TO 2 PWS Attch 2 Castle Base Spec Req NorCal BECOS vf2.docx

DOCX document 51 KB Posted

Attached to
BRAC Environmental Construction Optimization Services (BECOS) - NorCal Region Federal contract opportunity
Solicitation number
FA8903-20-R-0014
Issued by
Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency

About this file

This document outlines requirements for environmental remediation and monitoring services at the former Castle Air Force Base in California. The scope of work includes long-term operation and maintenance of groundwater treatment systems for two CERCLA sites, inspection and monitoring of landfills and sites with institutional controls, implementation of recommendations from a Five-Year Review report, and preparation of the next two Five-Year Reviews due in 2024 and 2029. The related federal contract opportunity is a solicitation issued by the Air Force Materiel Command Installation Contracting Agency under solicitation number FA8903-20-R-0014 for BRAC Environmental Construction Optimization Services in the NorCal region. Responses were due by the date listed on the solicitation documents.

View the file

Other files for this federal contract opportunity

Other files attached to BRAC Environmental Construction Optimization Services (BECOS) - NorCal Region, newest first.
File Type Posted
202000401_FA8903-20-R-0014 NorCal RFP Questions and Answers UPDATED.xlsx XLSX spreadsheet
20200313_FA890320R0014_NorCal_BECOS_Section_M v3 Amendment 1.docx DOCX document
Solicitation Amendment FA890320R00140001 SF 30.pdf PDF
20200323_FA890320R0014_BECOS_NorCal_Section_L-Amendment 1.docx DOCX document
FA890320R0014 NorCal Amendment Changes.docx DOCX document
20200109_NorCal TO2 Price Model-Amendment 1.xlsx XLSX spreadsheet
20200317_20-R-0014 NorCal RFP Questions and Answers Set 2 of 2.xlsx XLSX spreadsheet
FA890320R0014_BECOS NorCal RFP Questions and Answers Set 1 of 2_03102020.xlsx XLSX spreadsheet
IDIQ PWS Attch 3 NorCal Del Rev Process BECOS vf1.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B005-B006-B007 (ADMN).pdf PDF
CA20190018 24Jan2020 Merced Santa Clara Building, Heavy.pdf PDF
CA20190007 24Jan2020 Sacramento Building, Heavy.pdf PDF
TO 1 PWS NorCal BECOS vf3.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT A005-A006-A011 (CMAN).pdf PDF
TO 2 PWS NorCal BECOS vf3.docx DOCX document
20200122_NorCal FFP FBLR Tables v2.xlsx XLSX spreadsheet
TO 2 CDRLs Exhibit A B NorCal BECOS vf2.docx DOCX document
20200203_FA890320R0014_BECOS_NorCal_Section_L v4.docx DOCX document
20191217_Compensation Plan Model.xlsx XLSX spreadsheet
20200203_NorCal IDIQ_Sched B_CLIN Structure v2.xlsx XLSX spreadsheet
BECOS IDIQ DD1423 CDRLS EXHIBIT A003-A012 (MGMT).pdf PDF
WA20190076 1Nov2019 Spokane Heavy.pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT A013 (MISC CONT).pdf PDF
20200131_FA890320R0014_BECOS_Relevancy_PPQ.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B002-B003 (MGMT).pdf PDF
20200131_FA890320R0014_BECOS_Relevancy_Matrix v2.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT A007-A008-A009 (ENVR).pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT A001-A002-A004 (MISC).pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT A014 (DRPR).pdf PDF
IDIQ PWS NorCal BECOS vf5.docx DOCX document
20200131_FA8903-20-R-0014_BECOS RFP Questions and Answers Template.xlsx XLSX spreadsheet
Solicitation - FA890320R0014 v2.pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT C001 (MGMT).pdf PDF
IDIQ PWS Attch 2 NorCal Acr and Def BECOS vf2.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B001 (MISC).pdf PDF
WA20190017 15Nov2019 Spokane Building.pdf PDF
IDIQ PWS Attch 4 NorCal Perf Obj Def BECOS vf1.docx DOCX document
TO 2 PWS Attch 2 Mather Base Spec Req NorCal BECOS vf3.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B004 (CMAN).pdf PDF
TO 1 CDRLs Exhibit A B NorCal BECOS vf2.docx DOCX document
20200109_NorCal TO2 Price Model jb - Copy.xlsx XLSX spreadsheet
20200203_FA890320R0014_NorCal_BECOS_Section_M v3.docx DOCX document
IDIQ PWS Attch 1 NorCal Site List BECOS vf2.xlsx XLSX spreadsheet
TO 2 PWS Attch 1 NorCal Site List BECOS vf5.xlsx XLSX spreadsheet
BECOS IDIQ DD1423 CDRLS EXHIBIT A010 (QCIC).pdf PDF
TO 2 PWS Attch 2 McClellan Base Spec Req NorCal BECOS vf4.docx DOCX document
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

FA8903-20-R-0014 TO 2

ATTACHMENT 2

NORCAL REGION - CASTLE

5 December 2019

1.1 Scope

The former Castle AFB is listed on the National Priorities List (NPL) and has a Federal Facility Agreement (FFA) in place. A Preliminary Closeout Report was prepared by the United States Environmental Protection Agency (USEPA) in 2006. Records of Decision (RODs) have been signed for all Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites included in this task order and Last Remedy in Place (LRIP) has been achieved for the base.

The sites included in this task order are being addressed following the CERCLA process or state corrective action program (non-CERCLA). There are two CERCLA sites in remedial action-operation (RA-O) and all CERCLA sites require IC monitoring and Five Year Review. Groundwater pump and treat systems are currently operating at two of the sites (OT029 and OT030). The Operable Unit (OU)-1 Basewide Phase 3 groundwater treatment plant is currently operating at OT029 and the OU-2 groundwater treatment plant (Main Base Plant) is currently operating at OT030. Groundwater contamination associated with former Air Force activities has migrated beyond the former base property boundaries. Seven of the CERCLA sites are associated with three capped landfills/sites with ongoing Long-term Management. One CERCLA site has ICs and requires Five-Year Review only. Four petroleum-contaminated sites have ICs and require non-CERCLA Five Year Review only.

In addition to the requirements presented in this PWS, this scope includes the following:

· Monitoring for 1,2,3-TCP in drinking water wells and irrigation wells as part of the on-going long-term groundwater sampling program and monitoring of the Main Base Plume; as part of the monthly sampling of influent, primary effluent, and final effluent from the OU-1 and OU-2 groundwater treatment plants; in groundwater wells at Landfills 4 and 5; and at private drinking water wells as required to ensure protection of public.

· Replacement of wells that are dry due to lowering groundwater table, as needed.

· Monitoring for PFAS at the OU-1 and OU-2 groundwater treatment plants and O&M of GAC including changeouts as needed.

· Implementation of recommendations noted in the March 2019 Five-Year Review Report.

Contractors are not responsible for the following:

· Investigation and remediation of PFAS, except as noted above and in Attachment 1.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1
FFA
AR 1007
July 1, 1989
2
Comprehensive Basewide (CB) ROD - Part 1 (Groundwater)
AR 1586
January 31, 1997
3
CB ROD - Part 2
AR 2747
July 31, 2006
4
Source Control Operable Unit (SCOU) ROD - Part 1
AR 2246
September 1, 2002
5
SCOU ROD - Part 2
AR 2244
May 1, 2003
6
Revised SCOU ROD - Part 3
AR 2736
September 16, 2005
7
Fifth Five Year Review
AR 585780
March 2019

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

FA8903-16-F-0018
Castle/Mather/Norton PBR Contract
9/22/2021
9/22/2021

2.6.1 Meeting/Teleconference Support

· BRAC Cleanup Team (BCT) meetings are currently conducted annually at the former McClellan AFB (or comparable mutually agreed location for future meetings). Periodic technical meetings are conducted as needed in person or by teleconference.

2.6.2 Public Meetings and Hearings

· The Restoration Advisory Board has been adjourned and no other public meetings are currently scheduled.

2.6.5 Site Access: Permits, Easements, and Work Site Access

· All existing off-base easements extend beyond this task order POP.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No base-specific requirements in addition to those in the PWS.

6.14 Land Use Controls (LUC)

· The contractor shall conduct annual inspections and reviews to confirm compliance with all CERCLA and non-CERCLA environmental restrictions associated with the sites. Where possible, the contractor shall obtain and provide copies to the Air Force of annual reporting required by state covenants for applicable sites by respective property owners. An annual inspection report shall be provided or otherwise included in site reports by the contractor to confirm implementation of environmental restrictions.

· The contractor shall provide supporting information and technical support to the Air Force for property owner requests to remove restrictive covenants.

6.15 Five-Year Reviews

· The current PBR contractor completed the 5th Five-Year Review Report in March 2019. This TO includes preparation of the next two Five-Year Reviews due in March 2024 and March 2029.