HC1028-17-R-0020_ 0002- updates the PWS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HC1028-17-R-0020_0001.docx | DOCX document | |
| 17R0020_QA_1_-_final.pdf | ||
| Attachment_6__DD254.pdf | ||
| Attachment_7_Pricing_Sheet.xlsx | XLSX spreadsheet | |
| Attachment_5__QASP.docx | DOCX document | |
| Attachment_4__Key_Personnel_and_Minimum_Qualifications_Matrix.docx | DOCX document | |
| HC1028-17-R-0020_CAD_ENG.docx | DOCX document | |
| Attachment_2_PAR.pdf | ||
| Attachment_8__Task_Scenarios.doc | DOC document | |
| Attachment_9__consolidation_D&F.pdf | ||
| Attachment_1_NDA.DOCX | DOCX document | |
| Attachment_3_TAR.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HC1028-17-R-0020
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
as of March 16, 2017
| Contract Number: |
| (completed by the KO at time of contract or TO award) |
| Task Order Number: |
| N/A |
| Tracking Number: |
| HC1028-17-R-0020 |
| Follow-on to Previous Contract and Task Order Number: |
| HC1028-12-D-0004 & HC1028-14-A-0001 |
1. Contracting Officer’s Representative (COR)
a. Primary COR.
| Name: |
| TBD |
Organization:
Department of Defense Activity Address Code (DODAAC):
Address:
Phone Number:
Fax Number:
E-Mail Address:
b. Alternate COR. (ACOR)
| Name: |
| TBD |
Organization:
DODAAC:
Address:
Phone Number:
Fax Number:
E-Mail Address:
2. Contract Title. The Defense Information Systems Agency (DISA) Engineering and Data Center Management Division (MPE) – Computer Aided Drafting (CAD) and Engineering Support Services.
3. Background. DISA is a provider of Information Technology (IT) services supporting the Army, Navy, Marines, Air Force, Defense Finance and Accounting Service (DFAS), Defense Logistics Agency (DLA) and other Department of Defense (DoD) agencies. The DISA Engineering and DECC Management Division (MPE) Facilities Team manages and directs the facility engineering, maintenance programs, and raised floor infrastructure for DoD data centers within the continental United States (CONUS) and outside of the continental United States (OCONUS). Due to customer IT workloads and on-going DoD consolidation efforts, the current locations and volume of data centers may grow and/or contract throughout the performance of this contract. The facilities team establishes and maintains facility standards for the safe, reliable operations of those centers which are compiled from national codes, military handbooks, and industry best practices. In addition, the team establishes requirements to meet these standards while developing fiscally responsible solutions to meet or sustain site standards.
At times these locations require engineering/environmental support which exceeds the current resources available within MPE. The engineering/environmental support are typically location specific, time sensitive, and of limited duration. Engineering support (mechanical, electrical, civil, and structural) is required to evaluate existing conditions and proposed systems. The environmental support is required to validate existing site conditions, evaluate reports, and provide recommended processes and training to personnel.
4. Objectives: DISA MPE Facilities Engineering team is responsible for providing highly reliable, available, and maintainable facilities, infrastructure, and property to support DISA and its customers’ data processing missions. These objectives shall be met with strict adherence to federal, state, local, and DISA facility standards and codes. All work shall be completed in the most economically feasible and energy efficient manner possible. This contract will provide support services for the Government facility engineering staff in achieving this objective.
The objectives of this PWS is to provide base support for CAD services, engineering support, and Technical Requirements (TR) services for mechanical, electrical, and environmental engineering services. These services are a combination of persistent, ongoing service requirements as well as intermittent, as needed requirements depending on the individual task order.
5. Scope. The Contractor shall provide computer aided drafting and engineering support services to DISA to include all related support functions associated with facilities engineering while providing recommendations and assistance to Government personnel in areas of responsibility under this PWS.
5.1 Base Support Services Scope – The Contractor shall provide the CAD support and engineering/technical support as descripted under section 6, Performance Requirements, listed below. All deliverables provided as a result of this support will be subject to Government oversight and approval prior to implementation.
5.2 Technical Requirement (TR) Support Services Scope - The TR support personnel will be required to support DISA with engineering/architectural support and subject matter experts (SME) with knowledge of environmental engineering, structural engineering, mechanical engineering, electrical engineering, architectural design, codes/regulations, accessibility, commissioning, building envelope, and general building systems. Contractor personnel shall be available to travel to sites and perform site/building engineering surveys, assessments, analyses and reports, support design, construction and maintenance projects, support local site facility management staff, and establish facility standards and guidance. All deliverables provided as a result of this support will be subject to Government oversight and approval prior to implementation.
6. Performance Requirements. The Contractor shall provide services consisting of the following for a 1-Year Base Period and Four 1-Year Option Periods:
| - | CAD Support and Engineering Support – (Base Services) |
| - | Engineering/Environmental Services – (Technical Requirement Services) |
| - | Travel / Other Direct Cost (ODC) |
6.1 Task 1 - Computer Aided Drafting (CAD) Support – Base Services
6.1.1 Subtask 1 (Integrate) The Contractor shall provide CAD support and Configuration Management (CM) services with revision controls to complete the integration of the MPE Drawing Management System (DMS) through the shared network drive (or equivalent drawing file structure), conversion of existing Legacy Drawings to the newly established Master Drawing (AutoCAD 2015) formats (rebuild drawings that will not convert), completion of on-site surveys to update and expand existing as-built drawings into the Master Drawings, ensuring Master Drawings comply with guidance from the new facility standards, and integrating all existing project as-built drawings into the Master Drawings. Drawings shall follow guidance in mandatory reference United States Army Corps of Engineers Engineer Research and Development Center /Information Technology Laboratory TR-12-X A/E/C CAD Standard (current release) with respect to electronic file naming conventions, level/layer assignments and naming conventions, and standard symbology, unless approved otherwise by the Government. The Government review period for this subtask will be approximately thirty (30) calendar days. It is estimated that a total of twenty-four (24) individual site visits will be required to complete this action. These services require access to NIPR in order to access CAD resources and Master Drawing Format files.
6.1.2 Subtask 2 - (Sustain) The Contractor shall provide CAD support and CM services with revision controls to integrate new as-built sections from completed projects into the Master Drawing files. It is estimated that there are four (4) larger multi-discipline projects and four (4) larger single discipline projects with as-built drawings to be incorporated and twenty four (24) smaller projects with redlines to be incorporated annually. These services require access to NIPR in order to access CAD resources and Master Drawing Format files.
6.1.3 Subtask 3 - (Drafting) The Contractor shall provide CAD support and CM services with revision controls in collaboration with the Government Project Engineers in the development of basic drawing/concept plans for in-house designs. It is estimated that four (4) small in house designs will be done requiring four (4) individual site visits annually. These services require access to NIPR in order to access CAD resources.
6.1.4 Minimum Labor Qualifications
6.1.4.1 – Senior/Lead CAD Operator – Minimum eight (8) years of experience with AutoCAD in building design, engineering, or facilities related work.
6.1.4.2 – CAD Operators – Minimum three (3) years of experience with AutoCAD in building design, engineering, or facilities related work.
Deliverables:
| - | AutoCAD Drawings Files and PDF Drawing Files (95% and final submittals) |
| - | Building Usage Reports (floor plan drawings and square footage usage) |
| - | Update AutoCAD Files on Network Drive (controlled access folder) |
| - | Update PDF Files on SharePoint (DEPS) and Network Drive |
| - | Monthly Status Report |
6.2 Task 2 - Engineering Project Management and Support – Base Services
6.2.1 Subtask 1 – Mechanical Engineering - Project Design and Support. The Contractor shall provide assistance in the development of projects and services with supporting engineering calculations to include rough sizing of mechanical systems, piping, ductwork and other facility systems and mechanical components. The proposed support will encompass technical mechanical engineering reviews of approximately four (4) complex multi-discipline designs and the drafting of approximately four (4) Statements of Work (SOW) / Performance Work Statement (PWS) with supporting cost estimates annually. Mechanical engineering services shall include supporting project execution with engineering assistance for technical reviews and providing recommendation / review comments to the Government representative regarding contract status with schedule, and Contractor’s compliance with contracts on an estimated total of twelve (12) individual site visits annually and support for retrofitting and re-commissioning activities for an estimated two (2) locations. These services require access to classified information up to the Secret level and access to NIPR in order to review facilities reports and mission partner documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.2.2 Subtask 2 – Electrical Engineering - Project Design and Support. The Contractor shall provide assistance in the development of projects and services with supporting engineering calculations to include rough sizing of electrical systems, generators, uninterruptible power supplies (UPSs), conduits, conductors, and other electrical components. Maintain DISA’s existing electrical studies (coordination, arch flash & labels) using Easy Power software. The proposed support will encompass technical electrical engineering reviews of approximately four (4) complex multi-discipline designs and the drafting of approximately four (4) Statements of Work (SOW) / Performance Work Statement (PWS) with supporting cost estimates annually. Electrical engineering services shall include supporting project execution with engineering assistance for technical reviews and providing recommendation / review comments to the Government representative regarding contract status with schedule, and Contractor’s compliance with contracts on an estimated total of twelve (12) individual site visits annually and support for retrofitting and re-commissioning activities for an estimated two (2) locations. These services require access to classified information up to the Secret level and access to NIPR in order to review facilities reports and mission partner documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.2.3 Subtask 3 – Mechanical Engineering - Project Transition. The Contractor shall provide mechanical engineering assistance for technical reviews, computational fluid dynamics (CFD) using TileFlow software, commissioning coordination/oversight/duties, assist the Government project managers in transitioning and closing out of all projects from the project team to the maintenance team, and provide maintenance recommendations supporting those projects. In addition, provide technical reviews and recommendations to the Government representative regarding improvements to energy efficiency to reduce the Power Usage Effectiveness (PUE) of the data centers in regards to the maintenance and operations of existing systems, drafting SOW/PWS, cost estimates and acquisition package requirements for recommendations approved by the Government and review whole scale upgrades with a positive Return on Investment (ROI). It is estimated that eight (8) individual site visits annually will be required to support these subtasks. These services require access to classified information up to the Secret level and access to NIPR in order to review facilities reports and mission partner documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.2.4 Subtask 4 – Electrical Engineering - Project Transition. The Contractor shall provide electrical engineering assistance for technical reviews, authorized service interruption (ASI) tracking / coordination for all projects and maintenance activities, power distribution units (PDU) load analysis, uninterruptible power supplies (UPS) load analysis, commissioning coordination / oversight / duties, assist the Government project managers in transitioning and closing out of all projects from the project team to the maintenance team, and provide maintenance recommendations for those projects. In addition, provide recommendations / review comments to the Government representative regarding improvements to energy efficiency to drive down the Power Usage Effectiveness (PUE) of the data centers in the maintenance and operations of existing systems, drafting SOW/PWS, cost estimates and acquisition package requirements for recommendations approved by the Government and review whole scale upgrades with a positive Return on Investment (ROI). It is estimated that eight (8) individual site visits annually will be required to support these subtasks. These services require access to classified information up to the Secret level and access to NIPR in order to review facilities reports and mission partner documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.2.5 Subtask 5 – Facility Documentation-Technical Writer. The Contractor shall fully maintain and update the library of all soft/hard copy DISA Facilities and Maintenance Standards as well as the data center facility equipment technical engineering specifications while continually update them for compliance with changing Core Data Center Requirements, DoD, Federal, local and industry standards and codes as well as the TIA-942 and UPTIME Institute documentation. The contractor will make recommendations regarding the current DISA Facilities Standards and technical engineering equipment specifications for update, correction, writing of new sections and deletion of erroneous/duplicative sections. These services require access to classified information up to the Secret level and access to NIPR in order to review facilities reports and mission partner documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.2.6 Key Positions - The Contractor shall provide the personnel to fill key positions with the minimum qualifications listed below. The evaluation of the key positions will consider education, engineering experience, data centers experience, and security clearance level (minimum SECRET).
6.2.6.1 Mechanical Engineer (Project Support) – Bachelor degree (or higher) in mechanical engineering from an ABET accredited college or university, five (5) year of experience in building mechanical systems for data centers and a minimum of two (2) years of experience commissioning building mechanical systems for critical infrastructures. Government prefers the engineers have a current Professional Engineering License. A copy of the license shall be provided upon request to the Government COR/ACOR. Mechanical engineer must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, Word and AutoCAD) and have a background in project management.
6.2.6.2 Electrical Engineer (Project Support) – Bachelor degree (or higher) in electrical engineering degree from an ABET accredited college or university, five (5) year of experience in electrical systems for data centers, minimum of two (2) years of experience commissioning building electrical systems for critical infrastructures and one (1) year of experience in electrical engineering studies (Easy Power or equivalent software program). Qualified personnel shall be familiar with building powers systems including uninterruptible power supplies (UPS) (500 KW or larger) and building generators (1MW or larger). Government prefers the engineers have a current Professional Engineering License. A copy of the license shall be provided upon request to the Government COR/ACOR. Electrical engineer must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, Word and AutoCAD) and have a background in project management.
6.2.6.3 Mechanical Engineer (Project Transition) – Bachelor degree (or higher) in mechanical engineering from an ABET accredited college or university, experience in computational fluid dynamics (CFD), TileFlow or equivalent software program, five (5) years of experience in energy engineering or energy management with a focus on energy conservation for critical facilities, experience with computerized maintenance management system (CMMS) and three (3) years of experience in building automation systems (BAS). The engineer is required to be a Certified Energy Manager (CEM) by the Association of Energy Engineers (AEE), Leadership in Energy and Environment Design (LEED) AP by the US Green Building Council or other national recognized equivalent program. The Government prefers the engineers have a current Professional Engineering License. A copy of the license and CEM certificate or LEED AP certificate shall be provided upon request to the Government. The mechanical engineer shall be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, and Word).
6.2.6.4 Electrical Engineer (Project Transition) – Bachelor degree (or higher) in electrical engineering from an ABET accredited college or university, five years of experience in energy engineering or energy management with a focus on energy conservation for critical facilities and experience with computerized maintenance management system (CMMS). The engineer is required to be a Certified Energy Manager (CEM) by the Association of Energy Engineers (AEE), Leadership in Energy and Environment Design (LEED) AP by the US Green Building Council or other national recognized equivalent program. The Government prefers the engineers have a current Professional Engineering License. A copy of the license and CEM certificate or LEED AP certificate shall be provided upon request to the Government. The electrical / energy engineer shall be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, and Word).
6.2.6.5 Facility Documentation-Technical Writer – Bachelor degree (or higher) in engineering or architecture from an ABET or NAAB accredited college or university, minimum of eight (8) year experience in engineering, architecture, or facilities management including experience with data centers and a minimum of five (5) year experience as a technical writer preparing specifications and engineering standards. Government prefers the engineers/architects have a current professional license. A copy of the license shall be provided upon request to the Government COR/ACOR. Engineer/architect must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, Word and AutoCAD) and have a background in project management.
Deliverables:
| - | Draft Performance Work Statements / Statements of Work |
| - | Cost Estimates |
| - | Engineering Technical Review Comments & Recommendations |
| - | Facility Survey & Trip Reports |
| - | Maintenance Recommendations |
| - | Engineering Studies/Reports |
| - | Project Transition & Close-Out Documents |
| - | Monthly Status Report |
6.3 Task 3 - Technical Requirements (TR): Environmental Services. Technical Requirements (TR) are initiated by DISA to resolve /address environmental issues. These task order requests will be a limited duration and limited in scope. The requirements are issued in the form of a TR Task Order that outlines the technical requirements. The Contractor must provide a technical approach, schedule and pricing for each TR Task Order. All TRs are firm fixed price and must be accepted/approved by the Chief, Engineering Branch (MPE2), COR or ACOR, and Contracting Officer (KO). The KO shall add these requirements to the contract by awarding a Task Order before the beginning of any work. These services require access to classified information/documents up to the Secret level in order to review facilities reports and documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.3.1. Subtask 1 - Environmental Support Services. The services include, but are not limited to, Planning and Documentation Services for the development, planning, facilitation, coordination, and documentation of and/or for environmental initiatives or mandates in areas of chemical, radiological, and/or hazardous materials; ISO 14001 Environmental Management System (EMS) and sustainable performance measure development; Environmental Assessment and Environmental Impact Statement preparation under the National Environmental Policy Act (NEPA); Endangered species, wetland, watershed, and other natural resource management plans; Archeological and/or cultural resource management plans; Environmental program and project management; Environmental regulation development and other environmental support services as required.
6.3.2. Subtask 2 - Environmental Training Services. These services are designed to aid agencies in training personnel in a variety of environmentally related subjects in order to meet Federal mandates and Executive Orders. Environmentally related training can be conducted on- or off-site using standard off-the-shelf, customized, or computer/web-based interactive courses. Examples of environmental training courses include: Asbestos awareness; Environmental management planning and operations and maintenance (O&M) planning; Asbestos Hazard Emergency Response Act (AHERA); Compliance with environmental laws/regulations; Comprehensive Environmental Response Compensation and Liability Act (CERCLA); Confined space training; Emergency response plans; Environmental audits, awareness, compliance, and management; Hazardous materials and waste (HAZMAT) training to include compliance, operation, packaging, handling, generators, and incident response; Hazardous waste operations and emergency response (HAZWOPER) training inclusive of transportation, storage and disposal; ISO 14001 Environmental Management Systems (EMS); Lead training to include awareness, inspecting, assessing, rehabilitation, and renovation; Mold (abatement, assessment); National Environmental Policy Act (NEPA); Occupational Safety and Health Administration (OSHA); Pollution prevention; Sustainable environmental practices; Water conservation; and other environmental training as required.
6.3.3 Subtask 3 - Remediation and Reclamation Services. Remediation services include, but are not limited to: Excavation, removal and disposal of hazardous waste; Site preparation, characterization, field investigation, conservation and closures; Wetland restoration; Emergency response clean up (ERC); Underground storage tank/above-ground storage tank (UST/AST) removal; Air monitoring; Soil vapor extraction; Stabilization/solidification, bio-venting, carbon absorption, reactive walls, containment, monitoring and/or reduction of hazardous waste sites, as well as unexploded ordnance removal; Remediation-related laboratory testing (e.g., biological, chemical, physical, pollution and soil testing) and other environmental remediation and reclamation services as required.
6.3.4 Minimum Labor Qualifications:
6.3.4.1 Project Manager / Engineering Technician – Minimum five (5) years of experience with performing project management and engineering technical support for facilities projects.
6.3.4.2 Environmental Engineer - Bachelor’s degree (or higher) in environmental engineering or a closely related field, such as civil, chemical, or general engineering from an ABET accredited college or university in and minimum of ten years of experience in environmental engineering. Government prefers the engineers have a current Professional Engineering License and board certification from the American Academy of Environmental Engineers and Scientists. A copy of the license and board certification shall be provided upon request by the Government COR/ACOR. Must be proficient with basic office automation software packages such as MS Project, Excel, PowerPoint, and Word and have a background in project management.
6.3.4.3 Industrial Hygienist – Bachelor’s degree (or higher) in engineering, chemistry, physics, or in a closely related biological or physical science from an accredited college or university and a minimum of four (4) years of experience as an industrial hygiene. Government prefers certification with American Board of Industrial Hygiene. A copy of the certification shall be provided upon request by the Government. Industrial hygienist must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, and Word).
6.3.5 Other Labor Categories – The labor categories identified above are not inclusive of all labor categories required to fulfill Task 3. The Contractor shall offer additional labor categories, to include, multiple category levels, associated with Task 3. The Contractor shall describe the characteristics of each category and level in terms of education, experience, and professional certification.
Deliverables:
| - | Technical Approach for each TR request |
| - | Pricing (Labor & ODC) for each TR request |
| - | Submittals as required for each TR request |
| - | Environmental Report/Recommendations as required by TR |
| - | Facility Survey & Trip Reports (if required) |
| - | Monthly Status Report |
6.4 Task 4 Technical Requirements (TR): Professional Engineering Services. Technical Requirements (TR) are initiated by DISA to resolve /address engineering issues. These task orders requests will be a limited duration and limited in scope. The requirements are issued in the form of a TR Task Order that outlines the technical requirements. The Contractor must provide a technical approach, schedule and pricing for each TR Task Order. All TRs are firm fixed price and must be accepted/approved by the Chief, Engineering Branch (MPE2), COR or ACOR, and Contracting Officer (KO). The KO shall add these requirements to the contract by awarding a Task Order before the beginning of any work. These services require access to classified information/documents up to the Secret level in order to review facilities reports and documentation. Classified information will be provided verbally or through hard copy reports/documentation.
6.4.1 Subtask 1 - Strategic Planning for Technology Programs/Activities. Services involve the definition and interpretation of high level organizational engineering performance requirements such as projects, systems, missions, etc., and the objectives and approaches to their achievement. Typical associated tasks include, but are not limited to, an analysis of mission, program goals and objectives, program evaluations, analysis of program effectiveness, requirements analysis, organizational performance assessment, special studies and analysis, and training.
6.4.2 Subtask 2 - Concept Development and Requirements Analysis. Services involve abstract or concept studies and analysis, requirements definition, preliminary planning, the evaluation of alternative technical approaches and associated costs for the development of enhancement of high level general performance specifications of a system, project, mission or activity. Typical associated tasks include, but are not limited to, requirements analysis, cost/cost performance trade-off analysis, feasibility analysis, developing and completing fire safety evaluation worksheets as they relate to professional engineering services, regulatory compliance support, technology/system conceptual designs, training, define interfaces and environments, collision avoidance analysis, perform plume impingement analysis, coupled load analysis, conduct spacecraft / satellite manifesting, and creating interface control documents.
6.4.3 Subtask 3 - System Design, Engineering and Integration Services. Services involve the translation of a system (or subsystem, program, project, activity) concept into a preliminary and detailed design (engineering plans and specifications), performing risk identification/analysis, mitigation, traceability, and then integrating the various components to produce a working prototype or model of the system. Typical associated tasks include, but are not limited to computer-aided design, e.g. CAD, design studies and analysis, design review services, shop drawing review services, submittal review services, conducting fire protection facility surveys, developing risk reduction strategies and recommendations to mitigate identified risk conditions, fire modeling, performance-based design reviews, high level detailed specification and scope preparation, configuration, management and document control, fabrication, assembly and simulation, modeling, training, analysis of single or multi spacecraft missions, and mission design analysis.
6.4.4 Subtask 4 - Test and Evaluation Services. Services involve the application of various techniques demonstrating that a system (subsystem, program, project or activity) performs in accordance with the objectives outlined in the original design. Typical associated tasks include, but are not limited to testing of a prototype, first article(s) testing, environmental testing, performing inspections and witnessing acceptance testing of fire protection and life safety systems as they relate to professional engineering services, independent verification and validation, reverse engineering, simulation and modeling (to test the feasibility of a concept), system, quality assurance, physical testing of the product system, training, receptions and inspection of Government Furnished Equipment / Satellite, conduct testing and safety audits.
6.4.5 Subtask 5 - Acquisition and Life Cycle Management Services. Services involve all of the planning, budget, contract and systems/program management functions required to procure and or/produce, render operational and provide life cycle support (maintenance, repair, supplies, engineering specific logistics) to (technology based) systems, activities, subsystems, projects, etc. Typical associated tasks include, but are not limited to operation and maintenance, evaluation of inspection, testing, and maintenance program for fire protection and life safety systems, program/project management, technology transfer/insertion, and training.
6.4.6 Subtask 6 - Construction Management and Engineering Services Related to Real Property. Services include construction management, engineering support, project management, and related professional services specifically pertaining to real property. The construction management approach utilizes one or more firms with construction, design, and management expertise to expand the customer agency's capabilities, so that the agency can successfully accomplish its program or project. The Contractor performing construction management services assumes the position of professional adviser to the customer agency. Customer agencies may utilize the construction manager as the principal agent to advise or manage the process over the project regardless of the project delivery method used. Construction management services include, but are not limited to, design phase support, procurement support, commissioning services, testing services, construction claims support, and post-construction engineering services.
The Contractor performing engineering services functions as an advisor to the Government to assist with executing engineering tasks associated with real property. Engineering services relating to real property include, but are not limited to, mechanical engineering, electrical engineering, fire protection engineering, forensic engineering, structural engineering, or any other specialized engineering services that are utilized in regards to real property. Authorized engineering tasks include: design reviews, shop drawing reviews, submittal reviews, inspection and testing services, witnessing acceptance tests of equipment and systems, commissioning, modeling and analysis, loss investigation, facility surveys, safety evaluations, research studies, risk mitigation strategy development or reviews, and other related technical consulting services. The Contractor performing engineering services shall not perform the construction of real property, nor be a named party under the construction contract. Project management services relating to a construction management or engineering effort are authorized.
6.4.7 Minimum Labor Qualifications -
6.4.7.1 Project Manager / Engineering Technician – Minimum five (5) years of experience with performing project management and engineering technical support for facilities projects.
6.4.7.2 Mechanical Engineer – Bachelor degree (or higher) in mechanical engineering from an ABET accredited college or university, five year of experience in building mechanical systems for data centers and mission critical equipment. Government prefers the engineers have a current Professional Engineering License. A copy of the license shall be provided upon request to the Government COR/ACOR. Mechanical engineer must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, Word and AutoCAD) and have a background in project management.
6.4.7.3 Electrical Engineer – Bachelor degree (or higher) electrical engineering degree from an ABET accredited college or university, five (5) year of experience in electrical systems for data centers and one (1) year of experience in electrical engineering studies (Easy Power or equivalent software program). Qualified personnel shall be familiar with building powers systems including uninterruptible power supplies (UPS) (500 KW or larger) building generators (1MW or larger). Government prefers the engineers have a current Professional Engineering License. A copy of the license shall be provided upon request to the Government ACOR/COR. Electrical engineer must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, Word and AutoCAD) and have a background in project management.
6.4.7.4 Civil (Structural) Engineer – Bachelor degree (or higher) in civil engineering or related field from an ABET accredited college or university, five year of experience in structural engineering for buildings and structures. Government prefers the engineers have a current Professional Engineering License. A copy of the license shall be provided upon request to the Government ACOR/COR. Structural engineer must be proficient with basic office automation software packages (such as MS Project, Excel, PowerPoint, Word and AutoCAD) and have a background in project management.
6.4.8 Other Labor Categories – The labor categories identified above are not inclusive of all labor categories required to fulfill Task 4. The Contractor shall offer additional labor categories, to include, multiple category levels, associated with Task 4. The Contractor shall describe the characteristics of each category and level in terms of education, experience, and professional certification.
Deliverables:
| - | Technical Approach for each TR request |
| - | Pricing (Labor & ODC) for each TR request |
| - | Submittals as required for each TR request |
| - | Facility Survey & Trip Reports (if required) |
| - | Monthly Status Report |
6.5 Other Requirements
6.5.1 Other Direct Costs (ODCs) – The Contractor may be required to purchase incidental tools, supplies, or materials to complete projects. Authorization for ODC purchases must be approved by the COR/ACOR in advance using the Purchase Authorization Request form. Typical ODCs include items such as hardware tools, software tools, and project specific materials and supplies. The Contractor must provide a breakout of the ODCs for each billing period. ODC expenses shall be reimbursed on a cost basis. See Attachment 2 – Purchase Authorization Request.
6.5.2 Travel – The contractor is required to travel to complete certain work projects. The Contractor shall manage travel arrangements. The Contractor shall submit a Travel Authorization Request (TAR) no later than 15 days prior to the planned travel date. The TAR shall be reviewed and approved by the COR/ACOR prior to the Contractor incurring allowable travel expenses. Authorized travel shall be billed against the reimbursable line of the contract in accordance with the Federal Acquisition Regulation Part 31. Travel receipts for all expenses including lodging, airfare, and rental cars must be provided with the invoice. Travel shall be reimbursed on a cost basis and limited to the Government travel rates. See Attachment 3 – Travel Authorization Request.
6.5.3 Off-Peak Work Hours – DISA MPE occasionally requires services during off-peak hours and/or on weekends in excess of 40 hours per week in order to complete time-sensitive and special projects. Off-peak and weekend work will be requested by the Contractor and approved by the COR/ACOR at least 48 hours in advance.
6.5.4 Phase-In / Phase-Out Transition Plan – The Contractor shall create a detailed transition plan to address both “phase-in” and “phase-out” of the contract. The “phase-in”, not to exceed 15 days, shall describe the Contractor’s strategy to ensure seamless continuity of current projects from the current contract to this contract. The “phase-out” strategy shall assist the Government in the transition of services from this contract to any follow-on Contractor and will be updated annually. The Contractor must agree to coordinate service transition with any follow-on Contractor to prevent service disruption during the transition. It is anticipated there will be a follow-on contract in place by the end of the period of performance of this contract and the transition period shall begin at the end of the final contract period. The existing contract will provide coverage for all the services described herein until one of the following occurs: the existing contract ends or is no longer required by the Government. The Contractor shall propose an exit strategy based upon these criteria, or provide an alternative plan.
7. Performance Standards
| Performance Standard |
| Acceptable Quality Level (AQL) |
| Method of Surveillance |
Tasks: 6.1, 6.2, 6.3, &
6.4 – Monthly Status Report, ensure correct and timely information availability
| Performance occurs with no required re-performance or re-work at least 80% of the time. Problems that occur are minor and are re-solved in a satisfactory manner. |
| 100% inspection of deliverable materials |
| Tasks: 6.2, 6.3 & 6.4 – Facility surveys and trip reports are technically correct, completed IAW standard document format. |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are re-solved in a satisfactory manner. |
| Periodic inspection of deliverable materials. |
| Subtask 6.1.1 - Integrated as- built drawings into the Master Drawings to ensure complete, correct, and timely information availability. |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials. |
Subtask 6.1.1 – SharePoint (DEPS) & network drive updates shall be technically correct and timely infor mation availability.
Performance occurs with no req uired re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner.
100% inspection of deliverable materials.
Subtask 6.1.2 – Sustain existing Master Drawings Files by incorporating as-built drawings to ensure complete, correct, and timely information availability.
Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner.
100% inspection of deliverable materials.
| Subtask 6.1.3 – Drafting CAD support for in house engineering design. |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials |
Subtask 6.2.1 – Mechanical Engineering project design and support. Engineering calculations, in-house designs, design reviews, draft SOWs/PWSs, cost estimates, and reports shall be technically correct
Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner.
100% inspection of deliverable materials.
| Subtask 6.2.2 – Electrical Engineering project design and support. Engineering calculations, in-house designs, design reviews, draft SOWs/PWSs, cost estimates, and reports shall be technically correct |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials. |
| Subtask 6.2.3 – Mechanical Engineering Project Transition. Technical reports, project transition & close-out documents, maintenance recommendations, design reviews, draft SOWs/PWSs, cost estimates, CFD models, energy efficiency recommendations, and reports shall be technically correct |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials. |
| Subtask 6.2.4 – Electrical Engineering Project Transition. Technical reviews, ASI tracking/coordination, project transition & close-out documents, maintenance recommendations, design reviews, draft SOWs/PWSs, cost estimates, PDU/UPS load analysis, energy efficiency recommendations, and reports shall be technically correct |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials. |
| Subtask 6.2.5 – Facility Documentation-Technical Writer. Maintenance, updates, and recommendations for DISA Facilities and Maintenance Standards and data center facility equipment technical engineering specifications. |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials. |
| Task 6.3 – TR Environmental Services Technical approach, recommendations and reports meets technical requirements |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials |
| Task 6.3 – TR Environmental Services. Site visit and start TR task order. |
| Site visit (if required) and TR task order begins within 30 days from award of contract modification. |
| Periodic inspection of TR process. |
| Task 6.3 – TR Environmental Services. Submittals as required by TR. |
| Performance occurs with no re-quired re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials |
| Task 6.4 – TR Engineering Services. Technical approach, recommendations and reports meets technical requirements |
| Performance occurs with no required re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials |
| Task 6.4 – TR Engineering Services. Site visit and start TR task order. |
| Site visit (if required) and TR task order begins within 30 days from award contract modification. |
| Periodic inspection of TR process. |
| Task 6.4 – TR Engineering Services . Submittals as required by TR. |
| Performance occurs with no re-quired re-performance or re-work at least 95% of the time. Problems that occur are minor and are resolved in a satisfactory manner. |
| 100% inspection of deliverable materials |
8. Incentives. Both positive and negative performance will be documented in past performance reports in the Contractor Performance Assessment Reporting System (CPARS), and as appropriate, will be taken into consideration for any potential follow-on work.
The Government will identify and communicate to the Contractor any services or deliverables that do not meet acceptable levels using the procedures identified in the Quality Assurance Surveillance Plan (QASP).
Any performance/deliverable determined to be unacceptable based on the quality of the work shall be reworked at no additional cost to the Government until deemed acceptable by the Government. Any performance/deliverable determined to be unacceptable based on late delivery or late performance shall result in a reduction in the contract price to reflect the reduced value of the deliverable or services performed.
A Key Position that remains vacant for more than 60 days will result in a reduction in the monthly contract price equal to the price of the vacant position until the position is filled.
9. Place of Performance
9.1 Base Services - Place of Performance is the DISA Denver, DISA MPE facility located at 6162 S. Willow Drive, Suite 200, Greenwood Village, CO 80111. Places of Performance may expand to other locations throughout the duration of this contract.
9.2 Base Services and Technical Requirements – Temporary travel and support at other DISA CONUS and OCONUS field activities may also be required. DISA CONUS and OCONUS field activities include, but are not limited to the following: Fort Meade, MD; St Louis, MO; Mechanicsburg, PA; Ogden, UT; Oklahoma City, OK; Montgomery, AL; Columbus, OH; San Antonio, TX; Pensacola, FL; Stuttgart, Germany; and Manama, Bahrain.
9.3 Alternate Place of Performance - Contingency Only. As determined by the Contracting Officer’s Representative (COR), Contractor employees may be required to work at an alternate place of performance (e.g., home, the Contractor's facility, or another approved activity within the local travel area) in cases of unforeseen conditions or contingencies (e.g., pandemic conditions, exercises, Government closure due to inclement weather, etc.). Non-emergency/non-essential Contractors shall not report to a closed Government facility. Contractor shall prepare all deliverables and other contract documentation utilizing Contractor resources. To the extent possible, the Contractor shall use best efforts to provide the same level of support as stated in the PWS. In the event the services are impacted, reduced, compromised, etc., the Contracting Officer or the Contractor may request an equitable adjustment pursuant to the Changes clause of the contract.
The Contractor shall provide sufficient on-site personnel to complete or continue critical work already in process or provide on-call response in accordance with the Performance Work Statement.
10. Period of Performance. One-Year Base Period with Four One-Year Option Periods
| Base Year: | May 15, 2017 – May 14, 2018 |
| Option Year 1: | May 15, 2018 – May 14, 2019 |
| Option Year 2: | May 15, 2019 – May 14, 2020 |
| Option Year 3: | May 15, 2020 – May 14, 2021 |
| Option Year 4: | May 15, 2021 – May 14, 2022 |
The phase-in transition period will not exceed 15 days. The Contractor is expected to be at 100 percent performance on 1 June 2017. As directed by the COR/ACOR, the Contractor shall continue performance in emergency or mission essential conditions.
Additionally, the Contractor may be required to account for the whereabouts of their personnel should this information be requested by the COR/ACOR.
Generally, this technical support shall be performed Monday through Friday excluding all Federal Holidays. Normal duty hours are 8 hours per day, not including vacation, sick, holiday and TDY time. Work days shall be scheduled to ensure coverage of DISA’s core hours of 9:00 am to 3:00 pm.. As stated in section 6.5.3 above, occasional work may be required during off-peak hours.
The Contractor must provide the Government with a means of 24 hour communications with Contractor personnel.
11. Delivery Schedule.
| PWS Task# |
| Deliverable Title |
| Format |
| Due Date |
| Distribution/Copies |
| Frequency and Remarks |
| 6.1, 6.2, 6.3, & 6.4 |
| Monthly Status Report |
| Microsoft |
Word/Excel (email submittal)
7 calendar days from the start of each month
| Standard distribution and Chief, Facilities Engineering |
| Monthly |
| 6.2, 6.3 & 6.4 |
| Facility Survey and Trip Report |
| Microsoft |
Word/Excel
| 30 calendar days from date of the site visit |
| Standard distribution and Chief, Facilities Engineering |
| Submitted after every site visit |
| 6.1.1 |
| Integrate As-Built Drawings (95%) |
| AutoCAD & PDF |
| 30 calendar days from date of the site visit |
| Chief, Facilities Engineering |
| Once per location, annually |
| 6.1.1 |
| Integrate As-Built Drawings (Final) |
| AutoCAD & PDF |
| 30 calendar days from receipt of 95% review comments |
| Chief, Facilities Engineering |
| Once per location |
| 6.1.2 |
| Sustain As-Built Drawings |
| AutoCAD & PDF |
| 30 calendar days from receipt of project as-built AutoCAD files. |
| Chief, Facilities Engineering |
| As requested by the Government Project Engineer |
| 6.1.3 |
| CAD support for in house engineering design |
| AutoCAD & PDF |
| 30 calendar days from request |
| Project Engineer and Chief, Facilities Engineering |
| As requested by the Government Project Engineer |
| 6.2.1 & 6.2.2 |
| Engineering calculations, draft PWS/SOW, cost estimates, in-house designs, design reviews, and SOW/PWS reviews |
| As Required |
| 30 calendar days from date of the request |
| Project Engineer and Chief, Facilities Engineering |
| As requested by the Government Chief, Facilities Engineering |
| 6.2.3 |