SABER_Questions_and_Answers.doc

DOC document 27 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER) Federal contract opportunity
Solicitation number
FA8751-13-R-0014
Issued by
Department of the Air Force Materiel Command Research Laboratory

About this file

Q A Version 1

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition of Base Engineering Requirements (SABER), newest first.
File Type Posted
SABER_Specs_Addendum_1.docx DOCX document
FA8751-14-R-0003-01.pdf PDF
SABER_Questions_and_Answers.doc DOC document
Attachment_2_-_WRD_20120013.docx DOCX document
Attachment_4_-_WRD_20120031.docx DOCX document
FA8751-14-R-0003.pdf PDF
Attachment_1_-_Specifications.pdf PDF
Attachment_5_-_Past_Performance_Survey.doc DOC document
Attachment_3_-_WRD_20120014.docx DOCX document
PAST_PERFORMANCE_SURVEY_V2.docx DOCX document
SABER_2013_Master_Specifications_130227.pdf PDF
13R14_Section_L.doc DOC document
13R14_Section_M.doc DOC document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANSWERS TO INQUIRIES RECEIVED REGARDING SABER SOLICITATION #FA8751-14-R-0003

1.) To what extent will the prime Contractor (awardee) be responsible for design work associated with individual task orders?

Depending upon the scope of work associated with an individual task order, a minimum of 35% design shall be submitted to the (prime) Contractor. Normally, if required, the task order will contain enough detail such as reflected ceiling plans, equipment lists, finishes and so forth.

2.) If my company chooses to submit a joint offer with another firm, how does that affect the past performance requirement?

A proposal submitted on behalf of two (2) or more organizations is expected to include past performance information for any and all involved organizations. Past performance information of all organizations tied to an offer will be evaluated in the award decision.

3.) Why can’t I find/locate any plans or drawings on the FedBizOpps website?

The resultant contract of this solicitation will be a five (5) year Indefinite Delivery Indefinite Quantity (IDIQ) contract. The very nature of an IDIQ contract, as the name suggests, is such that it is not known in advance the exact type and number of requirements that will arise over the course of the five (5) year ordering period. Hence, no plans or drawings are available at the time of the solicitation of this IDIQ contract. The minimum amount of work guaranteed under the resultant contract is limited to the first task order.

4.) Should the coefficient be inclusive of bonding?

No. Costs associated with bonding should be included as line item(s) on the Contractor’s proposal for the individual task orders for which such bonding is required.

5.) Should by coefficient be inclusive of the cost associated with providing the Government the required copies of the RS MEANS price books?

Yes. Offerors’ coefficients should be reflective of the cost associated with providing the Government the required copies of the RS MEANS price books. It is anticipated that the RS MEANS price books will be included as a line item on the first task order issued to the awardee.

6.) Will you consider extending the proposal submission deadline?

At this time, no extensions are anticipated to be granted and the 24 January 2014 is firm. No late offers will be considered for award.

As of 17-January-2014. C.F.O