This document package includes a draft request for proposals (RFP) for professional technical support services for the Joint Directed Energy Transition Office (DE-JTO). The RFP seeks proposals for an indefinite delivery indefinite quantity contract to provide labor, operations, travel, studies and analysis in support of approximately $50 million and 100 projects in the DE-JTO portfolio. Key personnel requirements include a program manager and support at estimated levels of 3-4.5 full-time equivalents along with $2-3 million in subcontracted work. The incumbent contractor provides current support under contract number FA945117C0083, set to expire in 2022. Comments on the draft RFP are due by May 9, 2018 and award of the follow-on contract is anticipated within the next two months. Pricing will be fixed-price for labor and operations with cost reimbursement for allowable travel costs. The solicitation is designated as full and open competition.
Responses to questions received.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Draft_RFP_FA9451-18-R-0002.pdf | ||
| Draft_RFP_Section_J_Atch_1_JTO_PTSS_PWS.pdf | ||
| Draft_RFP_Section_J_Atch_5_JTO_PTSS_Section_L_ITO.pdf | ||
| Draft_RFP_Questions_and_Answers_Template.xlsx | XLSX spreadsheet | |
| Draft_RFP_Section_J_Atch_2_Draft_Task_Order_0001.pdf | ||
| Draft_RFP_Section_J_Atch_8_Cross_Reference_Matrix.pdf | ||
| Draft_RFP_Section_J_Atch_6_JTO_PTSS_Section_M_Evaluation_Criteria.pdf | ||
| Draft_RFP_Section_J_Atch_3_-__Task_Order_0001_PWS.pdf | ||
| Draft_RFP_Section_J_Atch_4_Solicitation_DD_254.pdf | ||
| Draft_RFP_Letter_DE-JTO_PTSS.pdf | ||
| Draft_RFP_Section_J_Atch_7_DE-JTO_PTSS_RFP_TEP_Calculation.xlsx | XLSX spreadsheet | |
| Draft_RFP_Section_J_Atch_5_L-1_Subcontractor_Consent_Letter.pdf | ||
| Draft_RFP_Section_J_Atch_5_L-2_PPQ.pdf | ||
| Draft_RFP_Section_J_Exhibit_A_Draft_CDRLs.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Line Item | Draft RFP Reference (i.e. contract, PWS, Section L, Section M) | Question | Answer |
| 1 | Section B, pg2, 001 | Item OO1 is the Labor and Operations at Firm Fixed Price. Will the final RFP include the level of effort expected over the first year and the option years? | This acquisition is anticipated to be solicited as an Indefinite Delivery Indefinite Quantity (IDIQ) Contract. Currently, the draft RFP is written to request offerors provide prices for Task Order 0001 which includes a base and four option years of FFP Labor and Operations. Per the PWS, the DE-JTO program will require support of the approximately $50M DE-JTO portfolio consisting of approximately 100 active projects in the form of Multi Research Initiatives (MRIs), Service and Agency (S&A) agreements, Broad Agency Announcement (BAA) awards and other special projects. |
| 2 | Section B, pg2, 002 | Item OO2 refers to the Travel task. Should the bidder estimate travel (trips, locations, days) or will the final RFP provide a travel value to include in the costing? | The Government anticipates providing a travel estimate that will not be included as part of the total evaluated price (TEP.) |
| 3 | Section B, pg2, 003 | Item OO3 refers to the Studies and Analysis task. Will the final RFP include the level of effort expected over the first year and the option years? | This acquisition is anticipated to be solicited as an Indefinite Delivery Indefinite Quantity (IDIQ) Contract. If the Government determines to incorporate studies into the solicitation analysis, they will be presented as separate task orders in the final RFP. |
| 4 | Draft RFP, Section 2.3.3 | Should the responder simply provide the mechanisms for consulting agreements with senior experts in DEW and not price this task or will the final RFP include the level of effort expected of the first year and the option years? | Consulting agreements with senior experts is part of the scope of Task Order 0001 Labor and Operations and should be priced accordingly. If additional task orders for studies and analysis are included in the final RFP and require additional consulting agreements, the offeror shall price according to those task orders. Historically, it is estimated consultants have supported between 1000-1500 hours per year including technical studies. This information is merely an estimate and is not considered mandatory. This data may not reflect manpower needed to perform this effort. The offeror shall propose the manpower and skill mix as they determine appropriate to support this effort. |
| 5 | Draft RFP, Section 2.6.4 | This section refers to the key personnel. It would appear that each of these are expected to support the effort at a full time level. Is this correct? Or will the final RFP include the level of effort expected for these folks over the first year and the option years? | The Government does not specify key personnel are required full time. The awarded contractor shall have the ability to provide the key personnel with these requirements to support the DE-JTO program office. Historically, the positions have not been provided on a full time basis. Further, the PWS will be updated to state key personnel shall be proposed as separate individuals with the exception of the Program Manager which may share the position with one other Key Personnel listed. |
| 6 | General Guidance | Given that this is an A&AS contract, it would seem that the final RFP would include the hours, travel and expenditures expected to support the effort such that the evaluations described in Section M will be determined via the approach, experience, personnel provided and cost. Is this correct? | The Government anticipates providing a travel estimate that will not be included as part of the total evaluated price (TEP.) For all other values requested as part of the pricing matrix, the offeror will propose the hours, labor, expenditures and any other associated costs. |
| 7 | General Guidance | Will the Government provide hours or FTEs per year against the labor categories provided for bidding purposes? | |
| No. The offeror shall determine and propose the labor and skills mix to support the PWS. Historically, the effort has required an estimated 3-4.5 full time equivalents with additional effort provided by $2-3M in subcontracted work covering both labor and operations as well as technical studies and analysis. This information is merely an estimate and is not considered mandatory. This data may not reflect manpower needed to perform this effort. The offeror shall propose the manpower and skill mix as they determine appropriate to support this effort. | |||
| 8 | General | How are these services currently being performed? Under contract? In-house? | DE-JTO currently has support from an A&AS contractor. |
| 9 | General | If these requirements are currently being performed under a contract, |
a. Who is the Contractor?
b. What is the contract number?
c. When does the contract expire?
d. What is the current contract value?
Please reference the redacted justification and approval (J&A) posted to FBO at the link below.
https://www.fbo.gov/spg/USAF/AFMC/AFRLPLDED/FA945117C0083/listing.html
| 10 | General | What is the anticipated RFP release date? | The Government is finalizing the acquisition strategy and plans to solicit within the next two months. |
| 11 | File “Draft_RFP_FA9451-18-R-0002” CLIN 0002 Travel Cost Reimbursable states “This is a Cost Reimbursable CLIN - No fee will be paid on travel” and file “Draft_RFP_Section_J_ Atch_1_JTO_PTSS_PWS”, page 19 states “Government will reimburse travel at actual direct costs to the Contractor without the application of additional costs associated with direct expenses, indirect expenses, or profit.” | Do "actual direct [travel] costs to the contractor" include G&A and Cost of Money? | The contract will be updated to state "This is a Cost Reimbursable CLIN - No fee will be paid on travel. Government will reimburse travel at actual direct costs to the Contractor without the application of additional costs associated with direct expenses and indirect expenses unless otherwise permitted in the contractor's disclosure statement or corporate practices. |
| 12 | File “Draft_RFP_Section_J_Atch_1_JTO_PTSS_PWS" para 2.3 and 2.4 | Is the classified work described in the PWS (e.g. paragraph 2.3 and 2.4) performed by the contractor at the DE-JTO office or is it required to be performed by the contractor at the contractor’s facility? | The DD254 requires a Top Secret Facility Clearance and a Secret Level of Safeguarding for Classified Information/Material required at the Contractor Facility. |
| 13 | Section J Attachment 2 Draft Task Order 0001 - Box 11 | The Draft RFP letter DE JTO PTSS states "This effort is anticipated to be competed as an unrestricted full and open competitive trade off source selection." However Box 11 on the DD Form 1155 has the order marked as Small Disadvantaged Woman Owned, can you please clarify the discrepancy and confirm that this is Full and Open competition type? | Box 11 of the DD Form 1155 is an error. This effort is anticipated to be competed as a unrestricted full and open competition. |