Attach_10_Question_and_Answers_16Jan17.docx
DOCX document 85 KB Posted
- Attached to
- Enhanced Mobile Satellite Services (EMSS) Global Logistical Services Management Contract (ELOG)
- Solicitation number
- HC101316R0014
- Issued by
-
Defense Information Systems Agency
About this file
This is a combined synopsis and solicitation for an indefinite delivery/indefinite quantity contract to provide enhanced mobile satellite services global logistical services management support. Key details include that the contract is a 100% set-aside for service-disabled veteran-owned small businesses to provide on-demand operational, logistical, training, program management, technical, and subject matter expert support services globally with a primary focus on distributed tactical communications system support. Field service representatives will commonly deploy overseas to support satellite-based push-to-talk services. The contract period of performance is a 5-year IDIQ from May 2017 to April 2022 with customer-funded requirements. Proposals are due by January 6, 2017 to the Defense Information Systems Agency for this firm-fixed price contract.
Attach 10 Questions and Answers
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED//FOR OFFICIAL USE ONLY
ELOG HC101316R0014 Questions & Answers Attachment 10
Question
Questions / Comments
RFP
Reference
Government Response
RFP
Change Required (Y/N)
| 1 |
| Clause states the successful offeror must have a final Top Secret Facility Clearance (FCL) from the Defense Security Service (DSS) Facility Clearance Branch (FCB) during the period of performance. |
Question: According to the DSS FCB, it takes an average of less than 30 days to upgrade a company from SECRET to TOP SECRET. In order to increase competition and improve opportunities for qualified SDVOSBs to perform the work, will the government consider bids from qualified SDVOSBs that have an approved SECRET FCL and use the time period from Contract award to the start of the period of performance (transition period) in order to process a TOP SECRET FCL per the DD-254 (attachment 8)?
| PWS Attachment 1, Section 12.2 |
| Yes. The RFP language in all applicable documents will be changed to read, “an offeror must be able to obtain a TOP SECRET facility clearance”. A TOP SECRET facility clearance will not be required at time of award, but must be obtained by 180 days after the contract effective date. |
Y
| 2 |
| Clause states in order to be eligible for award, the offeror must provide proof of a valid final Secret/Top Secret Facility Clearance (FCL) from the Defense Security Service (DSS) Facility Clearance Branch (FCB) with its proposal. |
Question: The Government indicates that a valid final Secret or Top Secret would be acceptable. In order to eliminate all doubt and remove conflict with other paragraphs within the PWS, will the government edit this clause to allow Offerors that have valid final SECRET FCLs to be eligible for award?
Addendums Attachment 9, Section D. ii. page 5 Yes. The RFP language in all applicable documents will be changed to read, “an offeror must be able to obtain a TOP SECRET facility clearance”. A TOP SECRET facility clearance will not be required at time of award, but must be obtained by 180 days after the contract effective date. Therefore, a SECRET FCL will be eligible for award.
Y
| 3 |
| Clause states offerors must present proof of a valid final Top Secret Facility Security Clearance (FCL) with the submission of their proposals. Non-conformance with these instructions may result in removal of the proposal from further evaluation. |
Question: Given the short timelines necessary to obtain final Top Secret FCL with appropriate awarded contract paperwork (DD254), is it the government's intent to limit competition only to SDVOSBs with existing TS facility clearances? In order to increase competition and potentially provide a better solution to EMSS users, will the Government consider allowing Offerors with valid SECRET FCLs to bid on the effort with the caveat that the awardee must obtain its final Top Secret prior to the performance start date?
Addendums Attachment 9, Section D. ii. page 5 Yes. The RFP language in all applicable documents will be changed to read, “an offeror must be able to obtain a TOP SECRET facility clearance”. A TOP SECRET facility clearance will not be required at time of award, but must be obtained by 180 days after the contract effective date. Therefore, a SECRET FCL will be eligible for award.
Y
| 4 |
| Clause states offerors must present proof of a valid final Top Secret Facility Security Clearance (FCL) with the submission of their proposals. Non-conformance with these instructions may result in removal of the proposal from further evaluation. |
Question: Will the government allow the Facility Clearance of Subcontractors to satisfy the TOP SECRET FCL requirement for the RFP?
Addendums Attachment 9, Section: D. ii.
The prime contractor is required to hold the facility clearance. The prime contractor must be able to obtain a TOP SECRET facility clearance. A TOP SECRET facility clearance will not be required at time of award, but must be obtained by 180 days after the contract effective date.
Y
| 5 |
| Question: If the three positions that require TS-SCI clearance are subcontracted to partners / teammates that have an active TOP SECRET FCL, will the government allow the Facility Clearance of those Subcontractors to satisfy the TOP SECRET FCL requirement for the RFP? |
PWS Attachment 1, Section 12.2 – 12.3
| No, however see the revised FCL requirement. |
| N |
| 6 |
| Clause states Quality Assurance is critical to ensure accurate and timely delivery of all products required under this contract, and to ensure that all items perform as required. Contractor shall be certified ISO-9001:2008 for the delivery of all items required by EMSS. |
Question: Given that this is a 100% SDVOSB set aside contract and that the ISO 9001:2008 certification process is normally something associated with larger businesses, will the government allow for the ISO-9001:2008 certification of partners and subcontractors to satisfy the ISO9001:2008 requirement for this effort?
PWS Attachment 1, Section 6.2.7
| Yes |
| N |
| 7 |
| The Government references including offeror information on the SF 1449, but one was not included in the solicitation documents. Will the Government please provide a SF 1449 for this effort? |
| Attachment 9, FAR 52.212-1, page 1 |
| No. The SF 1449 is not applicable when using the combined synopsis/solicitation. Solicitation states on page 1, paragraph (1), it is in accordance with the format in Subpart 12.6. (12.603(b)). Reference to SF 1449 has been removed from RFP. |
Y
| 8 |
| The Government requests the offeror’s OCCI Mitigation Plan both in Volume II – Technical, and Volume V – Contract Documentation. Will the government please confirm the OCCI Mitigation Plan is only required to be submitted once, and within Volume V – Contract Documentation? Offerors may still address their lack of OCCIs or reference their OCCI Mitigation Plan in Volume II – Technical, but with the limited technical page count it would be counterproductive for the Government to require offerors to submit the OCCI Mitigation Plan itself within the technical volume. |
| Attachment 9, (viii) Proposal Organization, (B) Volume II, Technical; (E) Volume V, Contract Documentation 7,12 |
| Yes, the OCCI Mitigation Plan is excluded from page count and may only be submitted once. |
| N |
| 9 |
| Will the Government please increase the page limit for Volume II – Technical by ten pages, to a total limit of 35 pages? 25 pages is an extremely limited space to provide all the requested technical information, as well as to fully address all the requirements for the sample task order. An increase of ten pages would enable a more thorough technical response while still addressing all sample task order requirements. |
| Attachment 9, (vi) Table 1, Proposal Organization, 6 |
| Yes. The new page limit for Volume II is changed from 25 pages to 35 pages. |
Y
| 10 |
| The Government states “2. You must provide completed pricing information in the CLIN spreadsheet.” This is usually provided in Section B, however, no Section B was included in the solicitation documents. Will the Government please provide a Section B for this effort? |
| Attachment 9, (E) Volume V, Contract Documentation 12, page 12 |
| A combined synopsis/solicitation does not have Section B. Attachment 2 are spreadsheets for Labor Rate Tables. |
N
| 11 |
| "...In order to be eligible for award, the offeror must provide proof of a valid final Secret/Top Secret Facility Clearance (FCL) from Defense Security Services (DSS) Facility Clearance Branch (FCB) with its proposal....Offerors must present proof of a valid final Top Secret Facility Security Clearance (FCL) with the submission of their proposals."cognizant Defense Security Service representative, Mr. Juan Carillo, he informed us that the Attach_9_Addendums document section referring to Facility Clearance Requirements should be changed as follows regarding Secret and or Top Secret statements: ADDENDUM TO 52.212-1, (ii) should read as follows: "...In order to be eligible for aware, the offeror must be able to obtain a valid final Secret/Top Secret Facility Clearance (FCL) from Defense Security Services (DSS) Facility Clearance Branch (FCB) with its proposal....Offerors must be able to obtain a valid final Top Secret Facility Security Clearance (FCL) with the submission of their proposals." |
The reason for this proposed change is due to the fact that a prospective contractor cannot apply for its own facility clearance, the procuring activity or cleared prime contractor must submit a request to clear the prospective bidder. This can be done via either a signed and completed DD Form 254 or letter from the procuring activity or cleared prime contractor requesting the bid validating the need for the clearance.
It would seem that requiring a Top Secret Facility Clearance at the time of submission of a bid significantly limits the number of Service Disabled Veteran Owned Small Businesses able to participate and gives an unfair advantage to contractors currently executing contracts that have a Top Secret FCL requirement currently employs personnel with Top Secret clearances and maintains them on our JPAS account, however we don’t currently have a contract that requires a Top Secret FCL. Our DSS representative indicated that “contractor name” has in place all the necessary requirements to upgrade our FCL from Secret to Top Secret. We respectfully ask that you consider this change to the wording in Attachment 9 and the corresponding change to the DD254.
| Attachment 9, Addendums to 52.212-1, (ii), page 5 of 31 |
| The RFP language in all applicable documents will be changed to read, “an offeror must be able to obtain a TOP SECRET facility clearance”. A TOP SECRET facility clearance will not be required at time of award, but is expected to be obtained by 180 days after the contract effective date. Therefore, a SECRET FCL will be eligible for award. |
Y
| 12 |
| . Additional Follow-up : |
We will be forced to sever the relationship in pursuing EMSS if we are forced to have a Top Secret Facility Clearance at the time of offer as opposed to during contract performance.
“Contractor name” is not at all suggesting that we cannot fulfill the requirement to obtain and maintain a TS FCL. On the contrary, our DSS Representative stated that we have everything in place to ensure upgrade to a TS FCL as soon as we have a sponsoring contract. He also counseled that it is not possible to get one for this contract without being awarded this contract. “Contractor name” has current Secret FCL and employees with Top Secret clearances.
Our position is that it is a significant limiter to competition if the offeror must have a final TS FCL at bid submission rather than during contract performance.
Further, Section 6.8 in the PWS reads, in part:
The initial start-up period will be established on a per task order basis after award and shall be completed six months after award of the basic contract or task order whichever occurs first… We ask that you amend the Addendums to the Instructions to Offerors as suggested below.
ADDENDUM TO 52.212-1, (ii) to read as follows:"...In order to be eligible for award, the offeror must be able to obtain a valid final Secret/Top Secret Facility Clearance (FCL) upgrade from Defense Security Services (DSS) Facility Clearance Branch (FCB) within the 6 month transition period....Offerors must be able to obtain a valid final Top Secret Facility Security Clearance (FCL) upgrade within the 6 month transition period”
PWS
Section 6.8 Yes. The RFP language in all applicable documents will be changed to read, “an offeror must be able to obtain a TOP SECRET facility clearance”. A TOP SECRET facility clearance will not be required at time of award, but is expected to be obtained by 180 days after the contract effective date. Therefore, a SECRET FCL will be eligible for award.
Y
| 13 |
| Solicitation is missing pertinent DFARS 225.3 clauses for contracts performed outside the US. Will the solicitation be amended to include these clauses? |
RFP
Page 2 of RFP shows 10 clauses included for DFARS 225. Please note among the DFARS 225 clause(s) is 252.225-7040, Contractor Personnel Supporting U.S. Armed Forces Deployed Outside the US.
N
| 14 |
| Is DBA insurance included in the ODC line or is it to be incorporated into the FFP labor rate? |
| N/A |
| DBA insurance will be included in the ODC line at the task order level. |
| N |
| 15 |
| Sample Task Order related: Is current training material to be provided as GFE? Is the TO labor rate table missing hours for project manager and logistics analyst lead? (there is tasking for those rates in the SOW but no hours allowed). There are no Contractor site hours stated for the FSRs – are they intended to be either deployed or on leave the entire 12 months? |
| Attachment 2 |
| Current training material will be provided as GFI. Reference Attachment 2, Sample Task Order tab. Only the labor categories and designated locations (e.g., Government Site or Contractor Site) with hours assigned to them by the Government are to be used to accomplish the work within the Sample Task Order PWS. Offerors are only required to input the applicable hourly labor rate based on the Government-selected labor categories and corresponding hours assigned. The hourly labor rates must not exceed the offeror’s ceiling rates for the applicable period of performance (e.g., Year 1). The summation of the labor category totals plus the provided ODC of $500,000 (e.g., total proposed price) will be the only price factor considered and evaluated for the Sample Task Order (e.g., there is no need to consider/factor-in leave or any other deployment status into the price). Moreover, Offerors should only use or reference these Government-selected categories when completing the technical/management aspect of the Sample Task Order proposal. |
N
| 16 |
| There is no format stated for the Vol I, IV, and V – is either word or pdf acceptable? |
| Vol I, IV, and V |
| Word or PDF is acceptable |
N
| 17 |
| Will an SF1449 be provided as an attachment to the solicitation? There is conflicting direction in attachment 9 regarding the SF1449 |
| Page 12 |
(E) 1 and 2
No. The SF 1449 is not applicable when using the combined synopsis/solicitation. Solicitation states on page 1, paragraph (1), it is in accordance with the format in Subpart 12.6. (12.603(b)). Reference to SF 1449 has been removed from RFP.
Y
| 18 |
| Are CDRL DD1423s are going to be provided for the deliverables stated in the PWS? |
| N/A |
| No |
N
| 19 |
| Are the same/duplicative past performance reference sheets to be included in Vol IV (see attach 9 pg 11 (D) Vol IV) and Vol V (see attach 9 pg 12 (E) Vol V #5)? |
Attachment 9, Vol IV, Vol V It refers to the same reference sheets and is only required to be submitted once.
N
| 20 |
| There are conflicting statements regarding COMSEC. DD254 states no COMSEC required but PWS Task 7, 6.7.3 and 6.7.4 state COMSEC requirements. |
PWS
Task 7, 6.7.3 and 6.7.4 The offeror must be able to comply with COMSEC storage laws and regulations. The offeror must be able to store and ship COMSEC. These requirements will not be enforced at time of contract award, but are expected to be achieved by 180 days after contract effective date. The applicable RFP documents will be updated accordingly.
Y
| 21 |
| Is Ref 10K in the DD254 Block 13 continuation sheet correct or should it be deleted and replaced information regarding access to SPIR /JWICS at Gov’t site? |
| DD 254 |
| Yes; corrections made. |
| Y |
| 22 |
| No clauses or instructions for payment/invoices instructions; subcontracting; travel costs; and payment for overtime. Does the Gov intend to incorporate additional clauses into the solicitation to cover these topics? |
| RFP and Attachment 9 |
| Clauses 52.212-4 and 52.219-14 are included in the solicitation which address payment/invoice instruction as well as subcontracting. |
Pricing for all future contract actions (including, but not limited to proposal and billing of future task orders, modifications) will be firm-fixed-price (FFP) and restricted to the labor categories and fully burdened labor rates established in the offeror’s proposed FFP Schedule of Rates. The use of uncompensated overtime is not encouraged, see FAR 37.115-2(a). However, if the offeror’s proposed labor rates are adjusted for uncompensated overtime and this practice is supported by the offeror’s accounting practices, the offeror must provide the supporting data in accordance with FAR 52.237-10. The offeror shall indicate within the price proposal if uncompensated overtime will be used and also include a copy of its policy addressing uncompensated overtime.
Travel invoicing instructions have also been added to the PWS.
No additional clauses are expected to be incorporated before the proposal due date.
N
| 23 |
| Does the gov intend to and/or reserve the right to award the sample TO as proposed? |
| N/A |
| No. The Sample Task Order will not be awarded. |
N
| 24 |
| Find out if there is an incumbent contractor currently performing these services or if this is a new requirement. If there is an incumbent, could you please provide the contract number? |
| N/A |
| Yes. HC104712D4011. |
| N |
| 25 |
| The Government clearly requires through the PWS for the contractor to support all EMSS services and devices. However, sections 6.1.15, 6.5.10, 6.5.12, 6.6.2, and 6.6.10 make specific restricted references to DTCS, only one technology in the larger EMSS portfolio. Will the Government reword these 5 sections to incorporate all EMSS products to be consistent with the rest of the PWS, and to allow for contractor responsibility on new technologies which may be incorporated into the EMSS program over the life of the contract? |
Attachment 1, PWS Para 6.1.15, 6.5.10, 6.5.12, 6.6.2, and 6.6.10, page 3, 7, 8
| The PWS sufficiently covers all EMSS services and devices as presently written. Specific sections elaborate on the most common service presently requiring support, DTCS |
| Y |
| 26 |
| Factor 1, Subfactor 1, c) in Attachment 9 (p. 14) refers to Task 6 as “CENTCOM Liaison Subject Matter Expert (SME) Support.” Attachment 1 – PWS (Para 6.6, p. 8), however, refers to Task 6 as “Highly Qualified Expert (HQE)/Subject Matter Expert (SME) Support.” Will the Government please clarify the proper name for Task 6 in attachments nine and one? |
| Attachment 1 , page 8, PWS Para 6.6; Attachment 9, page 14 |
| Attachment 9 administrative error has been corrected to “Highly Qualified Expert (HQE)/Subject Matter Expert (SME)”. |
Y
| 27 |
| To ensure quality assurance is adequately addressed during performance of the contract, will the Government require that offerors supply proof of their ISO 9001:2008 certification with their proposal? |
Attachment 1, PWS Para 6.2.7, page 5
| Yes. Proposals will be evaluation in accordance with the stated evaluation criteria in the solicitation. Proposal preparation instructions and requirements are contained in Addendum 52.212-1. |
| Y |
| 28 |
| The Government makes multiple references to supporting missions in the USCENTCOM AOR including Afghanistan and Iraq, and similarly in this section addresses the need for experience and compliance with Theater Business Clearance (TBCs). However, the Government does not address the need for compliance of Host Nation business and labor laws including commercial business licenses, corporate registrations with partner nations, and other prerequisite conditions before US companies can perform in many USCENTCOM countries specifically mentioned in the RFP. Will the Government incorporate a requirement for the contractor to demonstrate compliance with these Host Nation prerequisite conditions? |
| Attachment 1, PWS Para 6.2.9 |
| Proposals will be evaluation in accordance with the stated evaluation criteria in the solicitation. |
| N |
| 29 |
| The Government states that “The Contractor shall support the customer in all technical aspects of the intelligence reporting system and provide guidance and advice on utility options.” Will the Government please clarify what is meant by the “intelligence reporting system?” Does the Government mean command and control (C2), or a Common Operating Picture (COP)? |
| Attachment 1, PWS Para 6.5.7 |
Offerors may assume “intelligence reporting systems” are command and control (C2) or like systems. The intent of this requirement is for the contractor to be able to discern information from common C2 or like systems and recommend to the Government ways to best use the fielded capability (for example, DTCS) as a result of the information being produced by the C2 system.
N
| 30 |
| The Government is requesting work to be completed in Afghanistan (PWS Para 6.5.9). In order to successfully perform these services, the contractor MUST have an Afghanistan business license. Please be advised that the transition of this contract poses a serious risk to the Government if the contractor does not have this necessary license at the time of award. Will the Government consider incorporating a requirement for the contractor to have an active Afghanistan business license at the time of proposal? |
Attachment 1, PWS Para 6.5.9
| Proposals will be evaluation in accordance with the stated evaluation criteria in the solicitation. |
| N |
| 31 |
| The requirement “…to employ educated…to mean at least a bachelor’s degree….” does not seem consistent with Attachment 3, Personnel Qualifications, which describes each labor category in functional and technical terms which neither require nor imply a need for a bachelor’s degree to meet the labor category descriptions, and successfully perform those functions. Is it the Government’s intent that every labor category require a bachelor’s degree? To which labor categories is the Highly Qualified Expert (HQE)/Subject Matter Expert (SME) (para 6.6) to apply? Our experience is that college degrees do not equate to ELOG HQE/SME qualifications, capability, or performance. We request that the Government reconsider the requirement for bachelor’s degrees. |
Attachment 1, PWS Para 6.6.4, Attachment 3, Personnel Qualifications, Attachment 1
| Reference Attachment 6, “PWS”, article 6.6.4 which read, “The Contractor shall employ highly-trained, educated, and experienced personnel” is replaced with new language that does not stipulate the requirement of any degree, only experience consistent with the description provided in Attachment 3. In this instance the Highly Qualified Expert (HQE)/Subject Matter Expert (SME) pertains to the COCOM Liaison position as described with Attachment 3 as amended. |
| N |
| 32 |
| These sections seem to require COMSEC, however the DD254 (Attachment 8) does not require COMSEC. Will the Government please clarify? |
Attachment 1, PWS Para 6.7.3 and 6.7.4 The offeror must be able to comply with COMSEC storage laws and regulations. The offeror must be able to store and ship COMSEC. These requirements will not be enforced at time of contract award, but are expected to be achieved by 180 days after contract effective date. The applicable RFP documents will be updated accordingly.
Y
| 33 |
| The Government’s evaluation criteria demonstrates the high importance of Past Performance. However, by allowing a “Acceptable / Not Acceptable” wherein a “No Response” is counted as an “Acceptable” score, prospective bidders are incentivized not to respond to the Government’s request for Past Performance at all since doing so guarantees an “Acceptable” rating. Will the Government change the evaluation criteria to a “Color Rating” similar to the Technical and Management sections so as to not reward a lack of response, and to give a weighted consideration for the strength of the contractor’s Past Performance references? |
| Attachment 5, Ratings, |
Table 3, Ratings for Past Performance
| No. It is the Government’s discretion to evaluate Past Performance as Acceptable/Not Acceptable. |
| N |
| 34 |
| The focuses exclusively on DTCS, whereas other EMSS devices are being fielded and supported today in the areas listed in the STO. Will the Government widen the language to encompass all EMSS products/services to better align with known requirements of these theaters and to make the contractor’s STO response more relevant? |
Attachment 6, STO PWS
| The PWS sufficiently covers all EMSS services and devices as presently written. Specific sections elaborate on the most common service presently requiring support, DTCS |
| N |
| 35 |
| In the STO PWS, the Government refers to Task 6 both as “Highly Qualified Expert (HQE)/Subject Matter Expert (SME) Support” and as “CENTCOM Liaison Subject Matter Expert (SME) Support.” Will the Government please clarify the proper name for Task 6 in the STO PWS? |
Attachment 6
STO PWS,
Task 6, Page 3, 6
Administrative error has been corrected to “Highly Qualified Expert (HQE)/Subject Matter Expert (SME)”.
Y
| 36 |
| This section makes reference to “Theater Business Clearances” which are processes implemented by a US Combatant Command (i.e. USCENTCOM), however does not speak to the requirements imposed by Host Nations such as business and labor laws including commercial business licenses, corporate registrations with partner nations, and other prerequisite conditions. Since this STO specifically seeks to gauge the contractor’s ability to perform in Afghanistan and Iraq, will the Government require the contractor to demonstrate its compliance with Host Nation laws in these countries? |
Attachment 6, STO PWS Para 6.1.f
Proposals will be evaluated in accordance with the evaluation criteria specified in the solicitation. Proposal preparation instructions and requirements are contained in Section L of the solicitation.
N
| 37 |
| In the STO PWS, the Government refers to “Transition Support” both as Task 7 (p. 7) and as Task 8 (p.2). Will the Government please confirm that Transition Support is Task 7 in the STO PWS? |
Attachment 6, STO PWS, Transition Support Page 2, 7
The labeling is correct as written. “Task Area 8”, as referenced under the “Scope” section within the Sample Task Order PWS, is provided to sufficiently map Task 7, “Transition” back to the parent PWS (Attachment 1).
N
| 38 |
| This section makes reference to Para 12.1, which does not exist. Will the Government please clarify? |
Attachment 6, STO PWS, Para 13.3 Reference to paragraph 12.1 is removed and paragraph 13.3 updated to read “not applicable”.
Y
| 39 |
| Portions of block 13 on page two of Attachment 8 are cut-off and require the user to scroll while using Adobe to view all the information. Will the Government please reformat so that all the contents for block 13 are visible, perhaps by moving the cut-off portion onto the continuation page on page three? |
Attachment 8, DD 254, Block 13
| No |
| N |
| 40 |
| We do not understand the rationale for the Government adding the total cost from the Sample Task Order and the full 5 year (+ 6 month option) IDIQ rate table for the total price consideration. This effectively treats the Sample Task Order as if it were another option period on the master contract, it does not put any significant weighted consideration for the Offeror’s price response to the Sample TO. Typically a sample TO is the evaluated criteria and the IDIQ rate table is considered separately. Will the Government please clarify its intent? |
Attachment 9, Addendum to 52.212-2(a), Factor 3, Price, (a) and (c) Page 15, 16
| The sample task order is not another option period and will not be awarded. For evaluation purposes, it is included in Factor 3. The sample task order is also included in the evaluation for the technical/management Factor 1 |
| Y |
| 41 |
| The language in the referenced FAR clause says that, “The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement,” but does not speak to the incorporation of the Sample Task Order for evaluation or price consideration. The language on page 16 says that the evaluated price will also include the Sample Task Order. Please de-conflict and clarify. |
Attachment 9, 52.212-2 (b), Addendum to 52.212-2(a), Factor 3: Price, (a) and (c) Page 12, 15, 16
Subparagraph (b) as the title specifies it is referring to options. The overarching price evaluation under Factor 3 addresses total evaluated price and all elements which are included: “The total evaluated price is the sum of the proposed labor rates for each labor category multiplied by the corresponding estimated hours for all five years, the optional 6 month extension period, and the price of the Sample Task Order (reference HC1013-16-R-0014, Attachment 6).”
Y
| 42 |
| The Government states, “Contractor-proposed labor categories must be cross mapped to the Government-provided labor categories.” The Government’s intent is unclear. If the contractor is proposing a new labor category (including price in Attachment 2 and description in Attachment 3), why / how is the contractor to cross-map into an existing Government-provided labor category? What is the Government expecting from a “cross-map” to an existing labor category if the contractor is proposing a new technical skill set and price? |
Attachment 9, Addendum to 52.212-2(a), Factor 3: Price, (b)
| “Contractor-proposed labor categories must be cross-mapped to the Government-provided labor categories” means offerors may use their own corporate unique titles to satisfy the labor category descriptions specified by the Government, the offeror just needs to sufficiently articulate their category relative to ours. |
| Y |
| 43 |
| Will the Government please clarify if a written cost narrative is required? If so - what content should be included in the narrative; and if no written cost narrative is required, will the Government please clarify where offerors are to include their pricing notes? |
Attachment 9, Addendum to 52.212-1(b), (C) Volume III - Price Page 8, 9
Attachment 9, Addendum 52.212-1(b), paragraph 2.1.3.3 states that offerors are permitted to submit an addendum when proposing. There is no page limitation for the Price, Volume III, which may include a cost narrative with content determined by the offeror which supports Price in Word or PDF format.
N
| 44 |
| In Technical Sub-Factor 1 – Remote Mobile Telecommunications Services Management, the Government requires only that offerors demonstrate their knowledge of mobile systems and devices, and that knowledge of satellite-based systems is preferred. 100% of the systems under this contract are satellite based. Knowledge of satellite systems should not be merely preferred, but rather required. Further, 100% of the satellite systems for the EMSS office are on the Iridium constellation, and experience with Iridium satellites specifically should also be required. Will the Government consider incorporating these requirements? |
Attachment 9, Addendum to 52.212-2(a), Sub-Factor 1 – Remote Mobile Telecommunications Services Management Expertise
| No |
| N |
| 45 |
| The Government states that offerors for whom past performance information is not available will receive an “acceptable” rating for the past performance factor. This defeats the purpose of including a past performance volume. Will the Government consider revising the evaluation criteria for past performance to make the submission of relevant past performance references a criteria for receiving an “acceptable” ranking.? |
| Attachment 9 - Addendum to 52.212-2(a), Sub-Factor 1, Remote Mobile Telecommunications Services Management Expertise |
| No. It is the Government’s discretion to evaluate Past Performance as Acceptable/Not Acceptable. |
| N |
| 46 |
| First paragraph states "The total evaluated price is the sum of the proposed labor rates for each labor category multiplied by the corresponding estimated hours for all five years, the optional 6 month extension period, and the price of the Sample Task Order." However, the last paragraph on the same page states "The offeror’s total evaluated price will be calculated by adding the proposed price of the base and all option years to the proposed price of the Sample Task Order." |
Question: Please clarify if the optional 6 month extension period, and the price of the Sample Task Order are included in the total evaluated price?
| Attachment 9, page 13, paragraph b(1) |
| Yes, the total evaluated price includes the sum of the proposed labor rates for each labor category for all 5 contract years, plus the optional 6 month extension period plus the total price of the Sample Task Order. |
The last sentence in Factor 3, Price, subparagraph (c), has been removed.
Y
| 47 |
| The Summary tab of the price spreadsheet provided in RFP Attachment 2 includes formulas that automatically sum the prices for the base and all option years. However, this does not include the optional 6 month extension period, and the price of the Sample Task Order. This conflicts with the language in RFP Attachment 9, page 16, first paragraph. |
Question: Please confirm that the formulas in the Summary Tab of the Attachment 2 spreadsheet are correct.
| Attachment 2 |
| Attachment 2 spreadsheet formula has been corrected |
| Y |
| 48 |
| The labor rate category description for the COCOM Liaison position uses the term "incumbent" several times. |
Question: Please confirm that the term "incumbent" does not refer to the incumbent contractor.
Attachment 3, Page 3, 4 The use of the term “incumbent” means the “[individual] holder of the position” and does not mean the incumbent contractor (company).
N
| 49 |
| Will deployed contract personnel have access to firearms when “alongside U.S. Forces deployed in an operational combat zone and/or support area”? |
| N/A |
| Since this contract’s inception in 2010, no task order has held this requirement. |
| N |
| 50 |
| What are the strategic locations within Europe, Asia, and Africa that are currently supported or may be supported on this new effort? |
| Section 6.6.3 |
| In addition to Middle East nations, strategic locations may include (but are not limited to) Germany, Ukraine, Poland, Korea, Japan, Australia, Canada, and the entire continent of Africa. |
N
| 51 |
| Will routine medical care and other basic life support services be authorized through a Theater Business Clearance for contract employees on long term deployments? |
| N/A |
| Yes |
| N |
| 52 |
| Will this contract be Defense Priorities and Allocation System (DPAS) rated for any required procurement activity? |
| Section 6.2 |
| At time of award this contract will not be DPAS rated, but future task orders may be rated pursuant to customer requirements. |
N
| 53 |
| Will the government please clarify how hardship and hazard pay should be captured in the cost proposal? |
| N/A |
| Hardship and hazard pay are included as an ODC CLIN and the Government has provided plug numbers for those CLINs in the pricing attachment. |
| N |
| 54 |
| Security Requirements. The Contractor shall not divulge any information about files, data, processing activities or functions, user IDs, passwords, or other knowledge that may be gained, to anyone who is not authorized to have access to such information. The Contractor/contract personnel shall abide by all Agency rules, procedures, and standards of conduct. All Contractor personnel (CONUS or OCONUS) assigned to this task shall be U.S. citizens and be able to possess at least a SECRET or INTERIM SECRET security clearance, based on a National Agency Check Investigation that is no older than three years to obtain the required Common Access Card (CAC). The Contractor personnel must be able to obtain and maintain a SECRET clearance. |
Attachment 1 – PWS Section 12
Y
| 54 |
| (continued) |
The PWS states that All contractor personnel shall have a minimum Interim Secret or Secret clearance based on a NACI investigation that is no older than 3 years, to obtain a CAC.
a. The NACI investigation does not support adjudication for a Secret clearance, how will this adjudication be made based on the NACI?
b. Will the government sponsor and submit the NACI investigation for each contractor? Industry does not have that capability.
c. If the government will sponsor and submit the NACI, how will Industry be notified of the results; favorable or unfavorable?
d. How will Industry know if the contractor is within the 3-year timeframe identified in section 12, for issuance of the CAC?
| PWS |
| a. DISA ISC Security Office will make this determination. |
b. Yes, if industry doesn’t have the capability. Note: Contractor supporting this effort should have the capability to submit NACI investigations.
c. Notified by COR or designated representative.
d. Industry will be notified at a minimum of 30 days of CAC expiration.
N
| 55 |
| States all personnel need to obtain and maintain a Secret clearance; if the majority of the work is Unclassified; why is there a need for all personnel to have a Secret clearance? |
a. Will the government identify the specific positions within the contract identified that need a Secret Clearance verses those that only need a NACI for a CAC?
| Section 12.1 |
| For purposes of accessing SIPRnet and gaining needed access to mission information, etc., all personnel need to have a secret clearance. |
N
| 56 |
| The PWS asks for verification of a Top Secret Facility Clearance; what is an acceptable form of verification? |
| PWS |
| The Offeror shall provide an official notice from their cognizant Defense Security Service representative stating their facility clearance or otherwise provide an official DSS Point of Contact for whom the Government can validate this status. |
N
| 57 |
| Will this contract require compliance with Department of State Regulations regarding overseas special pay types, such as danger & hardship pays. If so, is this part of ODC funding? |
| N/A |
| All applicable regulations will be followed. Danger and hardship pay will be funded as ODCs as applicable. |
N
Is the cost of DBA insurance included in the ODC plug provided by the gov’t.
| N/A |
| Yes and for the Sample Task Order. |
N
| 59 |
| 25-page limit for Volume II |
Request increased page allotment for Volume II to 40 pages. Purpose: need more space to thoroughly address all requirements within the Instructions and Evaluation Criteria Attachment 9, Addendum Table 1, Proposal Organization The new page limit for Volume II is changed from 25 pages to 35 pages.
Y
| 60 |
| 6-page limit for Volume IV |
Request 1 additional page to provide an introduction page within Volume IV, Past Performance. Purpose: provide page allotment to show relevancy coverage across all three PP citations aligned to all PWS requirements Attachment 9, Addendum Table 1, Proposal Organization Page limit for Volume IV has been changed to allow 6 pages.
Y
| 61 |
| Font Size |
Request Government allow smaller font size of 10 point within tables and font size no smaller than 8 point for graphics to allow bidders to better address all requirements. All fonts will be readable at these sizes.
Attachment 9, Addendum B, Volume II Instructions Font Size
| No |
| N |
| 62 |
| Would the Government please provide the SF1449? |
| Attachment 9, Addendum |
E.1 Volume V Instructions No. The SF 1449 is not applicable when using the combined synopsis/solicitation. Solicitation states on page 1, paragraph (1), it is in accordance with the format in Subpart 12.6. (12.603(b)). Reference to SF 1449 has been removed from RFP.
N
| 63 |
| Functional Performance Criteria is checked; however, no functional performance criteria are provided within Attachment 7, QASP |
Request Functional Performance Criteria is included within the QASP in order to properly address the 508 Accessibility requirements within Volume V.
Attachment 9, Addendum & PWS 15 E.1 Volume V Instructions 508 Accessibility
| Attachment 7, paragraph 5, requirements set forth in Table |
| Y |
| 64 |
| Afghanistan Business License requirement is missing. |
Do we provide proof of our Afghanistan Business License within Volume V?
Attachment 9, Addendum E.1 Volume V Instructions
| Proposals will be evaluated in accordance with the evaluation criteria specified in the solicitation. Proposal preparation instructions and requirements are contained in 52.212-1 of the solicitation. |
| N |
| 65 |
| Theater Business Clearance Experience |
Do we provide the Government proof of a Theater Business Clearance and proof of current delivery in austere environments along combat personnel within Volume V?
PWS
6.2.9 Proposals will be evaluated in accordance with the evaluation criteria specified in the solicitation. Proposal preparation instructions and requirements are contained in 52.212-1 of the solicitation.
N
| 66 |
| ISO 9001:2008 Requirement |
Does we provide the Government our current ISO 9001:2008 Certificate within Volume V?
Attachment 9, Addendum &
PWS
E.1 Volume V Instructions 6.2.7
| Proposals will be evaluated in accordance with the evaluation criteria specified in the solicitation. Proposal preparation instructions and requirements are contained in 52.212-1 of the solicitation. |
| N |
| 67 |
| TOC and Vehicles Kits, List of Vehicles |
Request the Government provide the technical reference material list of components of the Tactical Operations Center kits, Vehicle kits and the list of vehicles historically and planned for installation
PWS
6.1.11
| Detailed list of parts and kits provided in spreadsheet entitled “DTCS Kits’ Contents_v2”. In the last 5 years, TOC kits have not been installed in any vehicles by the FSRs. |
| Y |
| 68 |
| Training support |
Request the Government provide detail regarding current and planned training courses, session and material required for EMSS support requirements
PWS
6.1.14 Power Point “DTCS Overview Briefing v4” will be provided. Normally this briefing is provided as part of an orientation to deployed users in theater. Other similar materials that expand on specific devices or use cases may also be used, as needed or demanded, by users.
N
| 69 |
| OEM Certifications |
Request the Government provide detail regarding required OEM certifications for FSRs and Senior FSRs.
PWS
6.1.15
| OEM certification pertaining to DTCS equipment means receiving formal training and authorization from the cognizant Harris Corporation office for performing the functions described in PWS 6.1.15. The Government will assist in facilitating this requirement. |
| N |
| 70 |
| Equipment BOM |
Request the Government provide detail regarding the historical Bill of Materials (BOM) required for logistics support, including devices, consumables and associated equipment
PWS
6.2.1 Current task orders which include the scope of effort found in PWS 6.2.1 contain 2-7 FSRs each, and support between 1,000 – 5,000 devices. Other specific equipment and level of effort is conveyed in actual task taskers.
N
| 71 |
| DPAS Account |
Does the Government intend to sponsor the incoming prime contractor for a DPAS account?
PWS
6.2.2
| Yes. This will allow equipment to be better tracked, tech refreshed, and DRMO |
| N |
| 72 |
| Inventory Management |
What tool is currently used for Inventory Management? Is this tool GFE/GFI software and data that will be transferred to incoming prime contractor?
PWS
6.2.3
| Inventory of items for the U.S. military is normally done through the Property Book Unit Supply Enhanced (PBUSE) and “AWARDS” systems. These are U.S. Government systems to which the contractor shall assume he/she will be sponsored for access. |
| N |
| 73 |
| Order processing system |
Request the Government provide more detail regarding the follow-on “Storefront” order processing system.
PWS
6.2.6
| DISA Storefront will be utilized. No follow on process will be available. |
| N |
| 74 |
| Vehicles |
What vehicles are FSRs current using within the CENTCOM AOR? What vehicle certifications are required?
PWS
6.2.8
| The Contractor shall operate vehicles using fully qualified drivers in accordance with DoD vehicle regulation. Detailed list of parts and kits provided in spreadsheet entitled “DTCS Kits’ Contents_v2”. In the last 5 years, TOC kits have not been installed in any vehicles by the FSRs. |
| N |
| 75 |
| Training |
Please provide a list of current training material, their medium, number of trainees expected per base and option year
PWS
6.3 Please see enclosed, “DTCS Overview Briefing v4” provided by the incumbent contractor. Normally this briefing is provided as part of an orientation to deployed users in theater. Other similar materials that expand on specific devices or use cases may also be used, as needed or demanded, by users.
Y
| 76 |
| Sound Version Controls |
Please provide detail regarding sound version controls on current training configurations
PWS
6.3.4
| Generally speaking, sound version control means the contractor shall implement an intuitive system for tracking documentation and materials. This may include the establishment and maintenance of consistent and useful naming conventions and version control numbers determined by the contractor and approved by the Government. |
| N |
| 77 |
| Training MSRs |
What metrics (MSRs) are currently used to measure training effectiveness
PWS
6.3.7
| Representative metrics include the number of personnel trained; number and type of devices supported; issues or feedback experienced in training users or supporting operational missions (issues/feedback may pertain to the Iridium airtime service, the device itself; or the capabilities’ overall effectiveness in meeting mission requirements). |
| N |
| 78 |
| Formal Training Plan |
Is there a current Formal Training Plan? If so, will this be transferred to the incoming Prime Contractor
PWS
6.3.9
| An “in-progress” training plan exists and all government-owned training materials will be furnished to the incoming contractor as needed/applicable. |
| N |
| 79 |
| R&D Evaluations |
Where does the Government expect R&D evaluations with DISA and/or Sponsors to occur? How often?
PWS
6.5.2 R&D evaluations can occur at various locations around the globe and are normally on an ad-hoc basis. For example, NORTHCOM may need a task order for a R&D assessment of EMSS capabilities integrated into their end-to-end solution and the R&D is likely to occur in/around the North Pole. Similarly, National Science Foundation may require support in Antarctica.
N
| 80 |
| Surge Requests |
What is the notification lead time for Surge personnel requests?
PWS
6.5.4 Notifications for additional personnel vary, but have normally been very reasonable (e.g., 1 month or more). Shorter requests could occur, but customers understand that a hiring action by the contractor normally must result or the customer needs to fund reserves upfront to ensure expedited deployment of additional personnel. These requirements are defined at the task order level, with the majority of task orders maintaining a stable contractor workforce.
N
| 81 |
| Intelligence Reporting System(s) |
What is the current Intelligence Reporting System(s) in use? What is the classification level of this system?
PWS
6.5.7 Offerors may assume “intelligence reporting systems” are command and control (C2) or like systems. The intent of this requirement is for the contractor to be able to discern information from common C2 or like systems and recommend to the Government ways to best use the fielded capability (for example, DTCS) as a result of the information being produced by the C2 system.
N
| 82 |
| Shipping Method(s) |
What is the current shipping method(s)/carrier(s) used to ship DTCS equipment?
PWS
6.5.12
| Shipping method varies by country, but normally UPS, FedEx or DHL are used. |
| N |
| 83 |
| EMSS Customers |
Which COCOMs and DISA Field Offices are currently involved in the EMSS program?
PWS
6.6.1 All COCOMs, DISA Field Offices, and every U.S. federal department is an EMSS customer. EMSS has active relationships with all U.S. COCOMs and recently visited each COCOM in 2016. EMSS also has agreements with various foreign nations and entities, including Canada, United Kingdom, Australia, New Zealand, and NATO.
N
| 84 |
| SATCOM Technical Expertise |
Request the Government please provide more specific SATCOM technical expertise required for the HQE SME
PWS
6.6.4
| PWS 6.6.4 is updated. |
| Y |
| 85 |
| Facility Required |
Equipment Disposition Please provide detailed specifications regarding the facility for asset repair, maintenance and testing, storage and disposition of parts. Need information regarding: Location, size, technical specifications re IT infrastructure and storage.
Also please provide more details regarding preferred equipment disposition methods re DoD regulations.
PWS
6.7.1 Location: 6’x6’ work room.
Technical specification: Climate controlled; work bench; 110V power; commercial internet. D
Disposition methods are determined at the task order level based on customer direction, and sometimes includes following DRMO procedures. Current storage areas for all EMSS gear is approximately 8’x20’ at each site.
N
| 86 |
| COMSEC |
Please provide more detail regarding COMSEC storage, e.g., cage size, crypto handling certified staff, etc.
PWS
6.7.3
| Any COMSEC handling or staff certification requirements are guided by DODI 8523.01. Current storage areas for all EMSS gear is approximately 8’x20’ at each site. |
| N |
| 87 |
| COMSEC |
The DD254 is not marked for the COMSEC requirements stated in the PWS. Please de-conflict
PWS
DD254
6.7.3 The offeror must be able to comply with COMSEC storage laws and regulations. The offeror must be able to store and ship COMSEC. These requirements will not be enforced at time of contract award, but are expected to be achieved by 180 days after contract effective date. The applicable RFP documents will be updated accordingly.
Y
| 88 |
| COMSEC and ITAR Tracking |
Does the current Inventory Management tool log COMSEC and ITAR details for all devices and materials?
PWS
6.7.4
| Yes |
| N |
| 89 |
| OCCI Plan |
Request the Government require the OCCI Plan within only Volume V versus both in Volume II and Volume V. If still required within Volume II request the OCCI Plan(s) not be counted within the Volume II page constraints.
Attachment 9, Addendum Table 1 Proposal Organization
| Yes, the OCCI Mitigation Plan is excluded from page count and may only be submitted once. |
| Y |
| 90 |
| Volume TOCs and Volume Cover Pages |
Are Volume Table of Contents and Volume cover pages included in the Volume page constraints?
Attachment 9, Addendum Table 1 Proposal Organization
| No. Addendum 52.212-1 (b)(12)(iv) Page Limitations |
| N |
| 91 |
| Role Title |
HQW/SME
Attachment 1: “CENTCOM Liaison Subject Matter Expert (SME) Support.”
Task 6 as “Highly Qualified Expert (HQE)/Subject Matter Expert (SME) Support.”
Request clarification for the role title between attachments 1 and 9 Attachment 9, Addendum
PWS
Factor 1, Subfactor 1 c), 6.6
Attachment 9 administrative error has been corrected to “Highly Qualified Expert (HQE)/Subject Matter Expert (SME)”.
Y
| 92 |
| HQE SME Title |
Two names are for Task 6 expert are used: “Highly Qualified Expert (HQE)/Subject Matter Expert (SME) Support” and as “CENTCOM Liaison Subject Matter Expert (SME) Support.”
Request clarification for the role title in the STO PWS and PWS.
PWS
STO PWS
Task 6 Attachment 6 administrative error has been corrected to “Highly Qualified Expert (HQE)/Subject Matter Expert (SME)”.
Y
| 93 |
| The current education and experience requirements within the evaluation criteria is vague and does not equate to successful performance. |
Request government more closely map the education, experience and specific technical acumen required for each Labor Category to the EMSS ELOG scope of work.