FAA Proposal Breakdown Form.pdf
PDF 38 KB Posted
- Attached to
- RFO/Solicitation: SJU TDWR and Road Repairs Project at San Juan Airport in San Juan, PR.
- Solicitation number
- 697DCK-20-R-00293
About this file
This proposal breakdown form and solicitation are for the replacement of the SJU TDWR tower structure, repair of the access road, and refurbishment of the equipment shelter at the San Juan International Airport in San Juan, Puerto Rico. The Federal Aviation Administration Eastern Region Acquisition Service Area, Boston Acquisition Office is seeking offers for the SJU TDWR Replacement and Road Repairs project with an estimated price range from $4.0 million to $7.0 million. The performance period is 409 calendar days from the effective date of the notice to proceed. This procurement is set aside 100% for total small business concerns under NAICS code 236220 with a size standard of $39.5 million. Offerors must submit proposals using the specified FAA proposal breakdown form by the response deadline.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFO NO. 697DCK-20-R-00293
FAA Proposal Breakdown Form
The contractor must furnish all materials, labor, supervision, equipment and everything else whatsoever (except as noted in Section G) to replace the SJU TDWR Tower Structure, Repair the Access Road and refurbish the equipment shelter.
PRICE BREAKDOWN
a b c d
Item Description $ Materials $ Labor $ Equipment $Total
1 General Conditions
2 Site Demolition incl. Tower
3 Fuel Line
4 Building Demolition
5 Site Work
6 Tower
7 Maintenance Platform
8 Perimeter Wall
9 Building Exterior
10 Building Interior
11 Electrical
12 HVAC
13 Sprinkler System for HVAC
14 Access Road Repairs
15 PVC Conduit (Road)
16 Laydown Areas
17 Crane Rental
18 Subtotals :
19 PROJECT SUBTOTAL ALL COSTS (Same as 18 d): $
RFO NO. 697DCK-20-R-00293
20 PROFIT APPLIED TO LINE 19: % $
21 OVERHEAD AND G&A APPLIED TO LINE 19: % $
(Profit on Overhead/G&A not allowed)
22 PROJECT GRAND TOTAL (Total of lines 19, 20 & 21): $
ADDITIONAL COSTS:
FUTURE MODIFICATION
PRICING (successful contractor will be held to these rates for any and all future contract modifications, if any)
1 OVERHEAD % %
2 PROFIT % %
3 INSURANCE % %
4 BONDING % %
NOTES:
1. Offers must be submitted in the format requested in this section. Offers not submitted in the format requested may be deemed non-responsive and eliminated from consideration for award.
2. During negotiations the Contracting Officer (CO) may request a further breakdown of some or all of the costs listed in this section. By submitting an offer the offeror agrees to provide all information requested by the CO or risk being deemed non-responsive and eliminated from consideration of award
File details come from the government source that posted it. Updated .