Attachment Q - Permit Requirements Memo.pdf
PDF 94 KB Posted
- Attached to
- Replace Two 12, 470V to 480V Transformers
- Solicitation number
- FA940124B0003
About this file
This document is a Permit Requirements Memorandum related to a federal contract opportunity to replace two 12,470V to 480V transformers at Kirtland Air Force Base in New Mexico. The key details include:
The project requires a Welding/Burn Permit and a Landfill Permit. The contractor must also comply with the KAFB Checklist of Environmental Requirements, which details relevant regulations. Additional permits may be required depending on any changes to the project or new laws/policies enacted by local agencies. The government is advised to verify current permit requirements are being met prior to the start of construction.
The federal contract opportunity is Solicitation Number FA940124B0003 to replace the two transformers and associated equipment and wiring in Building 27497. The transformers are outdated and step power up from generator feeders and down to power several surrounding buildings.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERMIT REQUIREMENTS MEMORANDUM
DATE: 01 April 2024
SUBJECT: TN 24-012, Project No.: 230056 Replace Two 12,470v to 480v Transformers, B27497, Kirtland AFB, NM
FROM: NetCentric Technology, LLC, Project Manager, Luis Pinedo
The following permits are required on the subject project:
1. Welding/Burn Permit
2. Landfill Permit
Other permits may be required on this project. Particular attention must be paid by the Contractor to the requirements specified in the KAFB Checklist of Environmental Requirements for this project, which detail regulations with which those executing the work of the contract must comply.
If changes are made to the project, or new laws/policies enacted by the local agencies, there may be additional permits required for construction. Prior to work starting, it is recommended the government verify current permit requirements are being met at the time of construction.
Sincerely, Luis Pinedo Project Manager NetCentric Technology, LLC