This document outlines a deliverable review process for a federal contract. It details the sequential review tasks to be completed by both the contractor and regulators. The contractor will first prepare a working copy document and submit it for a 30-day review by the Air Force, focusing on regulatory, factual, technical, and legal issues. The contractor will then incorporate comments and submit a draft document along with a submittal letter for a 7-day review. Upon approval, the draft will be distributed for regulatory review by an unspecified deadline. The contractor will resolve regulator comments and submit a final document for acceptance. Review timelines vary based on applicable regulatory agreements but generally conclude within 7 days.

View the file

Other files for this federal contract opportunity

Other files attached to BRAC Environmental Construction Optimization Services (BECOS) - NorCal Region, newest first.
File Type Posted
202000401_FA8903-20-R-0014 NorCal RFP Questions and Answers UPDATED.xlsx XLSX spreadsheet
20200313_FA890320R0014_NorCal_BECOS_Section_M v3 Amendment 1.docx DOCX document
Solicitation Amendment FA890320R00140001 SF 30.pdf PDF
FA890320R0014 NorCal Amendment Changes.docx DOCX document
20200109_NorCal TO2 Price Model-Amendment 1.xlsx XLSX spreadsheet
20200323_FA890320R0014_BECOS_NorCal_Section_L-Amendment 1.docx DOCX document
20200317_20-R-0014 NorCal RFP Questions and Answers Set 2 of 2.xlsx XLSX spreadsheet
FA890320R0014_BECOS NorCal RFP Questions and Answers Set 1 of 2_03102020.xlsx XLSX spreadsheet
20200203_FA890320R0014_BECOS_NorCal_Section_L v4.docx DOCX document
20191217_Compensation Plan Model.xlsx XLSX spreadsheet
20200203_NorCal IDIQ_Sched B_CLIN Structure v2.xlsx XLSX spreadsheet
BECOS IDIQ DD1423 CDRLS EXHIBIT A003-A012 (MGMT).pdf PDF
WA20190076 1Nov2019 Spokane Heavy.pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT A013 (MISC CONT).pdf PDF
20200131_FA890320R0014_BECOS_Relevancy_PPQ.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B002-B003 (MGMT).pdf PDF
20200131_FA890320R0014_BECOS_Relevancy_Matrix v2.docx DOCX document
TO 2 PWS Attch 2 Mather Base Spec Req NorCal BECOS vf3.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B004 (CMAN).pdf PDF
TO 1 CDRLs Exhibit A B NorCal BECOS vf2.docx DOCX document
20200109_NorCal TO2 Price Model jb - Copy.xlsx XLSX spreadsheet
20200203_FA890320R0014_NorCal_BECOS_Section_M v3.docx DOCX document
IDIQ PWS Attch 1 NorCal Site List BECOS vf2.xlsx XLSX spreadsheet
TO 2 PWS Attch 1 NorCal Site List BECOS vf5.xlsx XLSX spreadsheet
BECOS IDIQ DD1423 CDRLS EXHIBIT A010 (QCIC).pdf PDF
TO 2 PWS Attch 2 McClellan Base Spec Req NorCal BECOS vf4.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B005-B006-B007 (ADMN).pdf PDF
CA20190018 24Jan2020 Merced Santa Clara Building, Heavy.pdf PDF
CA20190007 24Jan2020 Sacramento Building, Heavy.pdf PDF
TO 1 PWS NorCal BECOS vf3.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT A005-A006-A011 (CMAN).pdf PDF
TO 2 PWS NorCal BECOS vf3.docx DOCX document
20200122_NorCal FFP FBLR Tables v2.xlsx XLSX spreadsheet
TO 2 CDRLs Exhibit A B NorCal BECOS vf2.docx DOCX document
TO 2 PWS Attch 2 Castle Base Spec Req NorCal BECOS vf2.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT A007-A008-A009 (ENVR).pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT A001-A002-A004 (MISC).pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT A014 (DRPR).pdf PDF
IDIQ PWS NorCal BECOS vf5.docx DOCX document
20200131_FA8903-20-R-0014_BECOS RFP Questions and Answers Template.xlsx XLSX spreadsheet
Solicitation - FA890320R0014 v2.pdf PDF
BECOS IDIQ DD1423 CDRLS EXHIBIT C001 (MGMT).pdf PDF
IDIQ PWS Attch 2 NorCal Acr and Def BECOS vf2.docx DOCX document
BECOS IDIQ DD1423 CDRLS EXHIBIT B001 (MISC).pdf PDF
WA20190017 15Nov2019 Spokane Building.pdf PDF
IDIQ PWS Attch 4 NorCal Perf Obj Def BECOS vf1.docx DOCX document
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NorCal Region Attachment 3 5 December 2019

Deliverable Review Process Air Force Contractor Regulators Task: Prepare working copy document.

Timeframe: Dependent on task Scope: Dependent on task Task: Review working copy document.

Timeframe: 30 calendar days (max) Scope: Comments will focus on regulatory, factual, technical, and legal issues and should not conflict with the terms and conditions of the contract (e.g., directing the contractor on approach).

Tasks: Incorporate review comments. Prepare submittal letter.

Timeframe: Dependent on task Scope: Evaluate and incorporate all regulatory, factual, technical, and legal Air Force comments that do not conflict with the terms and conditions of the contract.

Task: Review draft document and sign submittal letter if document is acceptable. Return for further revisions if required.

Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.

Task: Obtain regulatory review of draft document.

Timeframe: TBD Scope: Distribute submittal letter and document to regulators. Provide copies to the Air Force.

Task: Provide regulatory review.

Timeframe: FFA/DSMOA/Circumstantial Scope: Provide regulatory review of submitted document.

Tasks: Resolve comments and revise document. Prepare submittal letter.

Timeframe: TBD Scope: Provide timely evaluation and resolution of regulatory comments with a goal of meeting predetermined objectives.

Task: Submit final document.

Timeframe: TBD Scope: Submit final document for regulatory acceptance/concurrence.

Task: Review final document and sign submittal letter if document is acceptable. Return for further revisions if required.

Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.

Task: Accept final document.

Timeframe: FFA/DSMOA/Circumstantial Scope: Accept final document and provide written notice.

Note: This is a generic document review process for this contract. Actual review times will be based on the Federal Facility Agreement (FFA) where applicable or the Joint Execution Plan (JEP) and associated schedules developed under the Defense State Memorandum of Agreement (DSMOA). Agencies reviewing the document may make specific requests based on complexity of the deliverable or work load of their technical review team that impact review timelines. Depending on the document, there may or may not be a draft version or there may be multiple draft versions.