ECM 103 Revision.pdf
PDF 16 KB Posted
- Attached to
- RECOVERY GSA/NCR Design-Build Construction Project Funded by the Recovery Act (Reagan Bldg)
- Solicitation number
- GS-11P-10-YA-C-0049
About this file
ECM 103 Revision
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ECM-103-1.pdf | ||
| List of Changes | — | |
| SF1442 | — | |
| List of Changes - Amendment-2 | — | |
| SF1442 | — | |
| Reagan DB SOW 3-16-2010.pdf | ||
| Questions - Group 4 - Final.xls | XLS spreadsheet | |
| Questions - Global.xls | XLS spreadsheet | |
| Minority Goals | — | |
| List of Changes - Amendment-2 | — | |
| Solicitation_GS11P10YAC0049 | — | |
| Sign in sheet 4.pdf | ||
| 3-8-10 Pre-Proposal Meeting Presentation FINAL.ppt | PPT presentation | |
| Sign in sheet 1.pdf | ||
| List of Changes | — | |
| Sign in sheet 2.pdf | ||
| Sign in sheet 3.pdf | ||
| ARRA.8(a) DB Competitive Solicitation GS11P10YAC0049.doc | DOC document | |
| WD-DC.doc | DOC document | |
| ARRA.8(a) DB Competitive Agreement GS11P10YAC0049.doc | DOC document | |
| FOB8 - Document Transmittal Form - 0049.doc | DOC document | |
| REPS-CERTS GS11P10YA-C-0049.doc | DOC document | |
| Reagan DB SOW 2-24-2010.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Solicitation No: GS-11P-10-YA-C-0049
Property of the United States Government – For Official Use Only.
Do not remove this notice. Properly destroy documents when no longer needed.
5.1 Base ECM Bundle
5.1.A ECM-103 Fabric Speed Doors at Loading Dock
Part 1 - General Requirements
1.1 Existing Documents
The Design Builder shall obtain the existing documents of the facility from GSA.
1.2 References
The design shall be in accordance with the Facilities Standards for the Public Buildings Service revised March 2005 – PBS-P100 and all applicable codes referenced within.
1.3 Design and Engineering
The Design Builder shall employ qualified licensed architects and engineers to provide full engineering and design services including but not limited to construction documents and specifications.
1.4 CAD Deliverables
The engineering design shall be in accordance with the GSA “CAD Deliverables Policy”, March 1, 2005.
1.5 Demolition: Remove existing loading dock doors.
1.6 Existing Condition: The loading docks allow a significant amount of infiltration from the parking garage into the building through the large corridor dock door. This door is the only connection point between the main loading dock and the building. The door is a approximately 8.5'x20', steel roll-up type with very slow operation. With the slow operation, it is left open at all times.
Part 2 – Statement of Work
2.1 Remove existing steel roll-up door in its entirety. Install two sections of fabric speed roll-up doors each with a window section. Install activating walking pads motion detector in proper locations, but not within normal walking spaces.
GSA Solicitation No: GS-11P-10-YA-C-0049
Property of the United States Government – For Official Use Only.
Do not remove this notice. Properly destroy documents when no longer needed.
Contractor to verify dimensions and provide two high speed roll up doors of equal size.
Part 3 - Performance Specifications
3.1 High Speed Fabric Doors
a. Shall be equal to Nergeco ‘Terkking Enduro’ or Rytec ‘Turbo SR’.
b. Provide corrosion resistant self supporting door frames.
c. Fabric Door shall have a minimum speed of 48” per second.
d. If accidental impact should occur, the door will automatically reinsert itself without operator intervention.
e. Provide dual thru beam photo eyes and auto-reversing edge in bottom bar.
f. Provide full width vision panels.
g. Provide weather seals on top bottom on both sides to reduce air infiltration.
h. Provide one year warranty on materials and workmanship.
i. Provide motion detectors on both sides of each door to activate doors.
3.2 Commissioning
a. There will be a third party Commissioning Authority contracted through GSA for this project.
b. Contractor’s tests shall be scheduled and documented in accordance with fundamental standard building commissioning services.
c. System verification testing is part of the commissioning process. Verification testing shall be performed by the contractor and witnessed and documented by the Commissioning Authority. GSA shall be notified of the time and date of any system verification testing in order to be witness to the testing.
d. Contractor shall coordinate with the design team and the Commissioning Authority to bring resolution to non-compliant or unacceptable test results.
e. Temporary systems do not require system verification as part of the commissioning process.
f. Comply with GSA’s Total Building Commissioning Guide and Construction Phases.