About this file
Pre-Solicitation Agenda
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMEND_02 SF30.docx | DOCX document | |
| DOC A RFI LOG 01062016.xlsx | XLSX spreadsheet | |
| DOC A RFI LOG 12312015.pdf | ||
| AMEND 01.docx | DOCX document | |
| Site Visit Sign In 121815.pdf | ||
| SOL C201 SBLPTA OCT 15A.pdf | ||
| GSA527-15.pdf | ||
| RnC C301 GC OCT 15.docx | DOCX document | |
| SF1442-14a.pdf | ||
| SF_24-98 Bid Bond.pdf | ||
| NEW--BLANK--NCIC GSA SCVR Oct 2014.xlsx | XLSX spreadsheet | |
| PBS_Past_Performance_Form_Rev_6_12_15.docx | DOCX document | |
| AGREE C101 SB OCT 15.pdf | ||
| DOCA_PH2_FINAL_CD_SPECS_VOL2.pdf | ||
| DOCA_PH2_FINAL_CD_SPECS_VOL1.pdf | ||
| Final_CD_Narrative.pdf | ||
| DOCA_PH2_FINAL_CD_SPECS_VOL3.pdf | ||
| Final_CD_Narrative_-_Appendix.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit December 18, 2015 - 9:00 AM
DOC A- Phase 2 Fit-Out Construction, Saint Elizabeths West Campus, SE, Washington, DC
Solicitation Number: GS11P15MMC7000
AGENDA
1) Introductions /Points of Contact/Communications
a) General Services Administration (GSA)
b) US Department of Homeland Security (DHS)
c) ZGF ARCHITECTS LLP
d) AFG Group
2) Review Scope of Work - Contractor shall provide professional design construction services and all labor, materials, equipment and supervision for the Tenant Fit-Out
Services DOC A Phase 2 Project. (the “Project”). The services required include:
a) Tenant fit-out for National Operations Center and Current Operations Division on lower level 3,
b) Installation of raised floor in empty shell spaces on lower levels 2 and 3 (included as
Add Alternates #3a and 3b),
c) Fit-Out of new toilet and shower rooms on lower level 3 (with corresponding fit-out on lower level 2 included as Add Alternate #4),
d) Construction of a new egress stair (Stair D), serving lower levels 2 and 3, on the north side of the DOC and its associated exit to grade.
e) Installation of a new elevator (a4) serving all levels in an existing hoist way at the southeast corner of the building near Stair B (with the installation of adjacent elevator A3 as a Add Alternate #2),
f) Completion of the DOC’s Chemical/Biological/Radioactive (CBR) systems design, including modifications to communicating doors to the Coast Guard and Utility
Tunnel and a three chamber decontamination suite (including showers) to serve those entering the DOC from the Center Building a CBR event (all included as Add
Alternate #1),
g) Connection from the DOC to Stair Charlie in the Center Building, Site Visit December 18, 2015 - 9:00 AM
h) Reconfiguration of the Interior of the existing DOC A entry pavilion on the ground level of the Coast Guard building to accommodate increased building occupancy.
The selective demolition of historic elements, partitions and carpet;
i) The sustainment of utilities affecting occupied spaces;
j) The installation of interior partitions and finishes (carpet, paint, ceiling tiles, etc.);
k) Alterations to building infrastructure (electrical, security, mechanical, fire protection and life safety, etc.); and
l) All coordination of the above with other GSA consultants, contractors, and vendors as needed to prepare the space.
3) Schedule
4) Site Access/Logistics
5) Building Tour
6) Questions and Answers
a) All questions must be submitted in writing to the Contracting Officer, Ms. Bonnie M
Echoles, at bonnie.echoles@gsa.gov no later than close of business Monday, December 28, 2015.