This is Addendum #6 to the Griffin Spalding Wayfinding Signage Project, a Question and Answers document issued by Spalding County and the City of Griffin in Georgia addressing bidder inquiries regarding the directional signage project. The project encompasses 39 signs to be placed throughout Spalding County and the City of Griffin to direct tourists and visitors to key points of interest. The signs have received full approval from the Georgia Department of Transportation (GDOT) and are anticipated for installation in February/March 2022.
The addendum clarifies three critical bidding specifications that were causing confusion among bidders. Sign #28.1 must be added to the bid form as it was not originally listed; sign #2.0 and sign #2 are confirmed to be identical items. Regarding base specifications, the county clarified that the Public Works director requested the inclusion of anchor cages for installation purposes, and the contracting authority committed to providing additional clarification on the specific base requirements, including the distinction between alignment plates with placement bolts and anchor cages. Additionally, the addendum specifies that breakaway requirements apply to all 39 signs in the project, not solely those labeled as Department of Transportation (DOT) signs.
Text of this file
Addendum #6 Griffin Spalding Wayfinding Signage Questions and Answers
1. We noticed that sign #28.1 wasn’t listed on the bid form. Is sign #28.1 taking the place of sign #29?
#28.1 should be on the bid form, if it is not there, it needs to be added
1. We also noticed that sign #2.0 isn’t listed on the bid form. Is sign #2.0 taking the place of sign #2?
Yes #2.0 and #2 are the same thing
1. We are also a little confused on the type of bases we are bidding. I see that in one spot the bid form calls out using an alignment plate and placement bolts. Then I see it also calls out for anchor cages? Can you please clarify what we need to ship in advance of the signs? Also, does the breakaway apply only to the signs labeled as DOT?
The bases, I’ll have to get back with you on. Our Public Works director asked me to add the anchor cages since they would be installing the signs, so I’ll reach out and get back with you ASAP Breakaway should apply to ALL signs
Other files
| File | Type | Posted |
|---|---|---|
| Price Sheet | — | |
| Addendum #5 Q&A | — | |
| Addendum #7 Q&A | — | |
| Correction : Bid Number | — | |
| Contact Requirements | — | |
| Bid Talley | — | |
| Award Information | — | |
| Sign Layout | — | |
| Notice of Intent to Award | — | |
| W-9 | — | |
| Addendum #4 Q&A | — | |
| E-Verify | — | |
| Griffin Spalding Wayfinding | — |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .