General Construction (GC) Services
Amendment 9 HST Modernization, Phase 1B-Bid Package 3 and 4 02/03/2010 Washington, DC
Revised Section F, Page 1-F-4
F.11 FAR 52.211-12 - Liquidated Damages - Construction (Sep 2000)
A. If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay to the Government liquidated damages as follows:
1. The sum of $32,500 for each calendar day of delay until the work for construction is completed or accepted.
B. If the Government terminates the Contractors’ right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the termination clause.
I-F-4