Exhibit F with 3 attachments.doc

DOC document 182 KB Posted

Attached to
Painting Services Federal contract opportunity
Solicitation number
FA930110R0008a
Issued by
Department of the Air Force Materiel Command Test Center

About this file

Exhibit F Request for Proposal Task Order 0001 and attached SOW ELIN Pricing Schedule and Form 66

View the file

Other files for this federal contract opportunity

Other files attached to Painting Services, newest first.
File Type Posted
Amendment 0004.pdf PDF
QR Paint Recompete 37-57.doc DOC document
Amendment 03.pdf PDF
Amendment 02 to Solicitation FA930110R0008a.pdf PDF
Attendee Lists Paint Pre-Proposal Conference.pdf PDF
Pre-Proposal Conference 10 June 2010.ppt PPT presentation
Amendment 0001 to Solicitation FA930110R0008a.pdf PDF
Paint FY10 Changed Location Notice.doc DOC document
Attachment 1 CA100031.doc DOC document
Attachment 2 CA100013.doc DOC document
Paint FY10 Site Visit Notice.doc DOC document
FA9301-10-R-0008 Solicitation.doc DOC document
CA13_dvb.txt TXT text file
CA31_dvb.txt TXT text file
Exhibit E Year 5.xls XLS spreadsheet
Specification Paint FY10.docx DOCX document
Exhibit D Year 4.xls XLS spreadsheet
Exhibit B Year 2.xls XLS spreadsheet
EAFB Design Standards.doc DOC document
Exhibit A Year 1.xls XLS spreadsheet
Exhibit C Year 3.xls XLS spreadsheet
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT F

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 95TH AIR BASE WING (AFMC)

EDWARDS AIR FORCE BASE, CALIFORNIA

28 May 2010

MEMORANDUM FOR

ALL OFFERORS

FROM:

95 CONS/PKB

5 South Wolfe Avenue

Edwards AFB, CA 93524-1185

SUBJECT:

Opportunity to Submit A Voluntary Proposal, Contract No. TBD/Task Order 0001: Project Title: Maintain Paint Exterior, Building 4221; Project/Work Order Number 254651

1.

Attached is a Statement of Work (SOW) dated 12 November 2009 for the subject task order.

2.

Funds have been certified for this project, and Task Order 0001 will be awarded at the time of contract award.

3.

Your proposal must be provided in original and two (2) copies, unless provided on disk, with your Request for Proposal on the date and time specified in the Request for Proprosal Block 13.

4.

The estimated price range for this project less than $25,000.

5.

You are hereby directed to use prices in Exhibit A, ELIN Pricing Schedule, Year 1.

6.

Your proposal must include a statement that indicates the cost proposal is provided voluntarily and at no cost to the government.

CHERLYE E. ARMSTRONG

Contracting Officer

95th Contracting Squadron 3 Attachments

1. Exhibit F, Attachment 1, SOW dated 11 November 2009

2. Exhibit F, Attachment 2, ELIN Pricing Schedule, Task Order 0001

3. Exhibit F, Attachment 3, Form 66, Schedule of Material Submittal

EXHIBIT F

Attachment 1

STRUCTURES SYSTEM

95 ABW / CETB

AIR FORCE FLIGHT TEST CENTER

EDWARDS AIR FORCE BASE, CALIFORNIA 93523-8540

STATEMENT OF WORK

MAINTAIN PAINT EXTERIOR

BUILDINGS 4221

W.O# 254651

12 NOVEMBER 2009

STATEMENT OF WORK

The work consists of, but is not limited to, furnishing all labor, materials, equipment, and supervision required to paint Bldg 4221 exterior. All work shall include surface preparation, repairs of exterior surfaces, lead abatement (on Redwood Trim), primer coat, and 2 finish coats (Marble Cream). Work includes all exterior handrails, ladders, doors and stairs (Redwood). Unpainted concrete surfaces will not be painted. This facility is located at North Base, Edwards Air Force Base, California.

Exhibit F

Attachment 2

ELIN Pricing Schedule

Task Order 0001

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACT

Project Location

FA9301-10-R-0008

Bldg 4221

CONTRACTOR

PROJECT NUMBER

W.O.# 254651

LINE
ITEM
UNIT
ELIN
LINE

NO.

OF
QUANTITY
UNIT PRICE
TOTAL

MEASURE

A001
Apply Prime Coat (1 coat) includes surface prep
SF
3,100.00
A002
Apply Finish Coat to Walls, Soffits, Duct Work & Mech Equipment Exterior(2 coats)
SF
3,100.00
A003
Apply Finish Coat to Doors and Door Frames (2 coats)
SF
120.00
A005
Apply Finish Coat to Fascia including gutters and downspouts (2 coats)
SF
367.00
A006
Apply Finish Coats to Railings (2 coats)
LF
360.00
A007
Apply Finish Coat to Ladders, grills and Steel Stairs (2 coats)
SF
360.00
A016
Lead Based Paint Abatement
SF
1,000.00

TOTAL

_1336550617.xls Sheet1

Exhibit F, Attachment 3 PROJECT NUMBER : PROJECT TITLE: SOLICITATION CONTRACT NUMBER

SCHEDULE OF MATERIAL SUBMITTALS W.O.# 254651 MAINTAIN PAINT EXTERIOR B4221 FA9301-10-R-0008

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NUMBER OF COPIES REQUIRED

LINE NUMBER ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL CERTIFICATION OF COMPLIANCE SHOP DRAWINGS SAMPLES COLOR SELECTION MANUFACTURER'S RECOMMENDATIONS MANUFACTURER'S WARRANTY CATALOG DATA OPERATING INSTRUCTIONS REPORT REQUIRED SUBMISSION DATE DATE RECEIVED IN CONTRACTING DATE TO CIVIL ENGINEERING RETURN SUSPENSE DATE SUBMITTAL NUMBERS DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL FINAL APPROVAL REMARKS

APPROVED DISAPPROVED

1 MATERIAL SAFETY DATA SHEETS X

2 ABATEMENT PLAN LEAD/ASBESTOS X

3 AIR SAMPLING RESULTS (AIR, PERSONAL, AREA, CLEARANCE) X

&CExhibit F Attachment 3 Form 66, Schedule of Material Submittals Task Order 0001

Sheet2

Sheet3