Amend03 Questions and Answers.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Electromagnetic Spectrum Services Applied Engineering, Spectrum and Electromagnetic Environmental Effects Engineering Analysis Support
Solicitation number
HC104720R0013
Issued by

About this file

This document contains a questions and answers file related to a federal solicitation for electromagnetic spectrum services and engineering analysis support. The solicitation seeks technical support services including E3 and spectrum engineering, technical advice, radio frequency measurements, and assistance acquiring host nation approval for equipment operation. The support is required to execute DoD spectrum policy. Key details include confirmation that only the prime contractor must maintain a top secret facility clearance, clarification that the small business participation plan and subcontracting plan should both be submitted in Volume V without page limits, and an extension denial with a response due date of December 17th.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Q&A INSTRUCTIONS: The purpose of these specific instructions is to expedite the process of answering questions. Please do not change the format of this document.
Complete the spreadsheet tab below named "Q&A" with all questions, comments, and recommendations about the RFP. Examples provided in the spreadsheet. **Please delete the examples before submitting your questions.

COLUMN A: Complete the "Page" column. This is the page number from the RFP located in the upper right hand corner of the page. Do not include the total page number. Enter only the page number where the topic begins.

COLUMN B: Complete the "Section/Paragraph" column with the applicable section and paragraph number (if applicable) of the RFP. For example: B2, C, or L5.1.2. For a section and paragraph number reference do not place a dot between the letter and the first number. Additional subparagraph references should be separated with a dot regardless of the format in the RFP, for example, L5.1.2.a. Do not including any other extraneous identifiers or other information other then instructed here. If the reference is to a CLIN, Clause, Appendix, or Attachment etc. the entry goes in the next column. At a minimum you will always insert at least the Section letter A through J in this column.

COLUMN C: Complete the "CLIN/Clause/Other" column. Insert the CLIN, Clause, Provision, Appendix, or Attachment number. For example: CLIN 0001, 52.217-8, Appendix A, or Attachment L3. Insert the section letter only in the Column B. This column will be completed only when there is not a more precise RFP reference number. NOTES: CLINs are in Section B. Most sections contain clauses so ensure you reference the correct section.

COLUMN D: Complete the Questions/Comments/Recommendations column. Start the question by referencing the topic. This may help the sort process. For example: Minimum Qualifications Checklist or Performance Area 10. Then insert the question or comment.

olicitation

Q&A

#RFP PageRFP Section/ ParagraphCLIN/ Clause/Appendix/Attachment/OtherQuestions/Comments/RecommendationsGovernment Response
110Amend 1 page 2 of 22AJ1 revisiedGiven the significant change to the pricing methodology introduced by the Revised J1, the 50% increase in the Technical Management Subfactors 1 - 3 content allocation based on the removal of the 1.5 line-spacing requirement, and the requirement for Offerors to send the Past Performance Questionnaires to their customer and have them returned to DISA by the due date of the proposal, along with the Thankgiving holiday in the remaining two weeks...request a two-week extension of the due date for submittal to 17 December.No additional extension is being granted.
11111 of 95C.9J1 revisiedC.9 states "The primary place of performance will be at the contractor facility…" yet there are a significant number of hours in the Revised J1 to be priced at Government Site. Please clarify the hours and locations to be priced.The hours and associated locations are for estimating purposes only. Final hours and locations are TBD at the task order level.
112Amend 1 page 14 of 22L.1.EL.1.E states "...If the offeror believes that no OCCI exists, the OCCI response shall set forth sufficient details to support such a position…." Please confirm that a statement to the effect that "...we do not have any actual or perceived OCI as defined in Subpart 9.5 of the Federal Acquisition Regulation. " and "All proposed subcontractors have certified to ... that they have no actual or perceived OCI. Their written certifications are filed at ... and are available for inspection upon request." meets this requirement.Confirmed.
113Amend 1 page 16/17 of 22L.2 Volume IIIThe response to Q91 stated "A table format is acceptable, however it is preferred to use the template being provided in the RFP" Please provide the cited Template.The list template is provided in Volume III – PAST PERFORMANCE INFORMATION
1143 of 95B1 (A)Q&A 104 and 105The responses to these two questions appear to be contradictory. Please confirm the NTE value cited in Section B1 (A) includes the 20% Surge but NOT the 6-month ExtensionConfirmed.
11594 of 95ATT L2ATT L2 and Q&A 21The response to Q21 states "….The customer is to submit them to the Government with RFP# as reference (KO & CS identified in the RFP)." The Template provided Section C states "C. FAX COMPLETED SURVEY FORM TO: _________________" Please provide a corrected Template or allow Offerors to modify the Template to direct Customers to Email their responses to the KO &CS as indicated in the response.The template may be modified. Responses should be sent to the KO & CS identified in the RFP via email.
116J1 revisiedPlease confirm that the rates Offerors propose in Column H of the FP Rate Sheet will be the "fixed [rates] for the life of the contract" even though Discounts are applied to obtain the "Proposed FP Labor Hr Rate" (Column J of the BP YY x Tabs) used to calculate the Total Price.Confirmed.
11794M.ARFP M.A specifies "All offerors shall provide their proposed goals in terms of percentages and the total dollars planned to be subcontracted, specifying the total dollars planned to be subcontracted to the various types of small and small disadvantaged businesses." in Volume II, Technical/Management. Also M.A states " offerors shall identify by name, type of business, product/service, dollar value, ..." in Volume II, Technical/Management.

RFP L.1.J states "All cost or pricing information shall be addressed ONLY in the Cost/Price Proposal Volumes."

AMD 1 L.1.K resolved the question on cost/price data in Volume V for the "DISA Subcontracting Plan Review Checklist", but was silent on the Small Business Subcontracting Plan (now in Volume V) and the Small Business Participation Plan (Volume II).

Request 1: Please confirm that the dollar values specified in Subfactor 5 for the Small Business Participation Plan should be included in Volume II.

The dollar values specified in Subfactor 5 for the Small Business Subcontracting Plan should be included in Volume V.
11894M.ARFP M.A specifies "All offerors shall provide their proposed goals in terms of percentages and the total dollars planned to be subcontracted, specifying the total dollars planned to be subcontracted to the various types of small and small disadvantaged businesses." in Volume II, Technical/Management. Also M.A states " offerors shall identify by name, type of business, product/service, dollar value, ..." in Volume II, Technical/Management.

AMD 1 L.1.K resolved the question on cost/price data in Volume V for the "DISA Subcontracting Plan Review Checklist", but was silent on the Small Business Subcontracting Plan (now in Volume V) and the Small Business Participation Plan (Volume II). Request 2: Please confirm that the dollar values specified in Subfactor 5 for the Small Business Subcontracting Plan should be included in Volume V.

The dollar values specified in Subfactor 5 for the Small Business Subcontracting Plan should be included in Volume V.
119Original RFP , 88

Amend 0001, Pages 14 and 15 and 16 Table L-1

Section L.2 There is some confusion regarding the submission Small Business Partnership Plan and the Small Business Subcontracting Plan.

Refernces: In the orginal RFP, table L1 had "Small Business Subcontracting Plan" as part of Vol II, with no page limit.

In the Amend 0001 RFP, Table L1 removed "Small Business Subcontracting Plan" as part of Vol II and moved it to Vol V. (refernce Section L, Volume V, d)

In the orginal RFP, Offeror's assumed that the referece to "Small Business Subcontracting Plan" in L-1 was for Subfactor 5 with no page limit.

In the Amend 0001 RFP Volume II still requires Subfactor 5, Small Business Participation Plan, however it is no longer listed in Table L-1.

Questions. Can the USG please clarify the following to ensure Offeror's submit compliant bids:

1. Are the Small Business Subcontracting Plan (Vol V) and Subfactor 5, Small Business Participation Plan one and the same requirement?

2. If there are two small business plans required (1. Subcontracting Plan and 2. Participation Plan) required, can the USG please clarify that both are not included in Page Count?

3. Can the USG please confirm the following are or are not required:

- Vol II, Subfactor 5, Small Business Participation Plan, No Page Limit

- Vol V, Contract Documentation, Small Business Subcontracting Plan, No Page Limit and Attachment L4, No Page Limit

4. Or can the USG please clarify if the Small Business Participation Plan listed as Subfactor 5 is to be included in Volume V with no page limit?

Revision was made to request Small Business Subcontracting Plan be submitted via Vol V, where initially it was in Vol II due to it being a Subfactor being evaluated.

Your SB Partnership Plan is applicable if you are partnering up with a SB. Your Subcontracting Plan is your proposed work being performed by SB's. Both Plans should be submitted under Vol V and are not considered in the page count 120 12 H9. Security Clearances "...if the successful offeror is comprised of a contractor teaming arrangement, each member of the teaming arrangement is required to maintain a Top Secret Facility Clearance throughout the life of the contract." Please confirm that the Contractor Teaming Arrangement being addressed is as described in FAR 9.601 (1) for this solicitation and not the typical Prime / Subcontractor as described in FAR 9.601 (2). Please confirm only the Prime Contractor is required to maintain a Top Secret Facility Clearance thorughout the life of the contract and not the subcontractors? Confirmed.