ECM 103 Revision.pdf

PDF 16 KB Posted

Attached to
RECOVERY GSA/NCR Design-Build Construction Project Funded by the Recovery Act (Reagan Bldg)
Solicitation number
GS-11P-10-YA-C-0049
Issued by

About this file

ECM 103 Revision

View the file

Other files

File Type Posted
ECM-103-1.pdf PDF
List of Changes —
SF1442 —
List of Changes - Amendment-2 —
SF1442 —
Reagan DB SOW 3-16-2010.pdf PDF
Questions - Group 4 - Final.xls XLS spreadsheet
Questions - Global.xls XLS spreadsheet
Minority Goals —
List of Changes - Amendment-2 —
Solicitation_GS11P10YAC0049 —
Sign in sheet 4.pdf PDF
3-8-10 Pre-Proposal Meeting Presentation FINAL.ppt PPT presentation
Sign in sheet 1.pdf PDF
List of Changes —
Sign in sheet 2.pdf PDF
Sign in sheet 3.pdf PDF
ARRA.8(a) DB Competitive Solicitation GS11P10YAC0049.doc DOC document
WD-DC.doc DOC document
ARRA.8(a) DB Competitive Agreement GS11P10YAC0049.doc DOC document
FOB8 - Document Transmittal Form - 0049.doc DOC document
REPS-CERTS GS11P10YA-C-0049.doc DOC document
Reagan DB SOW 2-24-2010.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA Solicitation No: GS-11P-10-YA-C-0049

Property of the United States Government – For Official Use Only.

Do not remove this notice. Properly destroy documents when no longer needed.

5.1 Base ECM Bundle

5.1.A ECM-103 Fabric Speed Doors at Loading Dock

Part 1 - General Requirements

1.1 Existing Documents

The Design Builder shall obtain the existing documents of the facility from GSA.

1.2 References

The design shall be in accordance with the Facilities Standards for the Public Buildings Service revised March 2005 – PBS-P100 and all applicable codes referenced within.

1.3 Design and Engineering

The Design Builder shall employ qualified licensed architects and engineers to provide full engineering and design services including but not limited to construction documents and specifications.

1.4 CAD Deliverables

The engineering design shall be in accordance with the GSA “CAD Deliverables Policy”, March 1, 2005.

1.5 Demolition: Remove existing loading dock doors.

1.6 Existing Condition: The loading docks allow a significant amount of infiltration from the parking garage into the building through the large corridor dock door. This door is the only connection point between the main loading dock and the building. The door is a approximately 8.5'x20', steel roll-up type with very slow operation. With the slow operation, it is left open at all times.

Part 2 – Statement of Work

2.1 Remove existing steel roll-up door in its entirety. Install two sections of fabric speed roll-up doors each with a window section. Install activating walking pads motion detector in proper locations, but not within normal walking spaces.

GSA Solicitation No: GS-11P-10-YA-C-0049

Property of the United States Government – For Official Use Only.

Do not remove this notice. Properly destroy documents when no longer needed.

Contractor to verify dimensions and provide two high speed roll up doors of equal size.

Part 3 - Performance Specifications

3.1 High Speed Fabric Doors

a. Shall be equal to Nergeco ‘Terkking Enduro’ or Rytec ‘Turbo SR’.

b. Provide corrosion resistant self supporting door frames.

c. Fabric Door shall have a minimum speed of 48” per second.

d. If accidental impact should occur, the door will automatically reinsert itself without operator intervention.

e. Provide dual thru beam photo eyes and auto-reversing edge in bottom bar.

f. Provide full width vision panels.

g. Provide weather seals on top bottom on both sides to reduce air infiltration.

h. Provide one year warranty on materials and workmanship.

i. Provide motion detectors on both sides of each door to activate doors.

3.2 Commissioning

a. There will be a third party Commissioning Authority contracted through GSA for this project.

b. Contractor’s tests shall be scheduled and documented in accordance with fundamental standard building commissioning services.

c. System verification testing is part of the commissioning process. Verification testing shall be performed by the contractor and witnessed and documented by the Commissioning Authority. GSA shall be notified of the time and date of any system verification testing in order to be witness to the testing.

d. Contractor shall coordinate with the design team and the Commissioning Authority to bring resolution to non-compliant or unacceptable test results.

e. Temporary systems do not require system verification as part of the commissioning process.

f. Comply with GSA’s Total Building Commissioning Guide and Construction Phases.