Updated_RASTER_Milestone_Schedule_20150528.pdf
PDF 59 KB Posted
- Solicitation number
- FA9451-13-R-0243
About this file
This notice is being posted in an effort to keep industry informed on the progress of the RASTER source selection. Due to unforeseen delays the Government anticipates that contract award will now be extended into the 4th Quarter of calendar year 2015. The updated milestone schedule posted with this notice reflects the Government's anticipated schedule to date.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anticipated Acquisition Milestones
• Contract Award 4th Quarter, Calendar Year 2015
• Phase-In Period begins Date of Contract Award
• Full performance begins Date of Contract Award + 3 months
Updated RASTER Milestone Schedule
Slide Number 1
File details come from the government source that posted it. Updated .