Sec J Att 14 Quarterly Accomplishment Report Template 12 Feb 20.pdf

PDF 187 KB Posted

Attached to
TEAMS-Next Contracting, Compliance, Cost/Price and Operations (C3PO)
Solicitation number
HQ0858-20-R-0001
Issued by

About this file

This document provides a quarterly accomplishment report template for the TEAMS-Next Contracting, Compliance, Cost/Price and Operations (C3PO) contract opportunity issued by the Missile Defense Agency. The template requires contractors to report on accomplishments, weaknesses, corrective actions, and requirements exceeded on a quarterly basis across seven areas of performance: quality, schedule, cost control, management, small business utilization, regulatory compliance, and cybersecurity. For each area, contractors must capture accomplishments supported by the contract performance oversight plan, identify any issues and the status of related deficiency reports and corrective action plans, and explain how any requirements were exceeded and the related benefits to the government. The report is limited to ten pages and must address all subfactors in the oversight plan for the applicable areas.

The federal contract opportunity is for executive-level research, analysis, advice, and product development services in areas like contract policy, pricing, and operations support. The Missile Defense Agency seeks to award a cost-plus-fixed-fee level of effort contract for a base period of two years plus six additional one-year and six-month options. The total small business set-aside contract will be awarded based on best value. Offerors must register in the System for Award Management and submit proposals by March 23, 2020 to be considered for the contract.

View the file

Other files

File Type Posted
Contractor BETA.SAM.GOV Quick Start Guide.pdf PDF
Sec J Att 15 SOFA Travel Clauses.pdf PDF
Sec J Att 06 Individual Contractor NDA 9 Jan 20.pdf PDF
Att L6 Accounting System Checklist 7 Feb 20.doc DOC document
Att L2 PPQ Form 20 Feb 20.docx DOCX document
Sec J Att 05 TERP Pricing Model 19 Feb 20.xlsx XLSX spreadsheet
Sec J Att 11 Cost Report Template 10 Feb 20.xlsx XLSX spreadsheet
Att L3 Sample Consent Letter 9 Jan 20.pdf PDF
Att L1 PPI Form 20 Feb 20.docx DOCX document
Sec J Att 08 DD-254 19 Feb 20.pdf PDF
Sec J Att 03 TERP Procedures 19 Feb 20.pdf PDF
Sec J Att 09 Auth ODC Travel by CLIN.xlsx XLSX spreadsheet
Sec J Att 13 Monthly Manpower Report Template 7 Feb 20.xlsx XLSX spreadsheet
HQ0858-20-R-0001 C3PO.pdf PDF
Att L7 OCI Disclosure Form 6 Feb 20.docx DOCX document
Sec J Exh A CDRLs.pdf PDF
Sec J Att 01 C3PO SOW 19 Feb 20.pdf PDF
Sec J Att 12 Travel Status Report Template 7 Feb 20.pdf PDF
Sec J Att 07 PPBE Form 9 Jan 20.pdf PDF
TEAMS-Next C3PO Sec M 20 Feb 20.pdf PDF
Att L5 Excel Pricing Worksheet 19 Feb 20.xlsx XLSX spreadsheet
Sec J Att 04 TERP Form 19 Feb 20.pdf PDF
Att L4 Client Authorization Letter 9 Jan 20.pdf PDF
Sec J Att 02 G-06 Allot of Funds 11 Feb 20.pdf PDF
Sec J Att 10 Monthly Status Report Template 10 Feb 20.pdf PDF
TEAMS-Next C3PO Sec L 20 Feb 20.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HQ0858-20-R-0001

Section J Att 14

Quarterly Accomplishment Report (QAR) Format

The purpose of the accomplishment report is to provide input that may be used for consideration of the Government’s assessment of the contractor’s overall performance. A current, fact-based self-assessment will include identification of accomplishments, risks encountered, how they were mitigated, and deficiencies in any aspect of contract performance. It will include any corrective actions required, whether or not they were successful, and proactive measures taken to prevent the recurrence of similar situations.

The Contractor may format as desired, provided the report does not exceed ten (10) pages and the QAR requirements below are addressed for each Area of Performance (AOP): Quality, Schedule, Cost Control, Management, Small Business Utilization, Regulatory Compliance and Cybersecurity. The Contracting

Officer’s Representative (COR) may advise the Contractor of needed improvements to the report as needed. At a minimum, the QAR shall include the following for each AOP:

Contractor’s Accomplishments: Capture the Contractor’s accomplishments and support accordingly as provided in the Contract Performance Oversight Plan (CPOP) under each AOP. Include only actions/events that have occurred during the reporting period. Do not identify the Contractor’s self-

Assessment rating and do not carry over items from past periods unless there have been new developments or progress.

Identify Weaknesses/Deficiencies or Corrective Actions: For each issue identified provide the following information:

Identify the details and dates of any weaknesses/deficiencies in performance

List the Contract Performance Deficiency Reports (CPDR) and Corrective Action Plans

(CAP), if applicable

List the actions taken to resolve and/or mitigate the weakness encountered

Status or final disposition of the issue identified

Identify Requirement(s) Exceeded: For each requirement exceeded provide the following information:

For the following AORs: Quality, Schedule, Management and Cybersecurity:

Identify the Statement of Work (SOW) section

Identify the Agency’s Functional Area supported

Explain what independent effort was performed and support how it is above and beyond the Government’s requirement. When and where possible, recommend using metrics to quantify performance.

Explain how the Government benefitted in gaining a specific efficiency or significant positive impact. Note: Accomplishing a task accurately as required in the SOW is not exceeding a requirement.

Ensure that the subfactors shown in the CPOP are addressed, as applicable

For the following AORs: Small Business Utilization and Regulatory Compliance:

Identify the relevant contractual requirement or standard.

Report actuals within the single contract year of interest and support how it is above and beyond the Government’s requirement.

Ensure all subfactors shown in the CPOP are addressed, as applicable.