Attachment B- SOW for HVAC Earle 4-2-12.pdf

PDF 57 KB Posted

Attached to
PROCURE & INSTALL EMERGENCY GENERATOR AND A/C UNITS
Solicitation number
HSFE02-12-R-0004
Issued by

About this file

ATTACHMENT B

View the file

Other files

File Type Posted
NOTICE OF AWARD.pdf PDF
QUESTIONS AND ANSWERS FOR GENERATOR HVAC- Updated 06-14-2012.pdf PDF
HVAC 4.jpg JPG image
QUESTIONS AND ANSWERS FOR GENERATOR HVAC- Updated 05-31-2012.pdf PDF
HVAC PIC 1.jpg JPG image
HVAC PIC 2.jpg JPG image
HVAC 3.jpg JPG image
FRONT 3.JPG JPG image
FRONT 1.JPG JPG image
FRONT 2.JPG JPG image
REAR 7.JPG JPG image
REAR 2.JPG JPG image
REAR 3.JPG JPG image
REAR 1.JPG JPG image
REAR 5.JPG JPG image
REAR 6.JPG JPG image
REAR 4.JPG JPG image
HSFE02-12-R-0004 A00003 —
Sign-In Sheet.pdf PDF
QUESTIONS AND ANSWERS FOR GENERATOR HVAC- Updated 05-14-2012.pdf PDF
HSFE02-12-R-0004 A00002 —
A1a Existing Building.pdf PDF
QUESTIONS AND ANSWERS FOR GENERATOR HVAC- Updated 05-10-2012.pdf PDF
2094036-37.TIF TIF image
3-5813F.TIF TIF image
3-5815F.TIF TIF image
2094035-36.TIF TIF image
2094033-34.TIF TIF image
2135294-5-8.TIF TIF image
2135295-6-8.TIF TIF image
3-5814F.TIF TIF image
2146816-1-8.TIF TIF image
2094034-35.TIF TIF image
2094032-33.TIF TIF image
RAPIDGATE.pdf PDF
HSFE02-12-R-0004 A00001 —
QUESTIONS AND ANSWERS FOR GENERATOR HVAC.pdf PDF
Attachment A- SOW for Generator. Earle- 4-2-12.pdf PDF
HSFE02-12-R-0004.pdf PDF
Attachment C- General Decision Number NJ120037.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT B

STATEMENT OF WORK

Replace HVAC System

Dated: 04/02/2012

DISCUSSION:

Location: FEMA New Jersey Close-out Office NWSC (Naval Weapon Station Earle): Bldg C-54. 201 Highway, 34 South

Colts Neck, NJ 07722

Current Condition:

Building C54 (Office Space 22,490 SF) is Heated and Air Conditioned with 2 HVAC Units located on the Roof of the

Building. Both units are over 25 years old with one unit missing the condenser and other parts. These parts are no longer available. The second unit is functioning at 20% capacity and an analysis concluded major parts needing replacement with parts required no longer available.

REQUIREMENTS:

1. Disconnect and remove of the two existing HVAC Units located on the roof of Building C54. Dispose in accordance with local and state requirements. Remove any electrical piping, duct and etc. as required. Repair any roof damage were units were removed.

2. Provide and install two new HVAC Units on the roof of the building and Condensers on the Ground next to the building.

Units are required to be sufficient and efficient to Heat and Air Condition 22,490 SF of Office Space.

a. Pour New Concrete Pad for the Condensing Units

b. Make new electrical, piping, duct and etc connections

c. Test, training, startup of units

3. Repair roof after removals. Repair and close any other penetrations.

4. Design, layout, shop drawings, approval design coordination.

5. 2 new HVAC units roof mounted.

6. 2 new condensing units.

7. HVAC units install on roof with all connection and materials.

8. Manufacture and install new ductwork to facilitate new units tying into existing.

9. Condensing units install next to building with all connections and materials.

10. Provide tonnage and vibration isolators for units on roof.

11. Verify structural condition of rood structure.

12. Use prefab unit for condensers.

13. All work shall be done in accordance with local, State and Federal requirements and regulations.