This document contains questions and answers related to a federal contract opportunity for Construct 3D Printer Room, Solicitation Number HM157524B0001, issued by the Department of Defense National Geospatial Intelligence Agency.

The key details are:

  • The height from finished floor to the bottom of the roof deck is 9.2 meters.
  • The contractor is responsible for removal and disposal of all debris and demolished material from the site, and may use the nearby overhead door on the north exterior wall for entry and exit of construction material and debris.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

# Date Document Section Question Answer 1 7/30/2024 1. What is the deck heights. Answer: Height from finished floor to the bo om of the roof deck is

9.2 meters.

2 7/30/2024 2. How do we dispose of the demolition debris. Answer: The contractor is responsible for removal and disposal of all debris and demolished material from the site. The contractor may use the nearby overhead door on the north exterior wall for entry and exit of construction material and debris.