GSA 013200 Construction Progress Documentation FY15 Update Oct. 1, 2014.docx

DOCX document 23 KB Posted

Attached to
Solicitation - Construction Manager as Constructor (CMc) contract for the FDA Forensic Chemistry Center Project
Solicitation number
47PF0020R0057S
Issued by

About this file

This document contains a construction progress documentation specification section for a federal construction project. It outlines requirements for submitting schedules of inspections and tests within 10 calendar days of the notice to proceed, as well as schedules of submittals within 14 calendar days. It also requires daily construction reports, material location reports at weekly intervals, field correction reports when necessary, and unusual event reports within 5 calendar days. The specification section provides instructions for the format and required information for each type of report. It will be applied to a repair and alteration project for the FDA Forensic Chemistry Center and Peck Federal Building in Cincinnati, Ohio, to modernize outdated systems and expand laboratory spaces. The General Services Administration intends to award a guaranteed maximum price Construction Manager as Constructor contract for construction management and general contractor services on the project, as described in solicitation number 47PF0020R0057S.

View the file

Other files

File Type Posted
EpsteinCombinedPart-4.pdf PDF
EpsteinCombinedPart-3Part-2.pdf PDF
EpsteinCombined Part 1.pdf PDF
EpsteinCombinedPart-2Part-1.pdf PDF
EpsteinCombinedPart-3Part-1.pdf PDF
EpsteinCombinedPart-2Part-2.pdf PDF
Appendix A.pdf PDF
Appendix H.pdf PDF
Appendix B.pdf PDF
Amendment 02_47PF0020R0057S.pdf PDF
Drawings Amendment 02.pdf PDF
Appendix J.pdf PDF
Appendix I.pdf PDF
Appendix E.pdf PDF
Concept Design Report.pdf PDF
Appendix F.pdf PDF
Pre Alteration Assessment Survey.pdf PDF
Appendix D.pdf PDF
Appendix C.pdf PDF
Amendment 01_RFP 47PF0020R0057S.pdf PDF
02_08_60_Lead_Mitigation.doc DOC document
Wage Determnation.pdf PDF
R5_Asbestos_Pre-Alteration_Assessment_Guidance.pdf PDF
Appendix-F_GPC_Checklist.pdf PDF
FDA CMc Solicitation_SOW.pdf PDF
Appendix-E_LEED-CI_Scorecard.pdf PDF
GSA 016000 Product Requirements FY15 Update Oct. 1, 2014.docx DOCX document
GSA 015930 Security Regulations FY15 Update Oct. 1, 2014.docx DOCX document
GSA 014025 Quality Control Testing for Air Barriers FY15 Update Oct. 1, 2014.docx DOCX document
GSA 011400 Work Restrictions FY15 Update Oct. 1, 2014.docx DOCX document
Appendix-D_InteriorDesign_Concepts.pdf PDF
SSL_TLS_Implementation_Guide_10-17-2016.docx DOCX document
GSA 019113 Commissioning FY15 Update Oct. 1, 2014.docx DOCX document
Appendix-H_ProjectLocation_FIRM_Map.pdf PDF
GSA_ACM_Notification_Form.pdf PDF
FDA-FCC_ConceptNarrative.pdf PDF
GSA 014100 Structural Testing Laboratory Services FY15 Update Oct. 1, 2014.docx DOCX document
GSA 013000 Electronic Project Management FY15 Update Oct. 1, 2014.docx DOCX document
Appendix-A_MeetingMinutes.pdf PDF
GSA 014000 Quality Assurance_Control FY15 Update Oct 1_2014.docx DOCX document
GSA 018111 Sustainable Design Requirements FY15 Update Oct. 1 2014.docx DOCX document
Appendix-C-DepartmentalDrawings.pdf PDF
FDA CMa and CXa SOW.pdf PDF
Peck DID Drawings.pdf PDF
GSA Smart Buildings Program Guide_v11.pdf PDF
SF24.pdf PDF
FDA Equipment_Responsibility_ Matrix.xlsx XLSX spreadsheet
GSA 013220 Photographic Documentation FY15 Update Oct. 1, 2014.docx DOCX document
GSA 015950 Safety_Health FY15 Update Oct 1_2014.doc DOC document
BuildingTechnologiesTechnicalReferenceGuidev11-2514.pdf PDF
Show 40 more

Latest 50 of 95 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name Project Location PCN #

[Div 1 Reviewer/Writer Instructions: 1. Turn ON Show/Hide feature in the Home tab to see any hidden instructions that may be embedded in each specification. Turn OFF after completing your final version. 2. Comments in [ ] are guidance for spec. writers to consider during the design phase. Delete in final version.]

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

[Coordinate with Section 014000 Quality Assurance & Control.]

GENERAL

SUMMARY

This section includes certain schedules and reports required for documenting the progress of construction during performance of the Work.

Coordinate the timing for preparation and processing of schedules and reports with the performance of other construction activities, and maintain a consistent and logical correlation between updated schedules and reports.

All construction progress documentation should be created and transmitted electronically into GSA’s electronic Project Management (ePM) database system.

Provide a reasonable time frame for the following when dealing with complex and large projects.

SCHEDULE OF INSPECTIONS AND TESTS

Prepare and submit a schedule of inspections, tests and similar services required by the Contract Documents within 10 calendar days after issuance of the Notice to Proceed.

Contractor shall coordinate the schedule of inspections and tests with the Construction Schedule and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:

Specification section number.

Description.

Identification of applicable standards.

Identification of methods to be used.

Number of inspections, tests or similar services.

Time schedule or time span.

Responsible entity.

Requirements for taking samples.

Unique characteristics.

Distribution: Submit in ePM electronic copies of the schedule of inspection and tests to the Contracting Officer, entities designated by the Contracting Officer, and each party involved in performance of portions of the Work where inspections, tests and similar serviced are required.

SCHEDULE OF SUBMITTALS

Prepare and submit a schedule of submittal required by the Contract Documents within [X] or [14] calendar days after issuance of the Notice to Proceed.

Contractor shall create in ePM the schedule of submittals and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:

[Add project specific requirements here. ]

REPORTS

Retain only those following paragraphs that suit the project, and edit as necessary. Add paragraphs for other reports. .

Daily Construction Reports: Prepare electronic daily construction report recording the following information concerning but not limited to events at the site. All daily reports are to be uploaded to GSA’s e-PM Include:

List of subcontractors at the site.

List of separate contractors at the site.

Count of personnel at the site.

High and low temperatures, general weather conditions.

Accidents.

Meetings and significant decisions.

Unusual events (see D. Unusual Event Reports below).

Stoppages, delays, shortages, and losses.

Meter readings and similar recordings.

Emergency procedures.

Orders and requests of governing authorities.

Change Orders received or implemented.

Services connected or disconnected.

Equipment or system tests and startups.

Partial completions or occupancies.

Summary of all work performed.

[Edit to reflect size of project.] Material Location Reports: At not more than weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered. Include a statement of progress on and delivery dates for materials or items or equipment fabricated or stored away from the site. Within [X] Calendar days submit copies of the list to the Contracting Officer (CO) or Contracting Officer's Representative (COR).

Field Correction Reports: When the need to take corrective action requires a departure from the Contract Documents, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Within [X] Calendar days submit a copy to the Contracting Officer or Contracting Officer's representative for approval.

Unusual Event Reports: When an event of an unusual and significant nature occurs at the site, prepare a detailed report. List the chain of events, persons participating, response by the Contractor's personnel, evaluation of the results or effects, and similar pertinent information. Within [X] Calendar days submit a copy to the Contracting Officer or Contracting Officer's representative immediately. Advise the Contracting Officer or Contracting Officer's representative in advance when such events are known or predictable.

[For capital projects add Security Clearance Tracking Reports by the Contractor and coordinate further with section 015930 Security Procedures.] PRODUCTS (Not applicable) EXECUTION (Not applicable)

END OF SECTION 013200

FY15 Update Oct. 1, 2014 Construction Progress Documentation 013200 - 2 image1.png