This solicitation announcement is for a new construction project at the San Juan International Airport in San Juan, Puerto Rico. The Federal Aviation Administration Eastern Region Acquisition Service Area, Boston Acquisition Office is seeking offers for the SJU TDWR Replacement and Road Repairs project. Engineering support will be provided by Maylisse Matos. The performance period is 409 calendar days from the effective date of the Notice to Proceed. This procurement is set aside entirely for small businesses with a NAICS code of 236220 and size standard of $39.5 million. The solicitation includes specifications, drawings, instructions, wage rates, forms and a sample construction waste report. The estimated price range for the project is $4.0 million to $7.0 million. The Acquisition Management System applies in place of the Federal Acquisition Regulation for this FAA procurement.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

M SJU TDWR project in San Juan, PR N/A 1 66

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0004 6/24/20

6. ISSUED BY 7. ADMINISTRATED BY (If other than Item 6)

Federal Aviation Administration

ATTN: AAQ-550

1200 District Ave Burlington, MA 01803

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

Offeror: Please fill name and address here:

9A. AMENDMENT OF SOLICITATION NO.

697DCK-20-R-00293

9B. DATED (SEE ITEM 11)

6/1/20

10A. MODIFICATION OF CONTRACT/ORDER NO.

*TO BE COMPLETED BY VENDOR IF NOT COMPLETE 10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is: extended is not extended.

(a) By completing Item 8 and 15, and returning 2 copies of the amendment; (b) acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hours and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO.

AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

.See Block #14 E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.

1. Amendment #4 issued to incorporate the attached corrected drawings (in place of the ones initially attached under Section J of the RFO) into the Solicitation requirements.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Robert K. Higgins.

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign)

BY

(Signature of Contracting Officer) 6/24/20

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

(a) Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

(b) Item 3 (Effective date).

(1) For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

(2) For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

(3) For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

(4) For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

(5) For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(c) Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

(d) Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original con- tract or order, unless changed by this or a previous modification.

(e) Items 9, (Amendment of Solicitation No.- Dated), and

10, (Modification of Contract/Order No.- Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

(f) Item 12 (Accounting and Appropriation Data). When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(1) Accounting classification Net increase $

(2) Accounting classification Net decrease $

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet."

(g) Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document.

(h) Item 14 (Description of Amendment/Modification).

(1) Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section (if UCF used) headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

(2) Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

(3) State reason for modification.

(4) When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(5) When Template 11 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to -

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(6) Include subject matter or short title of solicitation/ contract where feasible.

(i) Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

CHECKED

AECOM project no.

Copyright © 2014 AECOM Corporation, All Rights Rese rved

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCNISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-D-TDWR-

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIRPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV APPROVED

DATE

REDLINE

DATE

DESCRIPTION JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

DISCIPLINE: GENERAL

NAME : BRIAN E. WILLIFORD

GEORGIA REG. #: RA014107

GENERAL

10/01/2019

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

10/01/2019 100% DESIGN SUBMITTAL

3/ 6/

:0

6:

P M

G000

COVER SHEET

SAN JUAN INTERNATIONAL AIRPORT (SJU)

TERMINAL DOPPLER WEATHER RADAR(TDWR)

OCTOBER 1, 2019

REV

MARCH 5, 2020

3/5/2020

MAYLISSE MATOS COURTNEY NOLAN

Lowe, Jeff A (Atlanta) Typewriter 1604531

G000 COVER SHEET

G001 SHEET INDEX

G002 GENERAL NOTES

C100 OVERALL EXISTING CONDITIONS PLAN

C200 CIVIL DEMOLITION PLAN

C201 CIVIL DEMOLITION PICTURES

C300 OVERALL SITE PLAN

C301 CIVIL SITE PLAN

C400 EROSION CONTROL PLAN

C401 EROSION CONTROL DETAILS

C500 HVAC UNIT WASHDOWN SYSTEM PLAN

C600 ACCESS ROAD EXISTING CONDITIONS, BORINGS AND PROJECT LIMITS

C601 ACCESS ROAD GEOMETRIC LAYOUT

C602 ACCESS ROAD GRADING PLAN AND PROFILE

C603 ACCESS ROAD CROSS SECTIONS

C604 ACCESS ROAD CROSS SECTIONS

C605 ACCESS ROAD CIVIL DETAILS

A101 FLOOR AND ROOF PLAN

A102 EXTERIOR ELEVATION

A201 PICTURE REFERENCES

A202 PICTURE REFERENCES

A203 NEW SIGNAGE REQUIREMENTS

S001 GENERAL NOTES

S010 OVERALL SITE PLAN

S020 TOWER ISOMETRICS

S030 BRACING ELEVATIONS

S101 FOUNDATION PLANS

S102 FIRST & SECOND FLOOR FRAMING PLAN

S103 THIRD & FOURTH FLOOR FRAMING PLAN

S104 FIFTH FLOOR FRAMING PLAN

S201 BRACING DETAILS

S202 BRACING DETAILS

S210 CABLE BRIDGE SUPPORT

S301 FOUNDATION DETAILS

S302 STRUCTURAL STEEL DETAILS

S303 STRUCTURAL STEEL DETAILS

S401 STAIR AND LANDING PLANS

S402 STAIR TYPICAL PLANS AND DETAILS

S403 STAIR TYPICAL DETAILS

S501 MEMBER FORCES

S502 CORROSION PROTECTION

S601 PHOTO REFERENCE

S602 WALL REPAIR DETAILS

S701 MAINTENANCE LEVEL REFURBISHMENT

S702 MAINTENANCE LEVEL REFURBISHMENT

M-101 HVAC PLAN - RADAR TOWER

M-501 SCHEDULES & DETAILS

M-601 PICTURE REFERENCE

E001 ABBREVIATIONS AND SYMBOLS LISTS

E002 ELECTRICAL GENERAL NOTES

E101 EQUIPMENT BLDG - LIGHTING AND POWER PLAN

E102 EQUIPMENT BLDG - GROUNDING PLAN

E103 EQUIPMENT BLDG - SYSTEMS PLAN

E104 TOWER ELECTRICAL PLANS

E105 TOWER GROUNDING PLAN

E501 DETAILS

E601 PHOTO REFERENCES

E602 PHOTO REFERENCES

E603 PHOTO REFERENCES

E604 PHOTO REFERENCES

E605 PHOTO REFERENCES

E606 PHOTO REFERENCES

E607 PHOTO REFERENCES

SHEET INDEX

GENERAL

CIVIL

ARCHITECTURE

STRUCTURAL

MECHANICAL

ELECTRICAL

CHECKED

AECOM project no.

Copyright © 2014 AECOM Corporation, All Rights Reserved

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCNISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-D-TDWR-

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIRPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV APPROVED

DATE

REDLINE

DATEDESCRIPTION JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

DISCIPLINE: GENERAL

NAME : BRIAN E. WILLIFORD

GEORGIA REG. #: RA014107

GENERAL

10/01/2019

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

10/01/2019 100% DESIGN SUBMITTAL

3/

/2

5:

:1

PM

RJD G001

SHEET INDEX

REV

3/ 5/

3/ 5/

3/5/2020

M A

Y

LI

S S

E M

A

TO

S C

O U

R

TN

E Y

N O

LA

N

M A

Y

LI

S S

E M

A

TO

S C

O U

R

TN

E Y

N O

LA

N

MAYLISSE MATOS COURTNEY NOLAN

Lowe, Jeff A (Atlanta)

GENERAL NOTES

CHECKED

URS project no.

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCN

ISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-TDWR-C

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV

APPROVED

DATE

REDLINE

DATE

DESCRIPTION JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

DISCIPLINE: CIVIL

NAME: JEFFREY A. LOWE

GEORGIA REG. #: 27078

CIVIL

JAL

AAB

JAL

03/05/2020

P

M

AutoCAD SHX Text

GENERAL NOTES

AutoCAD SHX Text

GENERAL SECURITY & SAFETY NOTES

AutoCAD SHX Text

1. PAVEMENT CLOSURES - NO ROADWAY WILL BE CLOSED WITHOUT APPROVAL OF THE RE. PAVEMENT CLOSURES - NO ROADWAY WILL BE CLOSED WITHOUT APPROVAL OF THE RE. WRITTEN REQUESTS FOR CLOSURES ARE TO BE SUBMITTED TO THE RE A MINIMUM OF 3 BUSINESS DAYS PRIOR TO CLOSURE. 2. CONSTRUCTION LIMITS - ALL CONTRACTOR VEHICLES AND CONSTRUCTION TRAFFIC ARE CONSTRUCTION LIMITS - ALL CONTRACTOR VEHICLES AND CONSTRUCTION TRAFFIC ARE REQUIRED TO STAY WITHIN THE LIMITS OF CONSTRUCTION WHILE ON THE CONSTRUCTION SITE. THESE LIMITS ARE STRICTLY ENFORCED. LIMITS SHALL BE DEFINED AT THE PRE-CONSTRUCTION MEETING AND MAY CHANGE DURING CONSTRUCTION AS DIRECTED BY THE RE. TRAFFIC ASSOCIATED WITH CONSTRUCTION IS TO USE ONLY AREAS SHOWN FOR CONSTRUCTION USE. 3. THE CONTRACTOR SHALL NOT PERMIT ANY UNAUTHORIZED PERSONNEL OR TRAFFIC ON THE CONTRACTOR SHALL NOT PERMIT ANY UNAUTHORIZED PERSONNEL OR TRAFFIC ON THE SITE. 4. CONTRACTOR'S SECURITY CLEARANCE: THE CONTRACTOR'S EMPLOYEES SHALL COMPLY CONTRACTOR'S SECURITY CLEARANCE: THE CONTRACTOR'S EMPLOYEES SHALL COMPLY WITH ALL SECURITY CLEARANCE REQUIREMENTS OF THE CONSTRUCTION CONTRACT AND WITH LOCAL AUTHORITIES. 5. THE CONTRACTOR SHALL PREPARE A SITE SECURITY PLAN FOR ALL WORK AND SUBMIT THE CONTRACTOR SHALL PREPARE A SITE SECURITY PLAN FOR ALL WORK AND SUBMIT TO PUERTO RICO AIR NATIONAL GUARD (PRANG)/FAA FOR APPROVAL PRIOR TO COMMENCEMENT. ANY PROPOSED ADJUSTMENTS TO THE EXISTING SIDA FENCE MUST BE APPROVED BY FAA/PRANG. APPROVAL MAY TAKE UP TO 45 DAYS.

AutoCAD SHX Text

PROTECTION OF REMAINING ITEMS DURING DEMOLITION

AutoCAD SHX Text

1. PROTECT ALL ITEMS DESIGNATED TO REMAIN FROM DISTURBANCES OR DAMAGE DURING PROTECT ALL ITEMS DESIGNATED TO REMAIN FROM DISTURBANCES OR DAMAGE DURING DEMOLITION. 2. EXISTING FENCING SHALL BE PROTECTED DURING DEMOLITION. EXISTING FENCING SHALL BE PROTECTED DURING DEMOLITION. 3. THE CONTRACTOR SHALL PROTECT ANY PAVEMENT, SIDEWALK, CURB AND GUTTER, THE CONTRACTOR SHALL PROTECT ANY PAVEMENT, SIDEWALK, CURB AND GUTTER, UTILITY STRUCTURES THAT ARE TO REMAIN. THE RE AND CONTRACTOR SHALL FIELD VERIFY ALL ITEMS THAT ARE TO BE PROTECTED PRIOR TO EACH PHASE OF DEMOLITION. ANY DAMAGE SHALL BE REPAIRED TO AN EQUAL OR BETTER CONDITION THAN THE ORIGINAL TO THE SATISFACTION OF THE RE AND AT THE CONTRACTOR'S OWN EXPENSES.

AutoCAD SHX Text

GENERAL DEMOLITION AND REMOVAL NOTES

AutoCAD SHX Text

1. THE REMOVAL OF ALL FACILITIES SHALL BE PERFORMED BY THE CONTRACTOR UNLESS THE REMOVAL OF ALL FACILITIES SHALL BE PERFORMED BY THE CONTRACTOR UNLESS OTHERWISE INDICATED ON THE DRAWINGS. ALL AREAS WHERE LANDSCAPING HAS BEEN REMOVED SHALL BE RE-STABILIZED AND SODDED IN ACCORDANCE WITH NOTES AND SPECIFICATIONS. 2. ALL LANDSCAPING (TREES, SCRUBS AND GROUND COVER) THAT ARE NOT IDENTIFIED ALL LANDSCAPING (TREES, SCRUBS AND GROUND COVER) THAT ARE NOT IDENTIFIED TO BE REMOVED SHALL BE PROTECTED IN ACCORDANCE WITH DRAWINGS AND SPECIFICATIONS. PROTECT THE LANDSCAPING IN THE AREA TO THE EXTENT FEASIBLE. NO LANDSCAPING REMOVAL SHALL BE DONE WITHOUT APPROVAL OF THE RE. 3. SAW CUT EXISTING PAVEMENT TO BE REMOVED TO PROVIDE CLEAN EDGE, AND REPAIR SAW CUT EXISTING PAVEMENT TO BE REMOVED TO PROVIDE CLEAN EDGE, AND REPAIR AREAS OF BROKEN PAVEMENT ACCORDINGLY. PAVEMENT REMOVED TO BE HAULED TO A LICENSED RECYCLER UNLESS OTHERWISE APPROVED BY THE RE.

AutoCAD SHX Text

1. PRIOR TO INITIATING CONSTRUCTION, THE CONTRACTOR SHALL FIELD INSPECT PRIOR TO INITIATING CONSTRUCTION, THE CONTRACTOR SHALL FIELD INSPECT CURRENT CONDITIONS AND DETERMINE IF CONDITIONS THAT ARE NOT REFLECTED ON THESE PLANS EXIST. THE CONTRACTOR SHALL NOTIFY THE RE IN WRITING OF THE RESULTS OF THE INSPECTION, IF THERE ARE PROBLEM AREAS, THE RE SHALL DIRECT THE CONTRACTOR ON HOW TO PROCEED WITH WORK IN THE PROBLEM AREAS. THE CONTRACTOR SHALL NOT INITIATE WORK, ORDER MATERIALS OR FABRICATE IN AREAS WHERE THERE ARE IDENTIFIED PROBLEMS UNLESS APPROVED IN WRITING BY THE RE. 2. THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING UTILITIES WITH GROUND THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING UTILITIES WITH GROUND PENETRATING RADAR (GPR) PRIOR TO BEGINNING OF DEMOLITION WORK. ANY UTILITY THAT IS TO REMAIN SHALL BE PROTECTED DURING CONSTRUCTION. 3. THE EXISTING FEATURES SHOWN ARE BASED ON THE BEST AVAILABLE AS BUILT THE EXISTING FEATURES SHOWN ARE BASED ON THE BEST AVAILABLE AS BUILT DRAWINGS. ALL UTILITIES MAY NOT BE SHOWN ON DRAWINGS. CONTRACTOR SHALL USE GPR TO FIELD VERIFY LOCATION OF ALL UTILITIES. 4. ALL OPEN EXCAVATIONS AND TRENCHES SHALL BE CONTINUOUSLY BARRICADED, MARKED ALL OPEN EXCAVATIONS AND TRENCHES SHALL BE CONTINUOUSLY BARRICADED, MARKED AND LIGHTED TO THE SATISFACTION OF THE RE. 5. CONSTRUCTION SITE ACCESS AND HAUL ROADS: ACCESS TO THE JOB SITE SHALL BE CONSTRUCTION SITE ACCESS AND HAUL ROADS: ACCESS TO THE JOB SITE SHALL BE VIA SPECIFIC ROUTE ESTABLISHED AT THE PRE-CONSTRUCTION MEETING. ACCESS AND HAUL ROUTES MAY CHANGE DURING CONSTRUCTION AS DIRECTED BY THE RE. THE CONTRACTOR SHALL LOCK GATE AFTER EACH INGRESS/EGRESS. THE CONTRACTOR SHALL REPAIR ANY DAMAGE TO ROADS, RESULTING FROM EXECUTING THIS CONTRACT, AT NO ADDITIONAL COST TO THE GOVERNMENT. ALL CONTRACTOR VEHICLES AND TRAFFIC SHALL REMAIN WITHIN THE LIMITS OF CONSTRUCTION AREA, STAGING AREA, OR HAUL ROUTES. 6. STAGING AREA - THE CONTRACTOR'S STAGING AREA WILL BE SPECIFIED AT THE STAGING AREA - THE CONTRACTOR'S STAGING AREA WILL BE SPECIFIED AT THE PRE-CONSTRUCTION MEETING. THE CONTRACTOR SHALL MAKE PROVISIONS FOR ANY REQUIRED UTILITIES. THE CONTRACTOR SHALL PROVIDE SECURITY FENCE AROUND STAGING AREAS. UPON COMPLETION OF THE PROJECT, THE CONTRACTOR SHALL RESTORE THE STAGING AREA; INCLUDING THE REPAIR OF EXISTING FACILITIES, REMOVAL OF UTILITIES, RE-GRADING, TOP SOILING, AND RE-SEEDING COMPLETE TO THE SATISFACTION OF THE RE. 7. CONTRACTOR TO ENSURE THAT ALL TRAFFIC OVER EXISTING OR CONSTRUCTED CONTRACTOR TO ENSURE THAT ALL TRAFFIC OVER EXISTING OR CONSTRUCTED IMPROVED ROADWAYS ARE WITHIN THE DESIGN WEIGHT RANGE OF ROADS AND IS RESPONSIBLE FOR REPAIRS OF ANY DAMAGE OR DETERIORATION TO ROADS. 8. THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING OGPe PERMIT AND THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING OGPe PERMIT AND COMPLIANCE. THE SINGLE OPERATIONAL INCIDENTAL PERMIT (IN SPANISH, "PERMISO UNICO INCIDENTAL OPERCACIONAL") MUST BE APPLIED FOR AT THE OFFICE OF PERMITS MANAGEMENT (IN SPANISH, "OFICINA DE GERENCIA DE PERMISOS" OR OGPe) OF THE DEPARTMENT OF ECONOMIC DEVELOPMENT AND COMMERCE (DDEC, BY ITS SPANISH INITIALS). THE CONSOLIDATED OGPe PERMIT SHALL INCLUDE THE FOLLOWING SCOPE ITEMS: CONSTRUCTION OF THE NEW TOWER; EROSION AND SEDIMENT CONTROL; FUGITIVE DUST/AIR EMISSIONS; AND SOLID WASTE DISPOSAL. 9. THE CONTRACTOR SHALL ENSURE THAT ALL DEMOLITION-GENERATED SOLID WASTES, THE CONTRACTOR SHALL ENSURE THAT ALL DEMOLITION-GENERATED SOLID WASTES, INCLUDING THOSE THAT CONSIST OF ASBESTOS, LEAD, PCB'S, CFC'S OR OTHER HAZARDOUS CONSTITUENTS, WASTES, SUBSTANCES, OR MATERIALS, THAT CONTAIN REGULATED LEVELS, ARE MANAGED TO AVOID CONTAMINATION OF ENVIRONMENTAL MEDIA AND HANDLED AND DISPOSED OF CONSISTENT WITH ALL APPLICABLE REGULATIONS AND AT AN ENVIRONMENTALLY APPROVED WASTE SITE. 10. CONTRACTOR SHALL ACCOUNT FOR 30% OF WORKING HOURS TO OCCUR AT NIGHT OR CONTRACTOR SHALL ACCOUNT FOR 30% OF WORKING HOURS TO OCCUR AT NIGHT OR DURING EARLY MORNING HOURS DUE TO WEATHER CONDITIONS. 11. ENDANGERED SPECIES ANTILLEAN MANATEE (TRICHECHUS MANATUS MANATUS) AND ENDANGERED SPECIES ANTILLEAN MANATEE (TRICHECHUS MANATUS MANATUS) AND GREEN TURTLE (CHELONIAS MYDAS) HAVE BEEN DOCUMENTED AT OR NEAR THE PROJECT AREA, ESPECIALLY AT THE SMALL LAGOON NORTH OF THE ACCESS ROAD. REFER TO SPEC SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS. 12. ONLY LOW-PRESSURE SODIUM-VAPOR (LPS) LAMPS MOUNTED IN SHIELDED LUMINARIES ONLY LOW-PRESSURE SODIUM-VAPOR (LPS) LAMPS MOUNTED IN SHIELDED LUMINARIES ARE TO BE USED FOR TEMPORARY LIGHTING. 1) LIGHT BEAM SHALL BE POINTED DOWNWARD. LIGHT BEAM SHALL BE POINTED DOWNWARD. 2) LIGHT BEAM SHALL NOT REACH BEACH.LIGHT BEAM SHALL NOT REACH BEACH.

AutoCAD SHX Text

GENERAL EROSION CONTROL NOTES

AutoCAD SHX Text

1. ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL CONFORM TO THE MOST RECENT ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL CONFORM TO THE MOST RECENT REQUIREMENTS OF PUERTO RICO EROSION AND SEDIMENT CONTROL HANDBOOK FOR DEVELOPING AREAS. 2. THE RE MAY DIRECT THE CONTRACTOR TO ADD NEW MEASURES TO CONTROL EROSION AND THE RE MAY DIRECT THE CONTRACTOR TO ADD NEW MEASURES TO CONTROL EROSION AND SEDIMENT TRANSPORT AT ANY TIME DURING THE PROJECT. 3. THE CONTRACTOR SHALL LIMIT CLEARING AND LAND DISTURBANCE TO THE MINIMUM THE CONTRACTOR SHALL LIMIT CLEARING AND LAND DISTURBANCE TO THE MINIMUM NECESSARY FOR EXECUTING THE WORK INDICATED IN THE CONSTRUCTION DOCUMENTS. PROMPTLY RE-STABILIZE, DISTURBED AREAS IN ACCORDANCE WITH THE PUERTO RICO EROSION AND SEDIMENT CONTROL HANDBOOK FOR DEVELOPING AREAS. 4. CONSTRUCT ALL PERIMETER SEDIMENT CONTROL MEASURES TO INCLUDE BUT NOT LIMITED CONSTRUCT ALL PERIMETER SEDIMENT CONTROL MEASURES TO INCLUDE BUT NOT LIMITED TO, SILT FENCE, INLET PROTECTION AND STABILIZE CONSTRUCTION ENTRANCE IN ACCORDANCE WITH THE PUERTO RICO EROSION AND SEDIMENT CONTROL HANDBOOK FOR DEVELOPING AREAS PRIOR TO ANY DISTURBANCE. 5. ALL DISTURBED AREAS ARE TO BE PERMANENTLY VEGETATIVELY STABILIZED UNLESS THEY ALL DISTURBED AREAS ARE TO BE PERMANENTLY VEGETATIVELY STABILIZED UNLESS THEY ARE INDICATED TO BE AN IMPERVIOUS SURFACE, IN ACCORDANCE WITH THE PUERTO RICO EROSION AND SEDIMENT CONTROL HANDBOOK FOR DEVELOPING AREAS. 6. AREAS OF STOCKPILED MATERIALS WITHIN THE CONSTRUCTION AREA ARE TO BE TREATED AREAS OF STOCKPILED MATERIALS WITHIN THE CONSTRUCTION AREA ARE TO BE TREATED IN SUCH A MANNER AS TO PREVENT MOVEMENT OR EROSION RESULTING FROM WIND OR RAINFALL. THE CONTRACTOR IS RESPONSIBLE FOR IMMEDIATE CLEANUP OF ANY DEBRIS THAT FALLS ON PARKING LOT AND ROADWAY PAVEMENT. CONTRACTOR IS TO SWEEP ON A DAILY BASIS, ALL ROADWAYS THAT ARE ALONG THE CONTRACTOR'S HAUL ROUTES AND IMMEDIATELY CLEANUP MUD OR DEBRIS THAT FALLS ON ANY PAVEMENT OUTSIDE OF THE CONTRACTOR'S LIMITS OF CONSTRUCTION. 7. SPREAD WHEAT STRAW MAT ON DISTURBED AREAS DAILY FOR EROSION CONTROL. SPREAD WHEAT STRAW MAT ON DISTURBED AREAS DAILY FOR EROSION CONTROL. 8. EROSION AND SEDIMENT CONTROL MEASURES SHALL BE REMOVED ONLY WHEN AUTHORIZED EROSION AND SEDIMENT CONTROL MEASURES SHALL BE REMOVED ONLY WHEN AUTHORIZED BY THE RE.

AutoCAD SHX Text

1. THE EXISTING DRAINAGE STRUCTURE SHALL BE MAINTAINED FOR FINAL GRADING. THE EXISTING DRAINAGE STRUCTURE SHALL BE MAINTAINED FOR FINAL GRADING. EROSION CONTROL MEASURES SHALL BE MAINTAINED DURING DEMOLITION AND RE-VEGETATION. 2. CONTRACTOR SHALL GRADE ALL DISTURBED AREAS TO ENSURE POSITIVE DRAINAGE TO CONTRACTOR SHALL GRADE ALL DISTURBED AREAS TO ENSURE POSITIVE DRAINAGE TO DRAINAGE STRUCTURES AND DITCHES. NATURAL FLOW OF SURROUNDING WATERS SHALL NOT BE DISTURBED DURING CONSTRUCTION. 3. THE CONTRACTOR SHALL PROPERLY DISPLAY THE LAND DISTURBANCE PERMIT ON THE SITE THE CONTRACTOR SHALL PROPERLY DISPLAY THE LAND DISTURBANCE PERMIT ON THE SITE AT ALL TIME DURING CONSTRUCTION. 4. CONTRACTOR SHALL INCORPORATE BEST MANAGEMENT PRACTICE PRIOR TO ANY DEMOLITION CONTRACTOR SHALL INCORPORATE BEST MANAGEMENT PRACTICE PRIOR TO ANY DEMOLITION WORK. ANY DAMAGE TO THE NATURAL RESOURCES SHALL BE RESTORED BACK TO ITS ORIGINAL STATE AT THE CONTRACTOR'S EXPENSE. 5. TOPSOIL SHALL BE STRIPPED AND STOCKPILED AS APPROVED BY THE RE WITHIN THE TOPSOIL SHALL BE STRIPPED AND STOCKPILED AS APPROVED BY THE RE WITHIN THE ENTIRE LIMITS OF THE GRADING AREA OF THE PROJECT. TOPSOIL, WHEN STORED, SHALL BE KEPT SEPARATE FROM OTHER EXCAVATED MATERIALS. TOPSOIL IN EXCESS OF THAT REQUIRED FOR PREPARATION OR REPAIR OF NEW OR EXISTING LAWN AREAS, SHALL BE DISPOSED OF OFF THE SITE BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE GOVERNMENT. 6. EXCAVATED MATERIALS THAT MEET THE REQUIREMENT FOR EARTH FILL MAY BE USED FOR EXCAVATED MATERIALS THAT MEET THE REQUIREMENT FOR EARTH FILL MAY BE USED FOR BACKFILL. ALL UNSUITABLE EXCAVATED MATERIALS SHALL BE DISPOSED OF OFFSITE BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE GOVERNMENT. 7. WHEN EXCAVATIONS HAVE REACHED THE REQUIRED DEPTHS, THE EXCAVATED SURFACES WHEN EXCAVATIONS HAVE REACHED THE REQUIRED DEPTHS, THE EXCAVATED SURFACES SHALL BE INSPECTED AND APPROVED BY THE RE BEFORE PROCEEDING WITH FURTHER CONSTRUCTION IN THE EXCAVATED AREA. 8. ALL FILLED AREAS SHALL BE COMPACTED TO 95% PROCTOR. ALL FILLED AREAS SHALL BE COMPACTED TO 95% PROCTOR. 9. THE CONTRACTOR SHALL FINE GRADE THE AREA TO PREVENT PONDING ON THE SITE. THE THE CONTRACTOR SHALL FINE GRADE THE AREA TO PREVENT PONDING ON THE SITE. THE RE SHALL INSPECT AND APPROVE THESE AREAS PRIOR TO FINAL GRADING, TOPSOILING AND STABILIZATION. 10. THE CONTRACTOR SHALL ESTABLISH THE HIGH SPOT AS INDICATED ON DRAWINGS. THE THE CONTRACTOR SHALL ESTABLISH THE HIGH SPOT AS INDICATED ON DRAWINGS. THE FINAL DRAINAGE PATTERNS SHALL NOT DIFFER FROM THE EXISTING PATTERNS. THE MAJORITY OF THE DRAINAGE WILL FLOW TO THE NATURAL PATTERNS. 11. THE CONTRACTOR SHALL GRADE THE AREA TO SHEET FLOW IN ALL DIRECTIONS.THE CONTRACTOR SHALL GRADE THE AREA TO SHEET FLOW IN ALL DIRECTIONS.

AutoCAD SHX Text

GENERAL GRADING NOTES

AutoCAD SHX Text THE CONTRACTOR SHALL SUBMIT TO THE FAA A REMOVAL SEQUENCE PLAN FOR THE REMOVAL OF THE MAINTENANCE LEVEL (UPPER AND LOWER LEVELS), RADOME MOUNTING RING ASSEMBLY, AND RADAR ANTENNA MOUNTING EQUIPMENT (I.E. BARBETTE). THE CONTRACTOR SHALL RECEIVE WRITTEN NOTIFICATION TO PROCEED WITH EQUIPMENT REMOVAL PRIOR TO ANY EQUIPMENT OR STRUCTURE REMOVAL. THE REMOVAL SEQUENCE PLAN SHALL INCLUDE THE FOLLOWING: 1. THE CONTRACTOR SHALL PROVIDE CRANE AND OPERATOR FOR 30 DAYS THE CONTRACTOR SHALL PROVIDE CRANE AND OPERATOR FOR 30 DAYS 30 DAYS TO REMOVE THE EXISTING RADAR ANTENNA MOUNTING EQUIPMENT (BARBETTE), RADOME MOUNTING RING ASSEMBLY, AND THE MAINTENANCE PLATFORM LEVEL OF THE EXISTING TOWER PRIOR TO COMMENCEMENT OF ANY DEMOLITION. 2. BARBETTE IS DIRECTLY ATTACHED TO THE STRUCTURAL STEEL MEMBERS BARBETTE IS DIRECTLY ATTACHED TO THE STRUCTURAL STEEL MEMBERS OF THE TOWER'S MAINTENANCE PLATFORM LEVEL. THE BARBETTE'S STRUCTURAL STEEL SUPPORT MEMBERS INCLUDE BRACING THAT EXTENDS BELOW THE MAINTENANCE PLATFORM LOWER LEVEL. 3. THE CONTRACTOR SHALL PROVIDE PERSONAL AND EQUIPMENT NECESSARY THE CONTRACTOR SHALL PROVIDE PERSONAL AND EQUIPMENT NECESSARY TO DISCONNECT STRUCTURAL STEEL MEMBERS THAT SUPPORT THE MAINTENANCE LEVEL/BARBETTE TO THE EXISTING TOWER STRUCTURE. THE CONNECTION BASE PLATES ARE TO BE REUSED INTACT. 4. THE CONTRACTOR AND FAA WILL DETERMINE WHAT THE CONTRACTOR AND FAA WILL DETERMINE WHAT COMPONENTS/EQUIPMENT OF THE MAINTENANCE PLATFORM CAN BE REMOVED PRIOR TO LIFTING OFF EXISTING TOWER. 5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR IDENTIFYING SAFE LIFT THE CONTRACTOR SHALL BE RESPONSIBLE FOR IDENTIFYING SAFE LIFT POINTS FOR BARBETTE, RADOME MOUNTING RING ASSEMBLY, AND STRUCTURAL STEEL MEMBERS OF MAINTENANCE PLATFORM PRIOR TO REMOVAL. CONTRACTOR SHALL SUBMIT LIFT PLAN TO FAA FOR REVIEW PRIOR TO REMOVAL OF EQUIPMENT. 6. THE CONTRACTOR SHALL COORDINATE WITH FAA ON DESIGNATED AREA THE CONTRACTOR SHALL COORDINATE WITH FAA ON DESIGNATED AREA ON "GROUND" FOR PLACEMENT OF BARBETTE, RADOME MOUNTING RING ASSEMBLY, AND STRUCTURAL STEEL MEMBERS OF THE MAINTENANCE PLATFORM PRIOR TO REMOVAL. CONTRACTOR SHALL CONSTRUCT TEMPORARY PLATFORM TO PLACE EQUIPMENT AND PERFORM REFURBISHMENT. SAFELY PLACE THE BARBETTE IN FAA DESIGNATED AREA FOR REFURBISHMENT BY FAA. 7. THE CONTRACTOR SHALL REFER TO SHEET S701 AND S702 FOR SCOPE THE CONTRACTOR SHALL REFER TO SHEET S701 AND S702 FOR SCOPE RELATED TO REFURBISHMENT OF MAINTENANCE LEVEL. 8. UPON COMPLETION OF THE NEW TOWER STRUCTURE, UNDER DIRECTION UPON COMPLETION OF THE NEW TOWER STRUCTURE, UNDER DIRECTION OF FAA, THE CONTRACTOR SHALL PROVIDE CRANE AND OPERATOR FOR 30 DAYS TO REPLACE THE REFURBISHED BARBETTE AND THE TO REPLACE THE REFURBISHED BARBETTE AND THE REFURBISHED MAINTENANCE PLATFORM LEVEL. 9. THE CONTRACTOR SHALL PROVIDE PERSONAL AND EQUIPMENT NECESSARY THE CONTRACTOR SHALL PROVIDE PERSONAL AND EQUIPMENT NECESSARY TO RECONNECT THE STRUCTURAL STEEL MEMBERS THAT SUPPORT THE MAINTENANCE LEVEL/BARBETTE TO THE NEW TOWER STRUCTURE. 10. THE CONTRACTOR SHALL PROVIDE PERSONAL AND EQUIPMENT NECESSARY THE CONTRACTOR SHALL PROVIDE PERSONAL AND EQUIPMENT NECESSARY TO LEVEL AND ALIGN THE MAINTENANCE LEVEL/BARBETTE AS DIRECTED BY FAA FOR PROPER OPERATION OF THE EQUIPMENT.

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text E

AutoCAD SHX Text G

AutoCAD SHX Text I

AutoCAD SHX Text S

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text N

AutoCAD SHX Text 27078

AutoCAD SHX Text

PROFESSIONAL

AutoCAD SHX Text L

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text F

AutoCAD SHX Text N

AutoCAD SHX Text I

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text N

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text F

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text D

AutoCAD SHX Text W

AutoCAD SHX Text I

AutoCAD SHX Text O

AutoCAD SHX Text A.

AutoCAD SHX Text J

AutoCAD SHX Text Y

AutoCAD SHX Text WEIGHTS OF EQUIPMENT BARBETTE: 4,600 LBS 4,600 LBS RADOME MOUNTING RING ASSEMBLY: 4,850 LBS 4,850 LBS MAINTENANCE PLATFORM ASSEMBLY: 6,500 LBS6,500 LBS

AutoCAD SHX Text

GOVERNMENT FURNISHED EQUIPMENT REMOVAL AND REPLACEMENT

AutoCAD SHX Text

12. THE FINAL GRADE SHALL BE ESTABLISHED TO ALLOW EXISTING TREES THE FINAL GRADE SHALL BE ESTABLISHED TO ALLOW EXISTING TREES TO REMAIN. ANY DAMAGE TO THIS SLOPE TO BE REPAIR IMMEDIATELY. 13. BACKFILL AND FINAL GRADING SHALL BE SUFFICIENT TO ALLOW FOR BACKFILL AND FINAL GRADING SHALL BE SUFFICIENT TO ALLOW FOR SETTLEMENT OF FILL AND STILL PROVIDE POSITIVE DRAINAGE AWAY FILL AND STILL PROVIDE POSITIVE DRAINAGE AWAY FROM THE HIGH POINT AREA. 14. NO SLOPE SHALL BE STEEPER THAN 4H : 1V UNLESS AUTHORIZED BY NO SLOPE SHALL BE STEEPER THAN 4H : 1V UNLESS AUTHORIZED BY THE RE.

Lowe, Jeff A (Atlanta)

URS project no.

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCN

ISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-TDWR-C

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV

APPROVED

DATE

REDLINE

DATE

DESCRIPTION

JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

DISCIPLINE: CIVIL

NAME: JEFFREY A. LOWE

GEORGIA REG. #: 27078

CIVIL

JAL

AAB

JAL

03/05/2020

P

M

OVERALL EXISTING CONDITIONS PLAN

MAYLISSE MATOSCOURTNEY NOLAN MAYLISSE MATOSCOURTNEY NOLAN

MAYLISSE MATOS COURTNEY NOLAN

AutoCAD SHX Text

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

AutoCAD SHX Text M

AutoCAD SHX Text

TOP= 49.19

AutoCAD SHX Text

INV= 44.72

AutoCAD SHX Text

CB

AutoCAD SHX Text M

AutoCAD SHX Text

CB

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

TOP= 49.16

AutoCAD SHX Text

INV= 36.96

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text M

AutoCAD SHX Text CONC. PIPE 24" Dia.

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

LW= 49.80

AutoCAD SHX Text T

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

EDGE OF EXISTING

AutoCAD SHX Text

PAVED ROAD

AutoCAD SHX Text

UP

AutoCAD SHX Text

EXISTING

AutoCAD SHX Text

GUARD POSTS

AutoCAD SHX Text

UP

AutoCAD SHX Text J

AutoCAD SHX Text

PARKING AREA

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text L

AutoCAD SHX Text S 08° 15' 42.5" W 86.00'

AutoCAD SHX Text N 81° 44' 16.7" W 100.00'

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text N 08° 15' 42.9" E 86.00'

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 41.5'

AutoCAD SHX Text

SLOPE

AutoCAD SHX Text

SLOPE

AutoCAD SHX Text

4" CONCRETE WALKWAY

AutoCAD SHX Text

TOP OF PIER

AutoCAD SHX Text

ELEV.= 42.00'

AutoCAD SHX Text S 81° 44' 18.7" E 100.00'

AutoCAD SHX Text 40.5'

AutoCAD SHX Text 40.5'

AutoCAD SHX Text

LOAD

AutoCAD SHX Text

BANK

AutoCAD SHX Text

PAD

AutoCAD SHX Text

STAIR

AutoCAD SHX Text

LANDING

AutoCAD SHX Text 40.5'

AutoCAD SHX Text 40.5'

AutoCAD SHX Text

PERIMETER

AutoCAD SHX Text

FENCE SEE

AutoCAD SHX Text

EDGE OF PROPOSED

AutoCAD SHX Text

STONE SURFACE

AutoCAD SHX Text

TREATMENT

AutoCAD SHX Text

WIND

AutoCAD SHX Text

SOCK

AutoCAD SHX Text 40'

AutoCAD SHX Text 40'

AutoCAD SHX Text 40'

AutoCAD SHX Text

TDWR CMU EQUIPMENT

AutoCAD SHX Text

BLDG - F.F.E. = 41.00'

AutoCAD SHX Text A/C

AutoCAD SHX Text A/C

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

(GFM)

AutoCAD SHX Text 40'

AutoCAD SHX Text

UP & UT

AutoCAD SHX Text

UP & UT

AutoCAD SHX Text

TRANSFORMER AND

AutoCAD SHX Text

PAD

AutoCAD SHX Text

PAD MOUNTED

AutoCAD SHX Text

POWER METER

AutoCAD SHX Text

SEE NOTE 10

AutoCAD SHX Text

EDGE OF

AutoCAD SHX Text

PAVEMENT

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 1" = 10'-0"

AutoCAD SHX Text

DIESEL FUEL TANK PAD

AutoCAD SHX Text

CMU WALL

AutoCAD SHX Text

GATE

AutoCAD SHX Text

GATE

AutoCAD SHX Text

UNDERGROUND FUEL LINE

AutoCAD SHX Text

C TOWER

AutoCAD SHX Text L

AutoCAD SHX Text

MATCH LINE A-A

AutoCAD SHX Text

C TOWER AND WAVEGUIDE

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text E

AutoCAD SHX Text G

AutoCAD SHX Text I

AutoCAD SHX Text S

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text N

AutoCAD SHX Text 27078

AutoCAD SHX Text

PROFESSIONAL

AutoCAD SHX Text L

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text F

AutoCAD SHX Text N

AutoCAD SHX Text I

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text N

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text F

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text D

AutoCAD SHX Text W

AutoCAD SHX Text I

AutoCAD SHX Text O

AutoCAD SHX Text A.

AutoCAD SHX Text J

AutoCAD SHX Text Y

AutoCAD SHX Text

EXISTING TOWER

AutoCAD SHX Text

EXISTING ACCESS ROAD

AutoCAD SHX Text

EXISTING SUPPORT BUILDING

AutoCAD SHX Text

NORTH

AutoCAD SHX Text

( IN FEET )

AutoCAD SHX Text

GRAPHIC SCALE

AutoCAD SHX Text

AutoCAD SHX Text 1 inch = 20 ft.

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

SURVEY CONTROL NOTES

AutoCAD SHX Text

1. FIELD MEASURE DIMENSIONS AND ELEVATION OF MAINTENANCE PLATFORM PRIOR TO FIELD MEASURE DIMENSIONS AND ELEVATION OF MAINTENANCE PLATFORM PRIOR TO COMMENCING WORK. 2. SURVEY CONTROL FOR CENTERLINE OF TOWER AND ELEVATIONS OF MAINTENANCE SURVEY CONTROL FOR CENTERLINE OF TOWER AND ELEVATIONS OF MAINTENANCE PLATFORM PRIOR TO BEGINNING DEMOLITION.

Lowe, Jeff A (Atlanta)

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCN

ISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-TDWR-C

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV

APPROVED

DATE

REDLINE

DATE

DESCRIPTION

JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

DISCIPLINE: CIVIL

NAME: JEFFREY A. LOWE

GEORGIA REG. #: 27078

CIVIL

JAL

AAB

JAL

03/05/2020

P

M

REMOVE OBJECT

x x

REMOVE CONCRETE

SIDEWALK AND

STOOP

REMOVE ASPHALT

PAVING

REMOVE VEGETATION

LIMITS OF WORK

CIVIL DEMOLITION PLAN

x

MAYLISSE MATOS COURTNEY NOLAN

AutoCAD SHX Text

DIESEL FUEL PAD

AutoCAD SHX Text

TDWR EQUIPMENT BUILDING F.F.E. 41.00'

AutoCAD SHX Text

LOAD BANK PAD

AutoCAD SHX Text

PAD MOUNTED TRANSFORMER

AutoCAD SHX Text

CMU WALL

AutoCAD SHX Text

POWER METER

AutoCAD SHX Text

UNDERGROUND UTILITIES

AutoCAD SHX Text

UNDERGROUND FUEL LINE

AutoCAD SHX Text

BOLLARDS

AutoCAD SHX Text

BOLLARDS

AutoCAD SHX Text

TOP OF PIER ELEV: 42.00

AutoCAD SHX Text

AIR CONDITIONING EQUIPMENT PAD

AutoCAD SHX Text

SLOPE

AutoCAD SHX Text

SLOPE

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

WIND SOCK

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

LIMIT OF EXISTING PAVEMENT

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

4" CONCRETE WALKWAY

AutoCAD SHX Text

C TOWER AND WAVEGUIDE

AutoCAD SHX Text L

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text E

AutoCAD SHX Text G

AutoCAD SHX Text I

AutoCAD SHX Text S

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text N

AutoCAD SHX Text 27078

AutoCAD SHX Text

PROFESSIONAL

AutoCAD SHX Text L

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text F

AutoCAD SHX Text N

AutoCAD SHX Text I

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text N

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text F

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text D

AutoCAD SHX Text W

AutoCAD SHX Text I

AutoCAD SHX Text O

AutoCAD SHX Text A.

AutoCAD SHX Text J

AutoCAD SHX Text Y

AutoCAD SHX Text

DEMO LEGEND

AutoCAD SHX Text

NORTH

AutoCAD SHX Text

( IN FEET )

AutoCAD SHX Text 1 inch = 10 ft.

AutoCAD SHX Text

GRAPHIC SCALE

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text DEMOLITION NOTES: 1. CONTRACTOR RESPONSIBLE FOR TERMINATION AND REMOVING ALL CONTRACTOR RESPONSIBLE FOR TERMINATION AND REMOVING ALL UTILITIES IN DEMOLITION AREA UNLESS OTHERWISE NOTED. CONTRACTOR TO COORDINATE WITH UTILITY COMPANIES ON TERMINATION AND REMOVAL OF SERVICES. 2. ALL DEBRIS SHALL BE HAULED OFF SITE AND SHALL NOT BE BURIED. ALL DEBRIS SHALL BE HAULED OFF SITE AND SHALL NOT BE BURIED. 3. ANY EXISTING IMPROVEMENTS THAT ARE TO REMAIN AND BECOME ANY EXISTING IMPROVEMENTS THAT ARE TO REMAIN AND BECOME DAMAGED SHALL BE RESTORED TO THEIR ORIGINAL CONDITION AS ACCEPTABLE TO PARTIES HAVING JURISDICTION AT NO COST TO OWNER, 4. MINIMUM GRADING TO BE PERFORMED TO PREVENT PONDING. MINIMUM MINIMUM GRADING TO BE PERFORMED TO PREVENT PONDING. MINIMUM SLOPES: 1%, MAXIMUM SLOPES: 50% (2:1). 5. ALL EXISTING STORM SEWER PIPE AND DRAINAGE STRUCTURES TO ALL EXISTING STORM SEWER PIPE AND DRAINAGE STRUCTURES TO REMAIN IN PLACE. 6. THE REMOVAL OF ALL FACILITIES SHALL BE PERFORMED BY THE THE REMOVAL OF ALL FACILITIES SHALL BE PERFORMED BY THE CONTRACTOR UNLESS OTHERWISE INDICATED ON THE DRAWINGS. ALL AREAS WHERE LANDSCAPING HAS BEEN REMOVED SHALL BE RE-STABILIZED AND SODDED IN ACCORDANCE WITH NOTES AND SPECIFICATIONS. 7. ALL LANDSCAPING (TREES, SCRUBS AND GROUND COVER) THAT ARE NOT ALL LANDSCAPING (TREES, SCRUBS AND GROUND COVER) THAT ARE NOT IDENTIFIED TO BE REMOVED SHALL BE PROTECTED IN ACCORDANCE WITH DRAWINGS AND SPECIFICATIONS. PROTECT THE LANDSCAPING IN THE AREA TO THE EXTENT FEASIBLE. NO LANDSCAPING REMOVAL SHALL BE DONE WITHOUT APPROVAL OF THE RE. 8. SAW CUT EXISTING PAVEMENT TO BE REMOVED TO PROVIDE CLEAN EDGE, SAW CUT EXISTING PAVEMENT TO BE REMOVED TO PROVIDE CLEAN EDGE, AND REPAIR AREAS OF BROKEN PAVEMENT ACCORDINGLY. PAVEMENT REMOVED TO BE HAULED TO A LICENSED RECYCLER UNLESS OTHERWISE APPROVED BY THE RE.

AutoCAD SHX Text REMOVE EXISTING TOWER AND EQUIPMENT. SEE STRUCTURAL/ELECTRICAL FOR DEMOLITION AND PHASING DETAILS

AutoCAD SHX Text

REMOVE BOLLARDS (4)

AutoCAD SHX Text

REMOVE EXISTING CONCRETE STOOP

AutoCAD SHX Text

REMOVE EXISTING SIDEWALK. CONCRETE PAD AT EXTERIOR DOOR TO REMAIN

AutoCAD SHX Text

REMOVE BOLLARDS (2)

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

REMOVE 5' OF VEGETATION ON SOUTH AND EAST SIDES OF THE WALLS

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

REMOVE ASPHALT PAVEMENT TO EXISTING HVAC PADS

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

SAW CUT EXISTING ASPHALT IN LINE WITH BUILDING

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text REMOVE APPROXIMATELY 38' OF EXISTING BARRIER WALL TO ALLOW FOR FOUNDATION DEMOLITION. STOP WALL DEMO AT CONCRETE BANDING.

AutoCAD SHX Text

LIMIT OF TOWER BASE FOUNDATION TO BE REMOVED (SEE STRUCTURAL PLAN FOR DETAILS)

AutoCAD SHX Text REMOVE UNDERGROUND FUEL LINE BETWEEN AST AND BUILDING PRIOR TO DEMOLITION OF TOWER FOUNDATION

AutoCAD SHX Text

PATCH AND REPAIR CMU BARRIER WALL AT LOCATIONS WHERE RUST AND SPALLING VISIBLE.

AutoCAD SHX Text

REMOVE LOAD BANK PAD

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text REMOVE EXISTING COMMUNICATION BRIDGE FOOTINGS AND STEEL SUPPORT BRIDGE AND CONDUITS (2)

AutoCAD SHX Text

REMOVE EXISTING EG RADIATOR SUPPORT FOOTINGS (4)

AutoCAD SHX Text

DEMO PVC STORM DRAIN PIPE

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

AutoCAD SHX Text C201

AutoCAD SHX Text

DEMO PVC DRAIN AT BASE OF WALL

AutoCAD SHX Text

SILT FENCE

AutoCAD SHX Text

LAYDOWN AREA

AutoCAD SHX Text

AutoCAD SHX Text S602

AutoCAD SHX Text

AutoCAD SHX Text S602

AutoCAD SHX Text

AutoCAD SHX Text S602

Lowe, Jeff A (Atlanta)

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCN

ISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-TDWR-C

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV

APPROVED

DATE

REDLINE

DATE

DESCRIPTION

JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

DISCIPLINE: CIVIL

NAME: JEFFREY A. LOWE

GEORGIA REG. #: 27078

CIVIL

JAL

AAB

JAL

03/05/2020

P

M

C201

Picture 1: Vegetation at Exterior of Wall

NOT TO SCALE

C201

Picture 2: Existing Pavement

NOT TO SCALE

C201

Picture 3: Existing Concrete Compressor Pad

NOT TO SCALE

C201

Picture 4: Tower Base Area and Barrier Wall

NOT TO SCALE

C201

Picture 6: Existing AST and Bollards

NOT TO SCALE

C201

Picture 7: Existing bollards and equipment pad

NOT TO SCALE

C201

Picture 8: Existing Concrete Sidewalk

NOT TO SCALE

C201

Picture 5: Tower Area Drainage Depression

NOT TO SCALE

CIVIL DEMOLITION PICTURES

SAWCUT

MAYLISSE MATOS COURTNEY NOLAN

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text E

AutoCAD SHX Text G

AutoCAD SHX Text I

AutoCAD SHX Text S

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text E

AutoCAD SHX Text O

AutoCAD SHX Text N

AutoCAD SHX Text 27078

AutoCAD SHX Text

PROFESSIONAL

AutoCAD SHX Text L

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text F

AutoCAD SHX Text N

AutoCAD SHX Text I

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text N

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text F

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text D

AutoCAD SHX Text W

AutoCAD SHX Text I

AutoCAD SHX Text O

AutoCAD SHX Text A.

AutoCAD SHX Text J

AutoCAD SHX Text Y

AutoCAD SHX Text NOTES: 1. VEGETATION TO BE CUT BACK TO MINIMUM VEGETATION TO BE CUT BACK TO MINIMUM 5-FT FROM WALL.

AutoCAD SHX Text NOTES: 1. SAWCUT EXISTING PAVEMENT AT LOCATION SAWCUT EXISTING PAVEMENT AT LOCATION SHOWN ON PLAN PRIOR TO DEMOLITION OF EXISTING ASPHALT.

AutoCAD SHX Text NOTES: 1. COMPRESSOR PAD TO REMAIN. PROTECT COMPRESSOR PAD TO REMAIN. PROTECT DURING ASPHALT DEMOLITION.

AutoCAD SHX Text NOTES: 1. DEMO ASPHALT PER SHEET C200 DEMO ASPHALT PER SHEET C200 2. DEMO SIDEWALK TO TOWER PER SHEET C200 DEMO SIDEWALK TO TOWER PER SHEET C200 3. DEMO BARRIER WALL PER SHEET C200 FOR DEMO BARRIER WALL PER SHEET C200 FOR TOWER FOUNDATION DEMO.

AutoCAD SHX Text NOTES: 1. DEMO ASPHALT PER SHEET C200 DEMO ASPHALT PER SHEET C200 2. DEMO BOLLARDS PER SHEET C200 DEMO BOLLARDS PER SHEET C200 3. DEMO AND REPLACE FUEL LINES FROM AST DEMO AND REPLACE FUEL LINES FROM AST TO EMERGENCY GENERATOR PER SHEET C200 AND SHEET C300

AutoCAD SHX Text NOTES: 1. DEMO ASPHALT PER SHEET C200 DEMO ASPHALT PER SHEET C200 2. DEMO BOLLARDS PER SHEET C200 DEMO BOLLARDS PER SHEET C200 3. DEMO EQUIPMENT PAD PER SHEET C200DEMO EQUIPMENT PAD PER SHEET C200

AutoCAD SHX Text NOTES: 1. DEMO ASPHALT PER SHEET C200 DEMO ASPHALT PER SHEET C200 2. DEMO BOLLARDS PER SHEET C200 DEMO BOLLARDS PER SHEET C200 3. DEMO SIDEWALK PER SHEET C200DEMO SIDEWALK PER SHEET C200

Lowe, Jeff A (Atlanta)

DESIGNED DATE

H

G

F

E

D

C

B

A

7 6 5 4 3 2 1

H

G

F

E

D

C

B

A

8 7 6 5 4 3 2 1

DRAWN

APPROVED BY

JCN

ISSUED BY

SUBMITTED BY

SIGNATURE:

DATE:

DRAWING NO

SCALES SHOWN FOR 22" X 34" SHEET. ADJUST SCALE FOR OTHER SIZES

REVIEWED BY

SJU-TDWR-C

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

TDWR

EASTERN SERVICE AREA ATLANTA, GEORGIA

SAN JUAN PRSAN JUAN INTERNATIONAL AIPORT (SJU)

PROJECT/SYSTEM ENGINEER ENGINEERING MANAGER

REV

APPROVED

DATE

REDLINE

DATE

DESCRIPTION

JCN APVD

1360 Peachtree St, NE Suite 500 Tel. No (678)808-8800

Atlanta, Georgia 30309 Fax. (678)808-8400

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

FOR OFFICIAL USE ONLY

DISCIPLINE: CIVIL

NAME: JEFFREY A. LOWE

GEORGIA REG. #: 27078

CIVIL

JAL

AAB

JAL

03/05/2020

P

M

OVERALL SITE PLAN

MAYLISSE MATOS COURTNEY NOLAN

AutoCAD SHX Text M

AutoCAD SHX Text

TOP= 48.96

AutoCAD SHX Text

INV= 45.01

AutoCAD SHX Text

TOP= 49.23

AutoCAD SHX Text

INV= 45.58

AutoCAD SHX Text

TOP= 49.26

AutoCAD SHX Text

INV= 45.31

AutoCAD SHX Text

CB

AutoCAD SHX Text

CB

AutoCAD SHX Text

CB

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

AutoCAD SHX Text

BUILDING NO. 10

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text M

AutoCAD SHX Text

SUBSTATION

AutoCAD SHX Text M

AutoCAD SHX Text

TOP= 49.19

AutoCAD SHX Text

INV= 44.72

AutoCAD SHX Text

CB

AutoCAD SHX Text M

AutoCAD SHX Text

CB

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

TOP= 49.16

AutoCAD SHX Text

INV= 36.96

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

BUILDING NO. 09

AutoCAD SHX Text

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text M

AutoCAD SHX Text CONC. PIPE 24" Dia.

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

SMH

AutoCAD SHX Text

TOP= 26.53

AutoCAD SHX Text

INV= 21.63

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

10" DIAMETER

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

LW= 49.80

AutoCAD SHX Text T

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

SMH

AutoCAD SHX Text

TOP= 50.54

AutoCAD SHX Text

INV= 44.02

AutoCAD SHX Text

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

SMH

AutoCAD SHX Text

TOP= 47.07

AutoCAD SHX Text

INV= 37.97

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

TOP= 49.28

AutoCAD SHX Text

INV= 45.68

AutoCAD SHX Text

TOP= 49.29

AutoCAD SHX Text

INV= 42.92

AutoCAD SHX Text

TOP= 49.26

AutoCAD SHX Text

INV= 44.46

AutoCAD SHX Text

CB

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

CB

AutoCAD SHX Text

CB

AutoCAD SHX Text

SMH

AutoCAD SHX Text

TOP= 30.56

AutoCAD SHX Text

INV= 26.68

AutoCAD SHX Text

12' ROAD WIDTH

AutoCAD SHX Text

EDGE OF EXISTING

AutoCAD SHX Text

PAVED ROAD

AutoCAD SHX Text

UP

AutoCAD SHX Text

EXISTING

AutoCAD SHX Text

GUARD POSTS

AutoCAD SHX Text

UP

AutoCAD SHX Text J

AutoCAD SHX Text

PARKING AREA

AutoCAD SHX Text

EDGE OF CLIFF

AutoCAD SHX Text L

AutoCAD SHX Text S 08° 15' 42.5" W 86.00'

AutoCAD SHX Text N 81° 44' 16.7" W 100.00'

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text X

AutoCAD SHX Text N 08° 15' 42.9" E 86.00'

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 41.5'

AutoCAD SHX Text

SLOPE

AutoCAD SHX Text

SLOPE

AutoCAD SHX Text

4" CONCRETE WALKWAY

AutoCAD SHX Text

TOP OF PIER

AutoCAD SHX Text

ELEV.= 42.00'

AutoCAD SHX Text S 81° 44' 18.7" E 100.00'

AutoCAD SHX Text 40.5'

AutoCAD SHX Text 40.5'

AutoCAD SHX Text

LOAD

AutoCAD SHX Text

BANK

AutoCAD SHX Text

PAD

AutoCAD SHX Text

STAIR

AutoCAD SHX Text

LANDING

AutoCAD SHX Text 40.5'

AutoCAD SHX Text 40.5'

AutoCAD SHX Text

PERIMETER

AutoCAD SHX Text

FENCE SEE

AutoCAD SHX Text

EDGE OF PROPOSED

AutoCAD SHX Text

STONE SURFACE

AutoCAD SHX Text

TREATMENT

AutoCAD SHX Text

WIND

AutoCAD SHX Text

SOCK

AutoCAD SHX Text 40'

AutoCAD SHX Text 40'

AutoCAD SHX Text 40'

AutoCAD SHX Text

TDWR CMU EQUIPMENT

AutoCAD SHX Text

BLDG - F.F.E. = 41.00'

AutoCAD SHX Text A/C

AutoCAD SHX Text A/C

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

(GFM)

AutoCAD SHX Text 40'

AutoCAD SHX Text

UP & UT

AutoCAD SHX Text

UP & UT

AutoCAD SHX Text

TRANSFORMER AND

AutoCAD SHX Text

PAD

AutoCAD SHX Text

PAD MOUNTED

AutoCAD SHX Text

POWER METER

AutoCAD SHX Text

SEE NOTE 10

AutoCAD SHX Text

EDGE OF

AutoCAD SHX Text

PAVEMENT

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 1" = 10'-0"

AutoCAD SHX Text

DIESEL FUEL TANK PAD

AutoCAD SHX Text

CMU WALL

AutoCAD SHX Text

GATE

AutoCAD SHX Text

GATE

AutoCAD SHX Text

UNDERGROUND FUEL LINE

AutoCAD SHX Text 40.5

AutoCAD SHX Text 40.5

AutoCAD SHX Text 40.5

AutoCAD SHX Text 40.5

AutoCAD SHX Text

C TOWER

AutoCAD SHX Text L

AutoCAD SHX Text

MATCH LINE A-A

AutoCAD SHX Text

C TOWER AND WAVEGUIDE

AutoCAD SHX Text Co

AutoCAD SHX Text Ds3

AutoCAD SHX Text

DU

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text E

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 3F

AutoCAD SHX Text 3F

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

POWER POLE # 6

AutoCAD SHX Text

ACCESS ROAD TO EAST ISLAND

AutoCAD SHX Text

ASPHALT PAVED ROAD

AutoCAD SHX Text

ASPHALT PAVED ROAD

AutoCAD SHX Text 3F

AutoCAD SHX Text

POWER POLE # 5

AutoCAD SHX Text

CONCRETE BOX

AutoCAD SHX Text

POWER POLE # 4

AutoCAD SHX Text

POWER POLE # 3

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text P & T

AutoCAD SHX Text P & T

AutoCAD SHX Text P & T

AutoCAD SHX Text P & T

AutoCAD SHX Text P & T

AutoCAD SHX Text

LIMITS OF SURVEY AREA

AutoCAD SHX Text

LIMITS OF SURVEY AREA

AutoCAD SHX Text

LIMITS OF SURVEY AREA

AutoCAD SHX Text

LIMITS OF SURVEY AREA

AutoCAD SHX Text

LIMITS OF SURVEY AREA

AutoCAD SHX Text

UT

AutoCAD SHX Text

UT

AutoCAD SHX Text

UP

AutoCAD SHX Text

NEW GUY

AutoCAD SHX Text

RIP RAP FOR EROSION CONTROL

AutoCAD SHX Text

POWER POLE # 2 CONCRETE POLE END OF OVERHEAD POWER LINE

AutoCAD SHX Text

POWER POLE # 7 CONCRETE POLE BEGINNING POINT OF OVERHEAD SERVICE