This Invitation to Bid (ITB #22-006) is issued by the City of Griffin, Georgia for the Griffin/Spalding Wayfinding Signage Project. The project involves the fabrication and delivery of 39 directional wayfinding signs to be placed throughout Spalding County and the City of Griffin to direct tourists and visitors to key points of interest. The signs are available in four standard sizes (Small, Medium, Large, and X-Large) with full approval from the Georgia Department of Transportation (GDOT). All signs must incorporate break away safety systems, reflective material for night visibility, and specific dimensions including 57-inch widths for points of interest sections and 7 feet 8 inches clearance below signs. The scope of work is limited to fabrication and delivery only, with the City's Public Works Department responsible for installation on concrete bases. Two identical copies of sign number 28 are required. The bid submission deadline was Tuesday, January 4, 2021 at 2:00 P.M., with anticipated installation scheduled for February/March 2022. Bidders were required to provide a jig for bolt placement at least eight weeks prior to delivery to allow for concrete footing preparation. The contractor must provide a fabricated foundation anchor cage matching the exact bolt pattern for each sign and comply with GDOT Standard Specification 9054a, with all materials and fastening hardware in A709 Grade 36 Galvanized Steel.
Bid pricing must include separate line items for production and delivery, with proposals valid for a minimum of 90 days following submission. The evaluation committee allowed up to two weeks after receiving proposals to select the final company, with all companies notified of results once the selected contractor was confirmed. A minimum of three references from similar projects completed within the past 3–4 years were required, with at least one reference being a GDOT project. Bidders not contracted with the City in the past two years must provide detailed reference information including dates of service, contact persons, titles, and phone numbers, along with disclosure of any terminated services and reasons for termination. The City reserved the right to reject any or all bids, waive formalities, request best and final offers, and make awards based on responsive and responsible criteria rather than lowest price alone. Standard contract terms included a maximum one-year initial term with four renewal options totaling five years, firm pricing for the initial contract period, and potential liquidated damages of 1 percent per day of non-compliance (capped at $500 daily). Suppliers were required to obtain an Occupational Tax License if needed, maintain specified insurance coverage including $1,000,000 Commercial General Liability and $1,000,000 Automobile Insurance, and comply with Georgia's E-Verify requirements for labor and services exceeding $2,499.99.
Text of this file
CITY OF GRIFFIN, GEORGIA
INVITATION TO BID
BID #22-006
FOR
GRIFFIN / SPALDING WAYFINDING SIGNAGE PROJECT
For all questions about this Bid contact:
Sherri Huggins, Purchasing Coordinator shuggins@cityofgriffin.com
Submittal Deadline:
Tuesday, January 4, 2021 at 2:00 P.M.
ADVERTISEMENT FOR BIDDERS
Sealed proposals will be received by the City of Griffin, 100 S. Hill Street, PO Box T, Griffin, Georgia, 30223 in the City Manager Third Floor Conference Room until:
2:00 PM, local time, Tuesday, January 04, 2021
For the Project known as:
GRIFFIN / SPALDING WAYFINDING
SIGNAGE PROJECT
1. At which time and place the proposals will be publicly opened and read aloud. Proposals received after the designated time will not be considered. The OWNER of the project is the CITY OF GRIFFIN.
The approximate extent and character of the Work is generally described as follows:
The City of Griffin intends to install Wayfinding Signs in Griffin/Spalding County. This project will be for directional signage that will be placed throughout Spalding County and the City of Griffin to direct tourist/visitors to key points of interest throughout the community. The project consists of 39 signs to be placed in various areas along streets and highways. The signs have full approval from GDOT as they are being submitted here today. We are anticipating installation in February/March 2022.
This request is to use the attached designs and sign layouts to efficiently quote the project for installation in Griffin Spalding. The quote should only include fabrication and delivery as our Public Works Department will be responsible for installation of signs on concrete bases that they build. Each of these sections: production and delivery should be on separate line items. The deadline to send your final quotes will be Tuesday, January 4, 2021 and be received by 2:00 PM. Please be as thorough as possible and ask any questions that you feel that you need answered to adequately quote the project. Below are important notes regarding the project:
· Pages 1-8 are broken up into 4 separate standard sign sizes (Small, Medium, Large and X-Large); each is followed by the actual sign layouts that correspond with the sign size.
· Page 9 references the paint and vinyl colors; and the font specifications.
· Pages 10 and 11 describe the sign measurements and the graphics on the back of the sign.
· All signs must use break away safety systems.
· All sign faces with points of interest must be reflective material to easily be seen at night.
· Width of signs where points of interest are located 57” wide to accommodate longer names at a larger font. Heights of panels on the post will be different for each sign due to varying numbers in points of interest, however the clearance below the sign must remain at 7’ 8”.
· We need two of sign number 28 called Sign 28 and Sign 28.1.
· Any questions asked by one company will be answered to all companies so that all companies have the same information.
· Company must provide a jig for the placement of bolts in the concrete at least eight weeks prior to delivery so that the concrete footings can be poured before delivery and that the bolts set in the footings will match up to the sign post for installation.
· Sign fabrication to include foundation anchor cage fabricated to match the exact bolt pattern for each sign purchased, and designed for specified footing depth required. All materials & fastening hardware shall be A709 Grade 36 Galvanized Steel and plate configurations shall be manufactured in accordance with GDOT Standard Specification 9054a, Erection and Foundation Details for Special Roadside Signs Breakaway Type Post.
Please direct all questions to Patrick Kay, Director of Economic Development for the City of Griffin: pkay@cityofgriffin.com and 770-228-5356. All questions will be answered and made public on Vendor Registry and Team Georgia Marketplace. Please allow up to two weeks after we receive the proposal/quotes for us to select the final company. We will notify all companies of the final result once we confirm and notify the selected company.
| Patrick Kay, MSARP |
| Economic Development Director |
The Owner reserves the right to reject any or all Bids, to waive formalities and re-advertise.
INVITATIONS TO BID
BID# 22-006
1. SECTION I – GENERAL INFORMATION
Sections II - VII review the general terms and conditions. Any bid-specific information noted in Section I or in the Specifications & Response Section will take precedence.
2. SECTION II – GENERAL TERMS AND CONDITIONS
All information, notices and addenda regarding this Bid shall be posted on the City’s website. It is the bidder’s responsibility to check the site on a regular basis in order to confirm they have the most current information prior to submitting a response. Subsequent to the bid opening, all status notices will also be posted on the City’s website.
2.1. RESTRICTIONS ON COMMUNICATIONS WITH STAFF
All questions about this bid must be submitted in the following format:
Company Name
- Question Citation of relevant section of the bid
All questions regarding specification/technical issues must be in writing to the Project Manager for this bid (with a ‘cc’ to Procurement). The Project Manager, contact email and deadline for questions is noted in section 1.
All questions regarding administrative issues must be in writing to the Purchasing Coordinator:
Address: City of Griffin Sherri Huggins Purchasing Coordinator P. O. Box T, Griffin, GA 30224 Email: shuggins@cityofgriffin.com No questions other than written will be accepted. No response other than written will be binding upon the City. Questions will be combined into one list of questions and responses and will be posted as an addendum.
From the issue date of this request until an award has either been made or deemed closed for other reasons, institutions or individuals providing submissions are not permitted to communicate with members of the commission, the evaluation team or City employees, other than Procurement, with regard to the purpose or intent of this document. The exception to this is the submission of written technical questions to the project manager. The City reserves the right to reject the submission of the offending bidder if this provision is violated.
Any updates or changes to this and related documents will be posted on the City’s website (https://vrapp.vendorregistry.com/Bids/View/BidsList?BuyerId=52b8c206-866a-4ed2-b7b8-bef7db8a901b) or by selecting “Resources” and then “Bid Opportunities” from the City home page. It is the Supplier’s responsibility to refer to the website for any addenda or other pertinent information before responding to this RFP request.
2.2. PUBLIC DISCLOSURE AND PROPRIETARY INFORMATION
All bids and any other public record with respect to solicitation shall be subject to public inspection, upon request, after the posting of the Notice of Intent to Award (NOIA) or Notice of Award (NOA). This is being done in order to protect the integrity of the procurement process unless otherwise required by law. For any Open Records requests, the City may assess fees for the costs of producing these public records as permitted by the Georgia Open Records Act.
Exceptions to the availability of information include 1) bona fide trade secrets meeting confidentiality requirements that have been properly marked and documented; 2) matters involving individual safety as determined by the City; 3) company financial information requested by the City to deter determine vendor responsibility; and 4) other constitutional protections. All documents that are to be proprietary and confidential are to be clearly marked as such.
Information received in response to this request will become the property of the City and will not be returned. If a proposer feels that any information is confidential or proprietary in nature, the proposer must prominently mark and initial such information as “PROPRIETARY INFORMATION”. The City will not release or divulge such information to third parties without the consent of the Proposer unless required to do so by applicable law or order a court of competent jurisdiction.
3. SECTION III –OVERVIEW AND PROCEDURES
Sections II - VII review the general terms and conditions. Any bid-specific information noted in Section I or in the Specifications & Response Section will take precedence.
3.1. COMPANY BACKGROUND & EXPERIENCE
Bidders that have not contracted with the city in the past 2 years should provide a list of clients for whom similar services, as detailed in this bid, have been provided during the past 3-4 years. References must be for the organization or person submitting the bid. Subcontractor’s references are not acceptable.
The list must include:
| Dates of service |
| Name of contact person |
| Title of contact person |
| Phone number of contact person |
The Supplier will also disclose any services terminated by the client(s) and the reason(s) for termination.
Failure to provide this information will disqualify the bid submission.
3.2. REFERENCES
References should be for historical projects of similar size and scope. Details regarding these references are noted on the Reference page.
| 3.3. | BID REQUIREMENTS |
| 3.3.1. | SPECIAL CONDITIONS |
By submitting a bid response, Suppliers certify that their proposals are made without collusion or fraud and they have not offered or received any inducements in connection with their proposals. They further agree that this solicitation and any resulting contract shall be governed in all respects by the laws of the State of Georgia and they shall comply with applicable federal, state and local laws and regulations. Any contracts or leases resulting from the award of a Bid are to be for a period of not more than one year, with four renewal option for a total period not to exceed five years. Any exceptions to this policy must be noted and agreed to by both parties in writing, prior to the issuance of the Notice of Award. Pricing must remain firm for the duration of the initial term of the resulting contract; failure to hold firm pricing for the initial contract will be considered as sufficient cause for termination. Proposal submissions must remain valid for a minimum period of ninety (90) days after the submission due date unless otherwise stipulated.
The City reserves the right to reduce or increase the scope of the project if the lowest responsible and responsive supplier’s submittal is not in line with the budgeted amount for the project. The City, at its sole discretion, reserves the right to increase or decrease the scope of work to facilitate an award. This scope reduction will be enacted only if it is in the best interest of the City and constitutes no guarantee of scope.
The City also reserves the right to add to the contract any future work or purchased goods, with the agreement of the contractor, at prices offered in this bid document. This option will be enacted during the contract or within six months subsequent to the end of the contract, if in the best interest of the City and with the agreement of both parties.
3.3.2. RESPONSES
In responding to a bid, ALL item numbers with appropriate formatting must show some type of acknowledgment in order for the response to be properly evaluated. Failure to respond to all specification criteria items may be deemed as sufficient reason to reject a submission. If formatting is not provided for a response at the item level, any non-compliance must be clearly marked, detailed and included with the bid response. Any items not identified shall be deemed as in compliance. Suppliers must: 1) complete any/all required forms; 2) indicate agreement or disagreement on each mandatory requirement and, if requested, provide additional information on how the specifications will be exceeded or not met; and 3) provide complete and detailed responses to any and all non-mandatory requirement that can be fulfilled.
If determined to be in the City’s best interests, a Best and Final Offer (BAFO) may be requested. A BAFO may be requested when:
| - | The prices for all responsive and responsible submittals exceed budget; | |
| - | No single responsive and responsible submittal meets all requirements; | |
| - | When all responses are unclear or deficient in one of more areas; | |
| - | When the grading scores of two or more submittals require additional evaluation; | |
| - | At the discretion of the evaluation team to clarify submittals or to negotiate costs or other | deliverables. |
| 3.3.3. | PACKAGING OF BID |
Submissions must be by the following method:
No e-mail, fax or scanned submissions will be accepted. Hard copies are to be submitted in a sealed package containing an unbound original and the number of copies specified in Section I. The sealed package must be labeled on the outside as follows:
(Supplier Name) BID # (Bid Number) (Bid Title)
Supplier response to this solicitation must consist of the following documents in addition to any solicitation-specific information requested:
· Pricing
· Schedule of proposed work (when applicable),
· Completion Schedule (when applicable),
· Supplier Registration is to be completed online, with the following forms needing to be uploaded
| - Vendor Affidavit (E-Verify) (supplied in attachment), available online |
| - W-9 (supplied in attachment), available online |
| - The City cannot award to a supplier that is not registered and compliant, |
· Tax Compliance form (required if over $99,000) (supplied if required),
· Reference list of a minimum of three (3) references (supplied).
3.3.4. SUBMISSION OF BID
The original and specified copies of the solicitation response must be delivered to the Project Manager no later than the time and date specified in Section I. Any response received after stated time or delivered to another department other than that of the Project Manager, will not be accepted. The City of Griffin will not be responsible for any responses not received by the Project Manager prior to the deadline.
Responses must be submitted to:
City of Griffin Attention: Sherri Huggins, Procurement Coordinator P. O. Box T, Griffin, GA 30223 Or delivered to:
Attention: Sherri Huggins, Procurement Coordinator 100 S Hill Street, 3rd Floor Griffin, GA 30223 *Note: Notify Procurement via email (shuggins@cityofgriffin.com) if submittal is mailed via Post Office (USPS).
3.3.5. ALTERNATE BID DOCUMENTS
Documents prepared by the City must be used for the submission of Bid Response. Alternate bids or bids that deviate from the requirements of this solicitation may not be considered. Supplier shall not insert in their submission any written statement which will have the effect of making any material change or changes in the Scope of Services or in any contract between the parties covering the subject matter thereof.
3.3.6. ADDITIONAL INFORMATION/ADDENDA
The City will issue responses to inquiries and any other corrections or amendments it deems necessary in written addenda issued prior to the bid opening date. Suppliers should not rely on any representations, statements, or explanations other than those made in this Invitation to Bid and its’ addendums. Where there appears to be a conflict between the Invitation to bid and any addenda issued, the last addendum issued will prevail. It is the Supplier’s responsibility to check for addendums (under Bid Opportunities) on the City’s website.
Suppliers must acknowledge any issued addenda. Bids which fail to acknowledge the bidder’s receipt of any addendum will result in the rejection of the bid if the addendum contains information which substantively changes the City’s requirements.
| 3.3.7. | PROPOSAL PRICING, ERRORS AND OMISSIONS |
| 3.3.7.1. | In the event there is a discrepancy between a unit price submitted and the extended price, the unit price will prevail. |
| 3.3.7.2. | All corrections, changes or erasures to the proposal submission are to be initialed in ink. |
| 3.3.7.3. | While responses for ITBs are based on ‘responsive and responsible’ pricing, the City reserves the right to include a +/- variance of up to 2% for either exceptional or poor prior supplier performance. |
| 3.3.8. | WITHDRAWAL OF BID |
A supplier may withdraw his bid before the submittal deadline without prejudice to the supplier by submitting a written request of withdrawal to the Purchasing Coordinator.
3.3.9. LATE SUBMITTAL, LATE MODIFICATIONS & LATE WITHDRAWALS
Bid submittals received after the bid opening date and time will not be accepted. Modifications received after the bid opening date will not be considered. The City assumes no responsibility for the premature opening of a bid not properly addressed and identified or not delivered to the proper designation.
3.3.10. MIMINUM BID ACCEPTANCE PERIOD
Bids shall be valid and may not be withdrawn for a minimum period of 60 days from the date specified for receipt of bids. Suppliers will be asked for an ‘expiration date’ for the bid submitted, when appropriate. This does not impact the contract price once a bid has been awarded.
3.3.11. DISQUALIFICATION OF BIDS OR BIDDERS
Suppliers may be disqualified from participation in the bid process for reasons which include, but are not limited to the following:
| 3.3.11.1. | Evidence of collusion; |
| 3.3.11.2. | Attempting to manipulate the submittal pricing for its’ own benefit (i.e. pricing resulting in a failure of the City’s ability to enforce the Contract or impose the remedies intended following breach by Supplier); |
| 3.3.11.3. | Being in arrears on any of its existing contracts with the City or in litigation with the City or having defaulted on a previous contract with the City; |
| 3.3.11.4. | Being in arrears on taxes owed to the State of Georgia; |
| 3.3.11.5. | Poor, defective or otherwise unsatisfactory performance of work for the City or any other party on prior projects which, in the City's judgment and sole discretion, raises other party on prior projects which, in the City's judgment and sole discretion, raises party on prior projects which, in the City's judgment and sole discretion, raises doubts as to Bidder's ability to properly perform the work; |
| 3.3.11.6. | Any offering of gifts, unauthorized compensation or other unethical actions to City employees with respect to interest in any business activity; or |
| 3.3.11.7. | Any other cause which, in the City's judgment and sole discretion, is sufficient to justify disqualification of the supplier or the rejection of their submittal; |
| 3.3.12. | REJECTION/CANCELATION/AWARD OF BIDS |
The City reserves the right to:
| a) | reject any and all submittals received outside the time/place stated in the notice; |
| b) | reject any submittals which show omissions, irregularities, alteration of forms or unsolicited responses; |
| c) | waive any technicalities, or formalities of the bids; |
| d) | reject any or all bids or any part thereof; |
| e) | obtain clarification on any point in a respondent submittal or obtain additional information; |
| f) | accept the bid that is in the best interest of the City, regardless of whether or not it is the lowest bid; |
| g) | award the bids received on the basis of individual items or on the entire list of items. |
The City also reserves the right to cancel this bid at any time and will not be liable for any cost/losses incurred by the Supplier throughout this process.
Where applicable, the City reserves the right to make multiple awards or to award a contract by individual line items or alternatives, by group of line items or alternatives, or to make an aggregate award, whichever is deemed most advantageous to the City. If the City determines that an aggregate award to one bidder is not in the City’s best interest, "all or none" offers will be rejected.
3.3.13. COST INCURRED BY BIDDERS
All expenses involved with the preparation and submission of the bid to the City, or any work performed in connection therewith, is the responsibility of the supplier(s).
3.3.14. BID OPENING
All bids will be opened on the pre-determined bid opening date. The bid details and related documents will not be publically announced or reviewed at the bid opening; they will be turned over to an evaluation committee. No awards will be made or implied at this time. The Status field on the City’s website will be updated following any change in the Bid process. Refer to section 2.1 for details regarding this Status. Any bid-specific exceptions to the ‘non-public opening’ will be noted in the Schedule (Section 1.2).
3.3.15. AWARD AND RESULTING CONTRACT
Award will be made to the lowest responsive and responsible Supplier whose submittal is compliant to the terms of this bid request. The quality of the articles to be supplied, their conformity with the specifications, their suitability to the requirements of the City, the delivery terms and other criteria, as well as price, will be taken into consideration in making the award.
Any resulting contract shall not be binding upon the City nor should any action be started until it has been executed by both parties and a copy of the fully executed contract has been delivered to the successful Supplier. Specifications noted in this bid request shall be incorporated into the resulting contract. The City reserves the option to prepare and negotiate its own contract, giving due consideration to the stipulations of the supplier’s proposed contract and associated legal documents.
3.3.16. PROTESTS
Protest may be filed by the affected party regarding any aspect of the solicitation, evaluation or award. All protests must be in writing, include the information listed below and directed to the Procurement Department. Protests regarding the specifications or how a solicitation was written must be filed at least seventy-two (72) hours prior to the deadline. Protests regarding the validity of the evaluation team or the evaluation process must be filed within seventy-two (72) hours of the notice to bidders. Protests regarding the recommended awardee must be filed within ten (10) days of the Notice.
3.3.16.1. FILING A PROTEST
Only suppliers intending to submit a response may protest a solicitation and only suppliers that respond to a solicitation may protest the evaluation /award. All Protests must be directed to the Procurement Department, be in writing and contain the following information in order to be valid:
3.3.16.2. The name (company), address, telephone number and email of the protestor
3.3.16.3. Signature and printed name of the protestor
3.3.16.4. Identification of the solicitation and the sections contested
3.3.16.5. A statement of reason for the protest including copies of relevant supporting documents
3.3.16.6. A description of the remedy requested.
3.3.16.7. A decision will be rendered by Procurement. Should the protest need to be escalated, it shall continue as needed through the following stages: City Attorney, Board of Commissioners, court system.
3.4. INSPECTION AND ACCEPTANCE OF EQUIPMENT (FOR PURCHASE)
Where applicable, all items bid and furnished that are to be purchased must be completely new, free from defects and operate as intended unless otherwise specified in writing. Discontinued, remanufactured or demonstrator items will not be accepted unless specifically requested. The manufacturer’s standard warranty shall be identified and copies of the warranties are to be presented upon request. In addition, all items supplied shall comply with all Federal and State regulations, applicable and effective on the date of acceptance. All items must meet or exceed all existing Federal, State and Local health, safety, lighting, emissions and noise standards.
The City reserves the right to inspect and test any equipment being offered in the bid prior to making any award. The City may also request a demonstration or site visit for evaluation purposes. The equipment delivered under this bid shall remain the property of the seller until a physical inspection of the equipment is made and accepted by the City. In the event that the equipment supplied to the City is found to be defective or does not conform to the City’s specifications, the City reserves the right to cancel the order upon written notice to the seller and to return the equipment to the seller at the seller’s expense.
3.5. STATEMENT OF EXPERIENCE AND QUALIFICATIONS
The supplier may be required, upon request, to prove to the satisfaction of the City that he/she has the skill and experience and the necessary facilities and ample financial resources to perform the contract(s) in a satisfactory manner and within the required time. If the available evidence of competency of any bidder is not satisfactory, the response of such bidder may be rejected. The City reserves the right to request clarifications of any response or to conduct discussions for the purpose of clarification. Any clarifications made as a result of these discussions are to be provided in writing.
3.6. NON-COLLUSION AFFIDAVIT
By submitting a bid, the bidder represents and warrants that such bid is genuine and real and not made in the interest or on behalf of any person not therein named. It is further warranted that the supplier has not directly or indirectly solicited any other supplier to put in a sham bid, or any potential supplier to refrain from submitting and that the supplier has not in any manner sought by collusion to secure any advantage over any other supplier.
By submitting a bid, the supplier represents and warrants that no official or employee of City has, in any manner, an interest directly or indirectly in the bid or in the contract which may be made under it, or in any expected profits to arise therefrom. It is further warranted that the bidder is independent of the City.
3.7. HOLD HARMLESS AND INDEMNIFICATION
The Supplier agrees, insofar as it legally may, to indemnify and hold harmless the City, its officers, employees and agents from and against all loss, costs, and expenses, including attorneys' fees, claims, suits and judgments in connection with injury to or death of any person or persons or loss of or damage to property resulting from any and all operations performed by Supplier, its officers, employees, and agents under any of the terms of this contract.
3.8. BID BONDS (Bid, Performance, Payment)
For any bid as required and noted in Section 1 of this bid document, a one hundred ten percent (110%) Performance bond and a one hundred percent (100%) Payment bond shall be furnished payable to, in favor of, and for the protection of the City. When Bid bonds are required, they must be in a sum equal to five percent (5%) of the total amount of the supplier’s response and may be in the form of a surety issued bond or cashier’s check made payable to the City of Griffin. Bid bonds are returned to the unsuccessful suppliers when the Notice of Award has been issued or contract has been executed. When bonding is required, failure to submit appropriate bonding will result in automatic rejection of bid. Performance and/or Payment bonds must be presented within ten (10) days of the Notice of Intent to Award or prior to the award of contract, whichever is later. Surety companies executing bonds must appear on the Treasury Department’s most current publication (Circular 570 as amended) and be authorized to do business in Georgia. Unless otherwise specified, bonds shall be in effect for a period of one year from the completion of the project. The bond amounts shall be increased as the contract amount is increased. No alternative securities are currently accepted in lieu of performance or payment surety bonds.
4. SECTION IV – OTHER GENERAL SPECIFICATIONS
Sections II - VII review the general terms and conditions. Any bid-specific information noted in Section I or in the Specifications & Response Section will take precedence.
4.1. LIQUIDATED DAMAGES
Pursuant to O.C.G.A. § 36-91-24, it is understood that the Notice-to-Proceed and the time for completion of the work as specified are ESSENTIAL conditions of any resulting contract and that the performance and completion of this work within the specified time is vital to the City’s economic interests. If the Supplier neglects, fails or refuses to complete the work within the mutually agreed time specified, the City may impose liquidated damages for each day of non-compliance past the scheduled completion date. Unless otherwise specified in Section I of this document or in the resulting contract, liquidated damages may be assessed at a rate of 1%, with a limit of $500.00 per day of non-compliance.
4.2. FORCE MAJEURE
The City and Supplier will be excused from the performance of their respective obligations under this Contract when and to the extent that their performance is delayed or prevented by any circumstances beyond their control including but not limited to, fire, flood, explosion, strikes or other labor disputes, act of God or public emergency, war, riot, order/act of any governmental authority, provided that:
| 4.2.1. | The non-performing party gives the other party prompt written notice within three (3) business days describing the particulars of the Force Majeure including, but not limited to, the nature of the occurrence and its expected duration, and continues to furnish timely reports with respect thereto during the period of the Force Majeure; |
| 4.2.2. | The excuse of performance is of no greater scope and of no longer duration than is required by the Force Majeure; |
| 4.2.3. | No obligations of either party that arose before the Force Majeure causing the excuse of performance are excused as a result of the Force Majeure; |
| 4.2.4. | The non-performing party uses its best efforts to remedy its inability to perform. Economic hardship of the Provider will not constitute Force Majeure. The term of the Provider shall be extended by a period equal to that during which either party's performance is suspended under this Section. |
The provisions of this section shall not preclude the City from canceling or terminating any resulting award (or any order for any goods or services included herein), or from revising the scope of the Work, as otherwise permitted under this RFP.
| 4.3. | SUPPLIER'S INVOICE |
| 4.3.1. | The Supplier shall prepare and submit invoices to the attention of the project manager at: City of Griffin, Attn: (insert project manager name), PO Box T, Griffin, GA 30224. A proper invoice must include the items listed below: |
(a) Name and address of the Supplier.
(b) Invoice date and invoice number. (The Supplier should date invoices as close as possible to the date of the mailing or transmission.)
(c) Purchase order number for supplies delivered or work completed.
(d) Description, quantity, unit of measure, unit price, and extended price of supplies delivered.
(e) Shipping and payment terms (e.g., shipment number and date of shipment, discount for prompt payment terms).
(f) Name and address to which payment is to be sent.
(g) Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.
(h) Any other information or documentation required by the contract (e.g., evidence of shipment).
4.3.2. A summary invoice shall be provided for all deliveries made during a billing period, identifying the delivery tickets covered therein, stating their total dollar value. A summary invoice shall be supported by receipt copies of the delivery tickets. Delivery tickets or sales slips shall contain:
(a) Name of supplier
(b) Purchase Order number
(c) Ship to Department and Address
(d) Description, Quantity, unit price, and extension of each item.
(e) Date of delivery or shipment.
4.4. TAX LIABILITY
The successful supplier will be provided with the City’s Sales and Use Tax Certificate of Exemption number upon request.
4.5. PAYMENT
Payment will be made for items accepted by the City; standard terms are net 30.
4.6. ESTIMATED QUANTITIES
The quantities of items specified in the Bid Schedule are estimates only and are not purchased by this contract. If the City’s requirements do not result in orders in the quantities described as "estimated", that fact shall not constitute the basis for an equitable price adjustment. Delivery shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order clause or elsewhere in this contract, the Vendor shall furnish to the City all items specified in the Bid Schedule and called for by orders issued in accordance with the Ordering clause.
4.7. ASSIGNMENT OR NOVATION OF CONTRACT
The Supplier shall not assign or transfer, whether by Assignment or Novation, any of its rights, duties, benefits, obligations, liabilities, or responsibilities under the Contract without the written consent of the City; provided, however, that assignments to banks, trust companies or other financial institutions for the purpose of securing a bond may be made without the consent of the City.
4.8. TERMINATION FOR CAUSE
The City reserves the right to terminate the resulting contract, in whole or in part, for failure to comply with any provisions of the contract as outlined by providing a written notice to the Supplier at least thirty (30) days before the effective date of termination. The Supplier will not be relieved of any outstanding responsibilities or unfinished obligations under this contract. Receipt of items by the delivery date is critical to the terms of this contract. The City considers late delivery of contract items as reasonable cause to terminate the contract.
Prior to termination, a Cure Notice will be issued by the City. The Notice will identify the problems and deadlines that need to be met to remedy the problems to avoid termination for default. If the Supplier does not respond with an acceptable action plan to remedy the default or commence to remedy the default within a period of five (5) business days (or such longer period as the City may authorize in writing) after the issuance of notice, the City may issue termination for cause.
4.9. TERMINATION FOR CONVENIENCE
The City reserves the right to terminate the resulting contract, in whole or in part, in the event the City determines that such termination is in the best interest of the City, such as an unforeseen project cancellation. Any such termination shall be effected by the delivery of a notice specifying the extent to which performance of work under the contract is termination and the date upon which the termination becomes effective. The City will payment of deliverables satisfactorily executed according to industry standards or proven loss with respect to materials, etc.
4.10. TERMINATION FOR FUND APPROPRIATION
The City may unilaterally terminate this Agreement due to a lack of funding at any time by written notice to the Supplier. In the event of the City's termination of the resulting contract for fund appropriation, the Supplier will be paid for those services actually performed. Partially completed performance of the Agreement will be compensated based upon a signed statement of completion to be submitted by the Service Provider which shall itemize each element of performance
4.11. CHANGES
All work and materials furnished for this project shall be made in conformance with the contract documents. Changes in the scope of work or the terms and conditions of this contract may be made only by written agreement of the parties. Changes that involve an alteration to the payment amounts shall not commence until approved by the City and a Change Order has been issued.
4.12. REPORTING DISPUTES
The Supplier shall report any contract disputes and/or problems to the Purchasing Coordinator, both verbally and in writing within 48 hours of their occurrence.
5. SECTION V –INSURANCE REQUIREMENTS
Sections II - V review the general terms and conditions. Any bid-specific information noted in Section I or in the Specifications & Response Section will take precedence.
Prior to commencing work, the Supplier shall procure and maintain at their own cost and expense for the duration of the agreement the following insurance against claims for injuries to person or damages to property which may arise from or in connection with the performance of the work or services hereunder by the Vendor, his agents, representatives, employees or Subcontractors. A Certificate of Insurance (COI) and any other documents required by the City must be submitted to the City prior to the commencement of any work. In the event of failure to supply the required documentation, the City shall have the right to recover any costs or damages incurred.
The City of Griffin, its agents, elected officials, and employees shall be included as additionally named insured with respect to all liability policies herein except the professional liability coverage and worker’s compensation which shall be indicated on all applicable certificates of insurance. The insurance Certificates indicated above shall carry a written notice of change cancellation and shall be submitted in a reasonable period prior to the execution of any work under this contract. It shall be the responsibility of the Supplier to provide similar insurance for each subcontractor, or to provide evidence that each subcontractor carries his own insurance in like amounts, prior to the time such subcontractor proceeds to perform under the contract. The Supplier’s insurance policy shall be primary for the additional insured, and not excess over any policy held by the additional insured.
The information described below sets forth minimum amounts and coverage and is not to be construed in any way as a limitation on the Vendor’s liability.
| 5.1. | STANDARD INSURANCE REQUIREMENTS |
| 5.1.1. | The City reserves the right to require higher insurance limits on any contract, provided notice of such requirement is stated in the solicitation. |
| 5.1.2. | Commercial General Liability Insurance - $1,000,000 limit per person, $2,000,000 per occurrence for property damage and bodily injury. The Supplier should indicate in the proposal and on the insurance certificate that the coverage provided is occurrence based. The City of Griffin shall be named as "additional insured” as its interest may appear and “waiver of subrogation granted”. The insurance shall include coverage for the following: |
| • | Premise/Operations |
| • | Explosion, Collapse and Underground Property Damage Hazard (only when applicable to the |
| project) | |
| • | Products/Completed Operations |
| • | Contractual |
| • | Independent Contractors |
| • | Broad Form Property Damage |
| • | Personal Injury |
| 5.1.3. | Automobile Insurance - $1,000,000 limit per person or $2,000,000 combined single limit for property damage and personal injury. |
| • | Owned/Leased Autos |
| • | Non-owned Autos |
| • | Hired Autos |
| 5.1.4. | Umbrella Coverage | |
| 5.1.4.1. | Workers’ Compensation and Employers’ Insurance -- with benefits and monetary limits as set forth by Title 34, Chapter 9 of the O.C.G.A. Workers’ Compensation coverage is required as a condition of performing work or services for the City whether or not the Supplier is otherwise required by law to provide such coverage. The Supplier shall supply the City with proof of compliance with the Workers’ Compensation Act while performing work for the City by way of a COI. This proof must be received by the City prior to the commencement of work. If the Supplier does not meet the requirement for workers’ compensation coverage, the certificate of insurance shall state that the contractor waives subrogation in regard to workers’ compensation. | |
| 5.1.4.2. | Professional Liability/Errors & Omissions Insurance - $2,000,000 or as per project (ultimate loss value per occurrence). Primarily E&O insurance is designed to protect the professional advice providers (i.e. consultants, financial services) or professional service-providing professionals (i.e. medical providers, lawyers). | |
| 5.2. | OTHER INSURANCE PROVISIONS | |
| 5.2.1. | All Coverage | |
| 5.2.1.1. | Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, canceled, reduced in coverage or in limits except after thirty (30) days prior written notice has been given to the City. | |
| 5.2.1.2. | If the Supplier, for any reason, fails to maintain insurance coverage which is required pursuant to this Agreement, the same shall be deemed a material breach of contract. City, at its sole option, may terminate this Agreement and obtain damages from the Supplier resulting from said breach. | |
| 5.2.1.3. | Alternatively, the City may purchase such required insurance coverage (but has no special obligation to do so), and without further notice to the Supplier, the City may deduct from sums due to the Supplier any premium costs advanced by City for such insurance. | |
| 5.2.2. | Commercial General Liability and Automobile Liability Coverage | |
| 5.2.2.1. | The City, members of its City Commission, boards, commissions and committees, officers, agents, employees and volunteers are to be covered as insured as respects: liability arising out of activities performed by or on behalf of the Supplier; products and completed operations of the Supplier; premises owned, leased or used by the Supplier or premises on which the Supplier is performing services on behalf of the City. The coverage shall contain no special limitations on the scope of protection afforded to the City, members of the City Commission, boards, commissions and committees, officers, agents, employees and volunteers. | |
| 5.2.2.2. | The Supplier’s insurance coverage shall be primary insurance as respects the City, members of its City Commission, boards, commissions and committees, officers, agents, employees and volunteers. Any insurance or self-insurance maintained by the City, members of its City Commission, boards, commissions and committees, officers, agents, employees and volunteers shall be excess of the Suppliers's insurance and shall not contribute with it. | |
| 5.2.2.3. | Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City, members of its City Commission, boards, commissions and committees, officers, agents, employees and volunteers. | |
| 5.2.2.4. | Coverage shall state that Supplier's insurance shall apply separately to each insured against to whom a claim is made or suit is brought, except with respect to the limits of the insurer's liability. | |
| 5.2.3. | Workers' Compensation and Employers’ Liability and Property Coverage |
The insurer shall agree to waive all rights of subrogation against the City, member of its’ City Commission, boards, commissions and committees, officers, agents, employees and volunteers for losses arising from activities and operations of the Supplier in the performance of services under this Agreement.
5.2.3.1. Deductibles and Self-Insured Retention
| Any deductibles or self-insured retentions must be declared to the City. | |
| 5.2.3.2 | Acceptability of Insurer |
Insurance is to be placed with Georgia admitted A-rated carriers or better by A.M. Best's rating service.
5.2.4. Verification of Coverage
Supplier shall furnish the City with certificates of insurance and with original endorsements affecting coverage required by this clause. The certificates and endorsements for each policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The certificates and endorsements are to be received and approved by the City before work commences.
| 5.2.5. | Subcontractors | |
| Subcontractors must also be insured under the policies of insurance required herein. | ||
| 6. | REQUIRED IMMIGRATION/ENTITLEMENT AFFIDAVITS FOR GEORGIA |
For the successful Suppliers contracting for physical labor or providing services with the City:
6.1. VENDOR/CONTRACTOR AFFIDAVIT
6.1.1. Pursuant to the Georgia Security and Immigration Compliance Act of 2006, the Supplier understands and agrees that compliance with the requirements of O.C.G.A. § 13-10-91 and Georgia Department of Labor Rule 300-10-1-.02 are conditions of this Agreement. The Supplier further agrees that such compliance shall be attested by the Contractor through execution of the contractor affidavit required by Georgia Department of Labor Rule 300-10-1-.07, or a substantially similar supplier affidavit. The Supplier's fully executed affidavit is attached hereto as an Exhibit and is incorporated into this Agreement by reference herein.
6.2. SUBCONTRACTORS
6.2.1. The Supplier understands and agrees that, in the event the Supplier employs or contracts with any subcontractor or subcontractors in connection with this Agreement, the Supplier shall:
| 6.2.1.1. | Be responsible to the City for the acts and omissions of a sub-contractor or persons employed by said sub-contractor to the same extent that the Supplier is liable to the City. |
| 6.2.1.2. | Secure from each such subcontractor an indication of the employee number category as identified in O.C.G.A. § 13-10-91 that is applicable to the subcontractor; |
| 6.2.1.3. | Secure from each such subcontractor an attestation of the subcontractor's compliance with O.C.G.A. § 13-10-91 and Georgia Department of Labor Rule 300-10-1-.02 by causing each such subcontractor to execute the subcontractor affidavit required by Georgia Department of Labor Rule 300-10-1-.08, or a substantially similar subcontractor affidavit. The Supplier further understands and agrees that the Supplier shall require the executed subcontractor affidavit to become a part of the agreement between the Supplier and each such subcontractor. The Supplier agrees to maintain records of each subcontractor attestation required hereunder for inspection by the Department at any time." |
7. TITLE VI –as applied through the Civil Rights Restoration Act of 1987
The CITY OF GRIFFIN, GEORGIA, in accordance with Title VI of the Civil Rights Act of 1964, 42 U.S.C. 2000d to 2000d-4, as amended by The Civil Rights Restoration Act of 1987, hereby notifies all suppliers that no person shall on the grounds of race, color, national origin, sex, age, and handicap/disability, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity conducted by the CITY regardless of whether those programs, services, and activities are federally-funded or not. Further, it will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises as defined at 49 CFR Part 23 will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, national origin, sex, age, handicap/disabled in consideration for an award.
Please separate and use the following pages with your response submittal.
Additional pages may be used as needed. Thank you for your interest and participation in this opportunity.
RESPONSE SUBMITTAL COVER
BID #22-006
FOR
Griffin / Spalding Wayfinding Signage Project
Submitted by:
| Name of Company: |
| Mailing Address: |
| City/State/Zip: |
| Phone (including area code): |
| E-mail: |
Submittal Deadline:
Tuesday, January 4, 2021 at 2:00 P.M.
FAILURE TO RETURN THIS PAGE AS PART OF YOUR SUBMISSION MAY RESULT IN REJECTION OF RESPONSE
SUPPLIER DISCLOSURES
Respond with a YES or NO for each of the items below. On a separate sheet, detail the circumstances for any item with a YES response and attach to this sheet as part of your submittal. Reference to ‘Supplier’ denotes the organization submitting the response as well as the principal representing the organization.
| ___1 |
| Conflict of interest. A Conflict of Interest exists when personal interests interfere in any way with the best interest of the City. This can arise if any employee, agent of the City or their families will receive a monetary or other type of benefit based on the award of this project or if any supplier has an unfair competitive advantage over other suppliers. A conflict is also perceived if any previous history would make it impossible for the supplier to objectively fulfill the obligations associated with this project. Is there any known conflict of interest with the City or any employee or agent of the City? |
| ___2 |
| Collusion. Collusion Supplier affirms that this response submittal has not been prepared in collusion with any other supplier and the contents of the submission has not been communicated with other potential suppliers or with any agent of the City. |
| ___3 |
| Debarment. Supplier certifies that neither it or its subcontractors is presently debarred, suspended, proposed for debarment, declared ineligible, or otherwise excluded from doing business with any government agency. Has the Supplier been deemed ineligible from participating in any business with any government agency in the past five (5) years? |
| ___4 |
| Litigation. Within the past five (5) years, has the Supplier been the subject of or party to any civil or criminal proceedings or investigations based on wrongful death, fraud, theft, breach of contract, safety, misrepresentation or any other conduct? |
| ___5 |
| Financial stability. Financial stability demonstrates that the Supplier has the resources to complete and the ability to remain in business for the duration of the subsequent contract. Has any petition of bankruptcy, orders or judgment been filed against the supplier in the past five (5) years? |
| ___6 |
| Liquidated Damages. Liquidated Damages are types of compensation designed to reimburse the project owner (City) for certain problems or delays associated with a project; it serves as protection to both parties in the form of ‘contract completion insurance’. Has the Supplier been assessed any liquidated damages or defaulted on any project with a government agency in the past five (5) years? |
| ___7 |
| OSHA. Has the Supplier been cited for any OSHA violations in the past five (5) years? |
SUPPLIER ACKNOWLEDGEMENTS
The Supplier has examined, carefully studied and hereby acknowledges the Specifications and any Addenda and agrees to provide the required services in accordance with this proposal. The Supplier agrees to all specification items listed unless specifically noted on the Exceptions page. The Supplier further certifies that they are not currently debarred from submitting proposals by any agency of the State of Georgia or the federal government.
Specifications . . . . . . . . . . . . . . . . . . . . . . . Acknowledgement _______________ Addendum No. _____ dated _________ Acknowledgement _______________ Addendum No. _____ dated _________ Acknowledgement _______________ Addendum No.
This is the start of the file's text. The full file is on GovTribe.
Other files
| File | Type | Posted |
|---|---|---|
| Price Sheet | — | |
| Addendum #5 Q&A | — | |
| Addendum #7 Q&A | — | |
| Correction : Bid Number | — | |
| Contact Requirements | — | |
| Bid Talley | — | |
| Award Information | — | |
| Sign Layout | — | |
| Notice of Intent to Award | — | |
| W-9 | — | |
| Addendum #4 Q&A | — | |
| E-Verify | — | |
| Addendum #6 Q&A | — |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .