Attachment G - Construction AF 66.xlsx
XLSX spreadsheet 23 KB Posted
- Attached to
- Replace Two 12, 470V to 480V Transformers
- Solicitation number
- FA940124B0003
About this file
This document is an Attachment G - Construction AF 66 Excel spreadsheet that outlines the schedule of material submittals required for a federal contract to replace two 12,470V to 480V transformers in Building 27497 on Kirtland Air Force Base.
The key details include: The project number is MHMV230056 with a solicitation/contract number of B27497. The contractor must provide submittals such as utility outage requests, schedule of prices, personnel/vehicle/equipment forms, waste management plan, safety plan, construction schedule, quality control plan, shop drawings, transformer and switchgear details, panelboard details, inspection reports, and project closeout documents like warranties, as-builts, O&M manuals, and training. Most submittals are due 35 days prior to need, with some due 14 days after notice to proceed or 21 days prior to final acceptance. The contract is being issued by the Department of the Air Force Materiel Command Nuclear Weapons Center.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER: | PROJECT TITLE: | SOLICITATION/CONTRACT NO. | ||||||||||||||||||||||
| CONTRACTOR TO SEE SPECIFICATIONS FOR ADDITONAL REQUIREMENTS | MHMV230056 | REPLACE TWO 12,470V TO 480V TRANSFORMERS B27497 | |||||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | ||||||||||||||||||||||||
| NUMBER OF COPIES REQUIRED (# CP) | |||||||||||||||||||||||||
| LINE NO | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL (Note: Specification sections contain detailed requirements for submittals. Contractor Responsible for all submittal requirements listed on this form, as well as all requirements described in specification sections.) | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS - MFR. SPECS | SAMPLES | COLOR SELECTION, CHARTS | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | MIX DESIGN | CATALOG/ PRODUCT DATA | OPERATING INSTRUCTIONS | TEST DATA - REFERENCES | PLAN, SCHEDULE, LIST | AS-BUILT DRAWINGS | OTHER | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NO | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | ||
| D=DAYS | APPROVED | DISAPROVED | |||||||||||||||||||||||
| PROJECT START UP | |||||||||||||||||||||||||
| 1 | UTILITY OUTAGE | ||||||||||||||||||||||||
| REQUESTS AND PERMITS (Utility Shut-Off-Dig Permit Form 103 Fillable) | X | NTP+ 14 D prior to need | |||||||||||||||||||||||
| 2 | SCHEDULE OF PRICES, COST LOADED AF 3064 | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 3 | EAL Personnel, Vehicle and Equip Form Request | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 4 | Long Term Pass Request | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 5 | WASTE MGMT PLAN | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 6 | SITE SPECIFIC SAFETY | ||||||||||||||||||||||||
| PLAN, HAZMAT PLAN | X | NTP+ 14 D prior to need | |||||||||||||||||||||||
| 7 | Initial CPM CONSTRUCTION SCHEDULE | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 8 | QC PLAN | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 9 | CUI Docs Receipt -Updated | X | NTP+ 14 D prior to need | ||||||||||||||||||||||
| 10 | SDS AND | ||||||||||||||||||||||||
| WORKSHEET | X | NTP+ 14 D prior to need | |||||||||||||||||||||||
| TECHNICAL | |||||||||||||||||||||||||
| 11 | Shop drawings by the transformer manufacturer | X | X | X | X | 35 Days Prior to Need | |||||||||||||||||||
| 12 | Transformers and switchgear | X | X | X | 35 Days Prior to Need | ||||||||||||||||||||
| 13 | Panelboard | X | X | X | 35 Days Prior to Need | ||||||||||||||||||||
| 14 | Iterative Overall schedule | X | 35 Days Prior to Need | ||||||||||||||||||||||
| 15 | Iterative CPM CPM CONSTRUCTION SCHEDULE | X | 35 Days Prior to Need | ||||||||||||||||||||||
| 16 | Meeting agenda and meeting minutes | X | 35 Days Prior to Need | ||||||||||||||||||||||
| 17 | Final inspection reports | X | 35 Days Prior to Need | ||||||||||||||||||||||
| 18 | Iterative escort request | X | 35 Days Prior to Need | ||||||||||||||||||||||
| PROJECT CLOSE OUT | |||||||||||||||||||||||||
| 16 | WARRANTY LETTER | x | 21 D PRIOR TO FINAL ACCEPTANCE | ||||||||||||||||||||||
| 17 | AS BUILTS signed and sealed by the transformer manufacturer’s Professional Electrical Engineer | x | 21 D PRIOR TO FINAL ACCEPTANCE | ||||||||||||||||||||||
| 18 | O & M MANUALS/OPERATING | ||||||||||||||||||||||||
| INSTRUCTIONS | x | 21 D PRIOR TO FINAL ACCEPTANCE | |||||||||||||||||||||||
| 19 | OWNER TRAINING (Job training and maintains requirements for site personnel) | x | 21 D PRIOR TO FINAL ACCEPTANCE | ||||||||||||||||||||||
| 20 | INTERIM DD 1354, TRANSFER & ACCEPTANCE OF MILITARY REAL PROPERTY | x | 21 D PRIOR TO FINAL ACCEPTANCE | ||||||||||||||||||||||
| 21 | DD 1354, TRANSFER & ACCEPTANCE OF MILITARY REAL PROPERTY | x | 21 D PRIOR TO FINAL ACCEPTANCE |
&6CP:COPY, ST:SET, PN:SAMPLES PANEL, MD:MODULE, SM:SQUARE METER, EA:EACH, KG:KILOGRAM, CON:CONTAINER, LM:LINEAR METER, MAT APP: MATERIAL APPROVAL
&6COMPUTER GENERATED AF 66, OCT 89&