This notice is being posted in an effort to keep industry informed on the progress of the RASTER source selection. Due to unforeseen delays the Government anticipates that contract award will now be extended in the 1st Quarter of calendar year 2016. The updated milestone schedule posted with this notice reflects the Government's anticipated schedule to date.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anticipated Acquisition Milestones
• Contract Award 1st Quarter, Calendar Year 2016
• Phase-In Period begins Date of Contract Award
• Full performance begins Date of Contract Award + 3 months
Updated RASTER Milestone Schedule
Slide Number 1