The purpose of this amendment is see attached pages for changes and clarification provided by the Government for CTIMR Area 1 RFP. Please note an updated version of the RFP HSBP1010R0018 - POSTA00001 and A00002 is now available as part of this A00002 amendment package.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Signed__FINAL_P00005.pdf | ||
| Signed HSBP1012C00007 P00003 Rev1.pdf | ||
| HSBP1010R0018_Amendment_00003.pdf | ||
| 2.17.10 CTIMR AREA 1 RFP HSBP1010R0018 - POST A00003.doc | DOC document | |
| Roster Area 1 Site Visit - INDUSTRY.xls | XLS spreadsheet | |
| 1.29.10 CTIMR AREA 1 RFP HSBP1010R0018 - POST A00002.doc | DOC document | |
| CTIMR GFM order form.xls | XLS spreadsheet | |
| HSBP1010R0018_Amendment_00001.pdf | ||
| Site Visit Registration Form and Agreement.pdf | ||
| Web Notice Areas 1 Proposal Visits FINAL.doc | DOC document | |
| Cost-Reimbursement Estimate Tables by Work Category- Area 1.xls | XLS spreadsheet | |
| CTIMR AREA 1 RFP HSBP1010R0018 V5.doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
HSBP1010R0018 – A00002
Changes to the RFP
- The disclosure of the magnitude for this project has been added to the SF 1442 on page 2 in block 10 of the RFP using the following language: In accordance with FAR 36.204, the magnitude of the requirement is more than $10 million.
- Section H.10 has been added to the RFP on page 33 to indicate Proposal Bond Requirement using the following language: A proposal bond will be required in the amount of $2.72 million.
- FAR 52.217-3 Evaluation Exclusive of Options clause has been incorporated by reference into Section I.1 on page 35
- The word “cost” has been added to Section J: List of Attachments appropriately as it pertains specifically to Attachment 3: Guidance for Contractor Cost Proposal
- Factor 4: Small Business Utilization was deleted from Section M on page 97.
Factor 5: Cost/Price Evaluation was renumbered as Factor 4: Cost/Price Evaluation.
Government Clarification for Area 1 RFP
1). Each offeror must acknowledge all amendments made to the solicitation:
a) On the Standard form (SF) 1442, Block 19:
-list each amendment by number and date
OR
(b) Complete blocks 15A and 15B of page 1 (SF 30) for each amendment in order to acknowledge each amendment’s issuance and return with your proposal
2). Performance/payment bonds will be required after contract award. As required by the Miller Act, the payment bond shall be equal to the total amount payable by the terms of the contract. The amount of the payment bond shall not be less than the amount of the performance bond. The actual performance/payment bond amounts will be determined after contract award and based on the Miller Act guidelines.
3) In reference to amendment 1 changes in Section L.9 on page 94:
Tab A no longer references “for each work plan” but instead “for the base year”. The back-up cost information should support the Guidance for Contractor Cost Proposal, Attachment 3 within the RFP. Thus, the word “cost” has been added to Section J: List of Attachments appropriately as it pertains specifically to Attachment 3.
[END HSBP1010R0018 – A00002]
| IDCode: |
| Page: 1 |
| Pages: 2 |
| AmendNo: A00002 |
| EffDate: 01/29/10 |
| ReqNo: 0020053725 |
| ProjNo: N/A |
| IssCode: |
| IssuedBy: Department of Homeland Security |
Customs and Border Protection 1901 South Bell Street 8th Floor Arlington, VA 20598
| AdmCode: |
| AdminBy: |
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolAmdNo: HSBP1010R0018 |
| AmendDate: 01/29/10 |
| ModNo: |
| ModDate: |
| NoCopies: 2 |
| Amended: Yes |
| ApprData: N/A |
| ChgeOrder: |
| Modify: Off |
| SuppAuth: |
| OthrSpec: |
| Require: Off |
| Copies: |
| Descript: The purpose of this amendment is: see attached pages for changes and clarification provided by the Government for CTIMR Area 1 RFP. |
Please note an updated version of the RFP HSBP1010R0018 post A00001 and A00002 is now available as part of this A00002 amendment package.
| SignName: |
| SignTitl: |
| ContDate: |
| CoName: Mindy Lea Mcdaniel |
| CoTitle: Contracting Officer |
| CODate: |
| SolChgYs: Off |
| SolChgNo: Off |
| OffrExt: Off |
| OffrNoEx: No |
| ChgeOrd: Off |
| SuppAgre: Off |
| ModOthr: Off |
| NoReq: Off |
File details come from the government source that posted it. Updated .