Amendment 0003
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0003 02 NOV 12 21-13-853P45T85
6. ISSUED BY CODE HSCG85 7. ADMINISTERED BY (If other than Item 6) CODE
COMMANDER
SURFACE FORCES LOGISTICS CENTER C&P2
1301 CLAY ST. STE 807N
OAKLAND, CA 94612-5217
8. NAME AND ADRESS OF CONTRACTOR (no., street, county, State and ZIP Code) √ 9.A AMENDMENT OF SOLICITATION NO.
HSCG85-13-R-P30T85
9B. DATE (SEE ITEM 11)
18 OCT 12
10A. MODIFICATION OF CONTRACT/ORDER
NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the Offer submitted: or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
√ A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/.ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc)
SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
USCGC SEQUOIA (WLB 215) FY13 DRYDOCKING REPAIRS
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remain unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
)PREVIOUS EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR) 53.2
HSCG85-13-R-P30T85 Amendment 0003
1. Response(s) to Request(s) for Clarification 0004 – 0007 is/are provided as Attachment A.
2. Due to administrative error, Amendment 0002 indicated “0001” in Block 2 of that amendment. Offeror’s shall pen and ink or electronically edit Block 2 of that amendment to indicate “0002.”
3. There is no change to the proposal closing date, which remains as follows:
14 NOV 12 (1100 Pacific)
A responsive proposal shall consist of the following:
a) Signed & dated SF1449 (2 pages) and any Amendments
b) Completed Provision (26) Pre-Award Drydock Certs & Calcs
c) Completed Provision (33) Place of Performance (1 page)
d) Completed Provision (3) Info Regarding Responsibility Matters
e) Completed Provision (5) Prohibition…Corporate Expatriates
f) Any qualifications to FAR 52.212-3 (otherwise SFLC will consider your ORCA registration current, accurate, complete, and applicable (zero pages if no qualifications). Make sure your registration in SAM.gov is current and accurate.
g) Completed Electronic Spreadsheet Schedule of Supplies (1 page - submit electronically as a spreadsheet)
In addition to the requirements at (22) FAR 52.212-1 INSTRUCTIONS TO OFFERORS, you are encouraged to email a scanned copy of your proposal to the individual in Block 7.a.
at james.s.altice@uscg.mil. Please economize on the size of your emailed submission and please confirm receipt.
4. Shipchecks may be arranged by contacting vessel’s Engineering Officer, CWO Wendy Titensor. She can be reached via the following methods:
Ship’s Main Switchboard (671) 355-4885 Cell Phone (671) 688-0741 Email: Gwendolyn.A.Titensor@uscg.mil
ATTACHMENT A
Date: 11/1/12
Question No. 0008
REQUEST FOR CLARIFICATION
SHIP & HULL No.: CGC SEQUOIA (WLB 215) FY13 DRYDOCKING
RFP No.: HSCG85-13-R-P30T85
SOLICITATION SECTION: PARA NO.
WORK ITEM NO. 46 PARA NO. 3.2.1
TITLE: U/W Body, Preserve “Partial Condition C
QUESTION:
The contractor is to lightly clean the designated surfaces by water jetting (SSPC-SP-12/NACE No. 5 or abrasive off blasting SSPC-SP-7 NACE No. 4 to move all visible oil, grease, dirt, loose mill scale.
Loose rust and loose antifouling. For estimating what percentage of the under water hull will require blasting?
Condition B covered 100% of the underwater hull by water jetting (SSPC-SP-12/NACE No. 5 or Abrasive off blasting SSPC-SP-7 NACE No. 4
RESPONSE:
For condition “C”, assume that up to 100% of the underbody AF coating will require at least a brush blast to remove all contaminants from the tightly adhered AF prior to application of new coating.
Condition B differs in that it requires the removal of all AF coating down to the AC layer whereas Condition C is less intrusive but the square footage remains similar but with a less aggressive blast required.
Question No. 0009
RFP No.: HSCG85-13-R-P30T85
SOLICITATION SECTION: PARA NO.
WORK ITEM NO. 50 PARA NO. 3.2
TITLE: DRY DOCKING
SFLC STANDARD SPECIFICATION 8634 Paragraph 3.4.4.2. Requires the contractor to remove all marine growth from the entire underwater hull. Cleaning shall be supplemented with stiff bristle brushes and scrapers as necessary to remove all visible marine growth. For estimating can the ship supply any picture showing marine growth or what percentage of underwater hull will require scraping to remove marine growth?
Generally, hard marine growth requiring scraping is limited to a 4-6ft area around the circumference of the ship along the water line. There is generally less hard marine growth underneath that band.
Question No. 0010
RFP No.: HSCG85-13-R-P30T85
SOLICITATION SECTION: PARA NO.
WORK ITEM NO. 62 PARA NO. 3.2.1
TITLE:
Bilge (machinery space) stern thruster Machinery room preserve
For estimating what percentage of the bilge will require water jetting (SSPC-SP-12 NACE N0.5) or power tool cleaning (SSPC-SP-11) ?
100% of bilge surfaces, including adjacent structural framing and deck plates require SSPC-SP-11 or SSPC-SP12 preparation. Areas to be preserved include those at deck plate level and below.