About this file

This document is a General Requirements specification for a Veterans Affairs (VA) construction project involving road and parking lot resurfacing. The project scope includes renovation, maintenance, and resurfacing of Veterans Way, Elks Memorial Drive, and the Visitor's Parking Lot at a VA Medical Center. Key requirements include strict security protocols, with contractors required to obtain appropriate badges, comply with VA security management programs, and obtain permission from VA police before accessing the site.

The contract mandates comprehensive site preparation, including demolition and removal of existing site features, with specific attention to operational continuity. Contractors must develop a detailed work plan that ensures the Medical Center can maintain 24/7 operations, coordinate utility services interruptions with the Contracting Officer's Representative (COR), and protect existing infrastructure. Additional requirements include maintaining as-built drawings, protecting existing vegetation and structures, managing utility services, and following specific guidelines for temporary facilities, vehicle restrictions, and site access. The project involves careful phasing to minimize disruption to medical center operations while completing road and parking lot improvements.

View the file

Other files

File Type Posted
36C24225B0025 0002.docx DOCX document
36C24225B0025 0001.docx DOCX document
WD.pdf PDF
Site Visit Sign In Sheet Resurface Parking Lot.pdf PDF
Pavement Markings.docx DOCX document
Sustainable Construction Requirements.docx DOCX document
Asphalt Paving.docx DOCX document
Buy American Certificate.pdf PDF
Striping.pdf PDF
Quality Control.docx DOCX document
Solicitation Resurface Roadways and Patient Parking Lot.pdf PDF
Safety Requirements.docx DOCX document
Joint Sealants.docx DOCX document
Project Schedule.docx DOCX document
Resurface Visitor Lot 2.pdf PDF
Testing Laboratory Services.docx DOCX document
Earthwork.docx DOCX document
Auto Desk Build Documentation.pdf PDF
Resurface Visitor Lot 1.pdf PDF
Construction Waste Management.docx DOCX document
Demolition.docx DOCX document
Wage Determination.pdf PDF
VA Notice of Limitations on Subcontracting.docx DOCX document
Drawings.docx DOCX document
Shop Drawings and Product Data.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-01-21

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.1 GENERAL INTENTION

Contractor shall completely prepare site for construction operations, including demolition and removal of existing site features, and furnish labor and materials and perform work for the renovation, maintenance and resurfacing of Veterans Way, Elks Memorial Drive and the Visitor’s Parking Lot as required by drawings and specifications.

Visits to the site by Bidders may be made only by appointment with the Contracting Officer.

All employees of general contractor and subcontractors shall comply with VA safety and security management programs and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

STATEMENT OF BID ITEM(S)

ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, roads, walks, grading, drainage, paving necessary removal of existing items and construction and certain other items. See accompanying plans and specifications for full description of required work.

SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

CONSTRUCTION SECURITY REQUIREMENTS

Security Plan:

The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

Security Procedures:

General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

Guards: Not required.

Key Control:

The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officers Representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

The General Contractor shall install all permanent cores at completion of the work. See Section 08 71 00, DOOR HARDWARE and coordinate.

Document Control:

Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

Motor Vehicle Restrictions A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.

OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.

The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

Working space and space available for storing materials shall be as determined by the COR.

Workers are subject to rules of Medical Center applicable to their conduct.

Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

Do not store materials and equipment in other than assigned areas.

Schedule delivery of materials and equipment to immediate construction working areas in quantities sufficient for not more than two workdays. Provide unobstructed access to the Medical Center areas required to remain in operation.

Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, and a schedule defining the duration of the work with milestone subtasks.

1. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates and times on which the Contractor intends to accomplish work in each specific area of site. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site. Arrange such dates and times to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor.

ALTERATIONS

Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of the site where alterations may need to occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer.

DISPOSAL AND RETENTION

Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

Reserved items within the work area (if any) which are to remain property of the Government will be identified by attached tags as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to reinstallation and reuse. Store such items where directed by COR.

Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (FAR 52.236-9) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1. RESTORATION

Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

PHYSICAL DATA – NOT USED

LAYOUT OF WORK

The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor. (FAR 52.236-17)

AS-BUILT DRAWINGS

The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after acceptance of the project by the COR.

Paragraphs A, B, & C shall also apply to all shop drawings.

WARRANTY MANAGEMENT – NOT USED

USE OF ROADWAYS

For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

AVAILABILITY AND USE OF UTILITY SERVICES

The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.

The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

Water (for Construction and Testing): Furnish temporary water service.

Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.

Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

- E N D 01 00 00 -39

File details come from the government source that posted it. Updated .