to support Department of War (DoW) port clearance operations is 1,400 square meters.
| 2. To be considered for this contract award, the contractor's proposal must address the requirements for all ports specified in the Performance Work Statement (PWS). | No | ||
| 5 | 11-Feb-26 | Import Procedure: |
(a) Who will be (valid) consignee (s) in the B/L?
(b) Who is responsible for customs clearance (transshipment status)?
(c) Please confirm cargo (machines, equipment, materials, etc) be shipped to the port under transshipment status only?
(d) How long will cargo (equipment/ materials, etc) be staying at the port during the transshipment? 19-Feb-26 (a) The valid consignee(s) on the Bill of Lading (B/L) will vary depending on who the cargo is intended for and where it is destined. The consignee(s) should reflect the specific agency, service, or installation responsible for receiving the shipment at its final destination. This could include a single entity or multiple entities, depending on the nature of the cargo and its distribution requirements.
(b) The USG will not pay for or reimburse the Contractor for usage of port staging/storage free time, customs duties, taxes, and similar charges for which no services are received. The USG will only pay for port tariffs where the USG has requested and received services. The Contractor will not include such taxes, duties, customs fee, free time, excise fee/tax, inspection fee, bond, or the like in any of its rates. If the Contractor pays a tax, duty, customs fee, excise fee/tax, inspection fee, bond, or the like for which the USG is exempt, the Contractor is not entitled to reimbursement.
(c) No transshipments
| (d) The USG will move cargo under the FREE TIME agreement (5-7 days) established between the USG and the Malaysian Port Authority. | No | ||
| 6 | 11-Feb-26 | Vessels: |
(a) What are vessel size ranges (DWT, vessel LOA, required draft level, etc)?
(b) Will chartered carriers (RORO /breakbulk) appoint their own ship agents?
(c) We've received US Transcom's approved carrier list. Could you please specify the carriers operating in East Asia trade that'll be transporting to Malaysia (as not all carriers are operating in this area)? 19-Feb-26 (a) Average vessel length Vessel Type: Vehicles Carrier (Ro-Ro) Length Overall (LOA): 199.9 - 200 meters Beam (Width): 32.26 meters Deadweight (DWT): 21,232 MT Gross Tonnage: 57,030
(b) YES
| (c) No, the list provided to you by TRANSCOM includes the vessels authorized to transport USG cargo. Exceptions may occur only in extreme situations where the USG needs to contract an MSC vessel or a foreign-flag carrier. | No | ||
| 7 | 11-Feb-26 | Frequency of Transport: |
| (a) What are frequency of transport as per month or per year for both cargo coming in chartered vessels and liner vessels? | 19-Feb-26 | (a) The frequency of transport is entirely dependent on the mission requirements of the U.S. Government (USG). As such, no definitive frequency can be determined at this time. | No |
| 8 | 11-Feb-26 | Cargo: |
(a) DG cargo, please provide MSDS/ SDS (class/ IMMO/ handling concerns/ port approval on DG concerns)
(b) RORO carrier with requirement for using tugmaster/ tractor, please provide kingpin size ranges
(c) Please provide size ranges of RORO cargo and size & weifght ranges of static cargo on MAFI
(d) LOLO cargo (conventional/ breakbulk), please provide the size & weight ranges of the cargo. Please confirm cargo has proper lifting points for the hoisting purpose
(e) Are all containers SOC (MILVANS, BICON’s, TRICON’s, QUADON’s) ? Please confirm if they are CSC certified?
(f) Please confirm cargo in container are forkliftable (sitting on pallets/ crates c/w forkhole) What would be the heaviest package? 19-Feb-26 (a)All dangerous goods (DG) cargo will be identified, documented, and communicated to all stakeholders prior to execution.
(b)This level of detail will be provided for each mission, based on the cargo manifest, which will be shared prior to execution.
(C)This level of detail will be provided for each mission, based on the cargo manifest, which will be shared prior to execution.
(d) This level of detail will be provided for each mission, based on the cargo manifest, which will be shared prior to execution.
(e) The majority of SOC are CSC certified. Containers that are not CSC certified can be booked as breakbulk cargo under the USC contract.
| (f) This level of detail will be provided for each mission, based on the cargo manifest, which will be shared prior to execution. | No | ||
| 9 | 11-Feb-26 | Required facility area: |
(a) What is the estimated area (m2) for the required facility at each port?
(b) Assume the area is needed throughout the 5-year contract duration? (not temporary setup each time, to clarify short-term/ long term rental needs)
(c) Is the office required for 4 months / in each location / as per year ? 19-Feb-26 (a) Between 3,000 to 5,000 square meters will be required, with the understanding that the space needed may vary by mission depending on cargo volumes.
(b) The facility and square meters required are only needed for short-term use during port operations. Specific details, including time and duration, will be provided by the COR for each individual mission.
| (c) No, office space will be ordered by the COR as-needed. | No | ||
| 10 | 11-Feb-26 | Technology: |
(a) Any requirement to MPL for setting up IT platform/ having specific software?
(b) Any need for integration with US Transcom IT system? 19-Feb-26 (a) No MPL or IT software platform is required.
| (b) No integration with the U.S. TRANSCOM IT system is required. | No | ||
| 11 | 18-Feb-26 | It is Lunar New Year period of the year in Asia Pacific Region and several firms and units in Malaysia are returning from work next week. |
We request a week extension to the submission dates from 27th Feb 2026 to 12th Mar 2026 for SDDC S&RTS Solicitation Malaysia.
19-Feb-26 The RFQ will be extended to 11 March 2026 at 12:00 PM CT. Yes