Demolition.docx
DOCX document 21 KB Posted
- Attached to
- Z1DA--36C242-25-AP-2131 | 528-25-2-8192-0011 Resurface roads and Patient Parking Lot (VA-25-00058338)
- Solicitation number
- 36C24225B0025
About this file
This document is a Demolition Specification (Section 02 41 00) for a VA Medical Center project, detailing requirements for site demolition and debris removal. The specification outlines comprehensive safety protocols, including protecting adjacent areas, managing dust and debris, maintaining fire safety, and preventing damage to existing structures. Key execution requirements include completely removing designated items, breaking up concrete slabs below grade into 24-inch squares, and ensuring daily debris disposal off-site in compliance with federal, state, and local regulations. The related federal contract opportunity involves resurfacing roadways and a patient parking lot at the Albany VA Medical Center, with the solicitation number 36C24225B0025, under the Department of Veterans Affairs Veterans Health Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24225B0025 0002.docx | DOCX document | |
| 36C24225B0025 0001.docx | DOCX document | |
| WD.pdf | ||
| Site Visit Sign In Sheet Resurface Parking Lot.pdf | ||
| Pavement Markings.docx | DOCX document | |
| Sustainable Construction Requirements.docx | DOCX document | |
| Asphalt Paving.docx | DOCX document | |
| Buy American Certificate.pdf | ||
| General Requirements.docx | DOCX document | |
| Striping.pdf | ||
| Quality Control.docx | DOCX document | |
| Solicitation Resurface Roadways and Patient Parking Lot.pdf | ||
| Safety Requirements.docx | DOCX document | |
| Joint Sealants.docx | DOCX document | |
| Project Schedule.docx | DOCX document | |
| Resurface Visitor Lot 2.pdf | ||
| Testing Laboratory Services.docx | DOCX document | |
| Earthwork.docx | DOCX document | |
| Auto Desk Build Documentation.pdf | ||
| Resurface Visitor Lot 1.pdf | ||
| Construction Waste Management.docx | DOCX document | |
| Wage Determination.pdf | ||
| VA Notice of Limitations on Subcontracting.docx | DOCX document | |
| Drawings.docx | DOCX document | |
| Shop Drawings and Product Data.docx | DOCX document |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
08-01-17
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 DESCRIPTION:
This section specifies demolition and removal of site features and other items shown on the accompanying drawings.
1.2 RELATED WORK:
| A. | Demolition and removal of roads, walks, curbs, and ongrade slabs outside buildings to be demolished: Section 31 20 00, EARTH MOVING. |
| B. | Safety Requirements: Section 01 35 26 Safety Requirements Article, ACCIDENT PREVENTION PLAN (APP). |
| C. | Reserved items that are to remain the property of the Government: Section 01 00 00, GENERAL REQUIREMENTS. |
1.3 PROTECTION:
| A. | Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures. Comply with requirements of GENERAL CONDITIONS Article, ACCIDENT PREVENTION. |
| B. | Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations. Comply with requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES AND IMPROVEMENTS. |
| C. | Maintain fences, barricades, lights, and other similar items around exposed excavations until such excavations have been completely filled. |
| D. | Provide enclosed dust chutes with control gates from each floor to carry debris to truck beds and govern flow of material into truck. Provide overhead bridges of tight board or prefabricated metal construction at dust chutes to protect persons and property from falling debris. |
| E. | Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum. Do not use water if it results in hazardous or objectionable condition such as, but not limited to; ice, flooding, or pollution. Vacuum and dust the work area daily. |
| F. | In addition to previously listed fire and safety rules to be observed in performance of work, include following: |
| 1. | Wherever a cutting torch or other equipment that might cause a fire is used, provide and maintain fire extinguishers nearby ready for immediate use. Instruct all possible users in use of fire extinguishers. |
| 2. | Keep hydrants clear and accessible at all times. Prohibit debris from accumulating within a radius of 4500 mm (15 feet) of fire hydrants. |
| G. | Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The contractor shall take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Medical Center; any damaged items shall be repaired or replaced as approved by the Contracting Officer’s Representative (COR). The Contractor shall coordinate the work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. |
| H. | The work shall comply with the requirements of Section 01 00 00, GENERAL REQUIREMENTS and Section 01 35 26, SAFETY REQUIREMENTS. |
1.4 UTILITY SERVICES – NOT USED
PART 2 - PRODUCTS (Not Used)
PART 3 – EXECUTION
3.1 DEMOLITION:
| A. | Completely demolish and remove item slated for removal, including all appurtenances related or connected thereto as shown on the accompanying drawings. |
| B. | Debris, including brick, concrete, stone, metals and similar materials shall become property of Contractor and shall be disposed of by him daily, off the Medical Center to avoid accumulation at the demolition site. Materials that cannot be removed daily shall be stored in areas specified by the COR. Break up concrete slabs below grade that do not require removal from present location into pieces not exceeding 600 mm (24 inches) square to permit drainage. Contractor shall dispose debris in compliance with applicable federal, state or local permits, rules and/or regulations. |
| C. | Remove and legally dispose of all materials, other than earth to remain as part of project work. Materials removed shall become property of contractor and shall be disposed of in compliance with applicable federal, state or local permits, rules and/or regulations. |
3.2 CLEANUP:
On completion of work of this section and after removal of all debris, leave site in clean condition satisfactory to COR. Cleanup shall include off the Medical Center including disposal of all items and materials not required to remain property of the Government as well as all debris and rubbish resulting from demolition operations.
E N D 02 41 00 - 5