Administrative Support Services New England Region and Puerto Rico
GS-01-P-16-BW-C-7007
QUESTION SET 6
89. I have a question regarding the new amended hours. Whereas, some of the current people will have 2,3 and 4 weeks vacation, will we be required to have personnel cover them while they are gone?
Answer: No. However, the front desk needs to have coverage and the contractor will have to propose a plan to rotate the administrative assistant staff to provide the support required.
File details come from the government source that posted it. Updated .