About this file

This is a solicitation for the Joint Terminal Control Training and Rehearsal System (JTC TRS) Program. The solicitation seeks to continue procuring and sustaining high-fidelity simulation systems, including fixed dome, desktop, and portable devices, to provide realistic training for terminal attack control, close air support, and air-to-ground command and control. The systems must be upgradeable, HLA/DIS compliant, and capable of distributed operations over DMO networks. Contractor support will include operating the Air Support Operations Center simulator, performing maintenance, installing upgrades, and managing spare parts and repairs through a Training System Support Center. The contractor must meet repair time requirements and maintain system concurrency as defined in the performance specification and contract.

View the file

Other files for this federal contract opportunity

Other files attached to Joint Terminal Control Training and Rehearsal System (JTC TRS) Program, newest first.
File Type Posted
Attachment 7_Asset List_Revised_18 Jun 20.pdf PDF
Attachment 11_Section L_15 June 20.pdf PDF
Attachment 12_SECTION _M_15 Jun 20 update.pdf PDF
Attachment 3_Price Matrix_Revised_15 Jun 20.xlsx XLSX spreadsheet
Attachment 1_PWS_Revised 15 Jun 20.pdf PDF
Q and A_08 Jun 2020.xlsx XLSX spreadsheet
Attachment 12_SECTION _M_10 Jun 20 update.pdf PDF
Attachment 7_Asset List_Revised_10 Jun 20.pdf PDF
15-5229_Ft. Bliss TX.txt TXT text file
Attachment 11_Section L.pdf PDF
15-5683_Ft. Wainwright AK.txt TXT text file
15-4527_Ft Benning GA.txt TXT text file
15-5689_Wheeler HI.txt TXT text file
15-5253_JBSA TX.txt TXT text file
15-5197_Ft. Polk LA.txt TXT text file
15-4731_Wright Patt AFB OH.txt TXT text file
15-5629_Ft. Irwin CA.txt TXT text file
15-4701_Ft. Campbell KY.txt TXT text file
15-4377_Pope_Ft. Bragg NC.txt TXT text file
15-5775_Ft. Drum NY.txt TXT text file
15-5539_JBLM_Camp Murray WA.txt TXT text file
15-5315_Will Rogers ANG OK.txt TXT text file
15-4485_Ft. Stewart GA.txt TXT text file
Draft Model Contract_Rev 1.pdf PDF
Complete Q and A_01 Jun 2020.xlsx XLSX spreadsheet
JTC_TRS General Instructions 20200515_Update.pdf PDF
Exhibit A_JTC TRS CDRL_5-15-20.pdf PDF
Attachment 11_Section L_Final.pdf PDF
PPI_Letter_12 May.pdf PDF
L-2-Consent Letter.pdf PDF
Attachment 1_PWS_11 May 20.pdf PDF
M4 SCENARIO 3 DESCRIPTION AND TEST POINTS.pdf PDF
M3 SCENARIO 2 DESCRIPTION AND TEST POINTS.pdf PDF
Attachment 12_SECTION _M_RFP_FINAL.pdf PDF
Attachment 13-Cross Reference Matrix.docx DOCX document
Attachment 5_DD254.pdf PDF
M5 SCENARIO 4 DESCRIPTION AND TEST POINTS.pdf PDF
Attachment 8_GFP List.pdf PDF
Attachment 2_FoS_PSpec.pdf PDF
Attachment 9_AFMCForm158 JTC TRS.pdf PDF
L-4_PPI Tool.pdf PDF
L-3-Client Authorization Letter.pdf PDF
M1 TEST PLAN AND TEST POINTS.pdf PDF
M6 SUPPLEMENTAL AND EME TEST POINTS.pdf PDF
RFP_Cover_Letter_11 May.pdf PDF
JTC_TRS General Instructions 20200430_DRAFT.pdf PDF
Attachment 6_IUID JTC TRS.pdf PDF
Attachment 7_Asset List.pdf PDF
Exhibit A_JTC TRS CDRL_4_21_20.pdf PDF
M2 SCENARIO 1 DESCRIPTION AND TEST POINTS.pdf PDF
Show all 50

Joint Terminal Control Training and Rehearsal System (JTC TRS) Program has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER AND AWARD

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 350)

RATING

DO-A7

PAGE OF PAGES

1 130

2. CONTRACT NO. 3. SOLICITATION NO. 4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

5. DATE ISSUED

6. REQUISITION/PURCHASE NO.

FA8621-20-R-0003

7. ISSUED BY AFLCMC/WNSK CODE FA8621 8. ADDRESS OFFER TO (If other than Item 7)

USAF/AFMC/AFLCMC

AF LIFE CYCLE MANAGEMENT CENTER

2300 D STREET

WRIGHT-PATTERSON AFB OH 45433-7249

JACOB M. RUCKMAN 937 656-8072

JACOB.RUCKMAN.1@US.AF.MIL

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder”.

SOLICITATION

9.

10. FOR

INFORMATION

CALL:

A. NAME

See Block 7

B. TELEPHONE (Include area code)

(NO COLLECT CALLS)

C. E-MAIL ADDRESS

11. TABLE OF CONTENTS

() SEC. DESCRIPTION PAGE(S) () SEC DESCRIPTION PAGE(S)

PART I - THE SCHEDULE PART II - CONTRACT CLAUSES

A SOLICITATION/CONTRACT FORM 1 I CONTRACT CLAUSES 117

B SUPPLIES OR SERVICES AND PRICES/COSTS 2 PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACH.

C DESCRIPTION/SPECS./WORK STATEMENT 107 J LIST OF ATTACHMENTS 130

D PACKAGING AND MARKING 108 PART IV - REPRESENTATIONS AND INSTRUCTIONS

E INSPECTION AND ACCEPTANCE 109 K REPRESENTATIONS, CERTIFICATIONS, K - 1

F DELIVERIES OR PERFORMANCE 110 AND OTHER STATEMENTS OF OFFERORS

G CONTRACT ADMINISTRATION DATA 113 L INSTRS, CONDS, AND NOTICES TO OFFERORS L - 1

H SPECIAL CONTRACT REQUIREMENTS 116 M EVALUATION FACTORS FOR AWARD M - 1

OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

12. In compliance with the above, the undersigned agrees, if this offer is accepted within ________ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date of receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

10 CALENDAR DAYS

20 CALENDAR DAYS

30 CALENDAR DAYS

CALENDAR DAYS

14. ACKNOWLEDGEMENTS OF AMENDMENTS

(The offeror acknowledges receipt of amend-

AMENDMENT NO. DATE AMENDMENT NO. DATE

ments to the SOLICITATION for offerors and related documents numbered and dated:

15A. NAME

AND

CODE FACILITY 16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

ADDRESS

OF

OFFEROR

15B. TELEPHONE NO. (Include area code)

15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

17. SIGNATURE 18. OFFER DATE

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETI-

TION: 23. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

28. AWARD DATE

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 33 (REV. 9-97)

PREVIOUS EDITION IS UNUSABLE Prescribed by GSA

ConWrite Version 7.2.800 FAR (48 CFR) 53.21(c) Created 16 Apr 2020 2:29 PM

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

SECTION B FA8621-20-R-0003

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

SYSTEM PRODUCTION: DOMES

1000 1 __________ Each __________ Noun: DOME SYSTEM PRODUCTION: BASIC - CY 2021

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

This line item price was derived using the prices as set forth in Section J, Attachment 3, Pricing Matrix.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1001 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 1 - CY 2022

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1002 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 2 - CY 2023

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1003 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 3 - CY 2024

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1004 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 4 - CY 2025

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1005 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 5 - CY 2026

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1006 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 6 - CY 2027

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1007 OPTION CLIN __________

Noun: DOME SYSTEM PRODUCTION: OPTION YEAR 7 - CY 2028

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS devices in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2. The JTC TRS Training System shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1100 1 __________ Each __________ Noun: DESKTOP SYSTEM PRODUCTION: BASIC - CY 2021

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1101 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 1 - CY

PSC:

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1102 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 2 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

The Government may exercise this option more than once in a calendar year (CY) in accordance with the procedures outlined in Section J, Attachment 3 Pricing Matrix. Firm-fixed price CLINs (i.e. 1301, 1302, etc.) will be established when this option is exercised more than once in a CY by the Government.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1103 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 3 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1104 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 4 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1105 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 5 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1106 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 6 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1107 OPTION CLIN __________

Noun: DESKTOP SYSTEM PRODUCTION: OPTION YEAR 7 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS desktops in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS desktop shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly, installation, checkout and host base interface at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1200 1 __________ Each __________ Noun: PORTABLE SYSTEM PRODUCTION: BASIC - CY 2021

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1201 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 1 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1202 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 2 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1203 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 3 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1204 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 4 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1205 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 5 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1206 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 6 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

1207 OPTION CLIN __________

Noun: PORTABLE SYSTEM PRODUCTION: OPTION YEAR 7 - CY

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

The contractor shall provide all necessary management, resources, and effort to produce, deliver and install JTC TRS portable devices in accordance with Section J, Attachment 1, Performance Work Statement (PWS), Paragraph 3.11, and Section J, Attachment 2, Performance Specification. The JTC TRS portable shall consist of hardware, software, firmware, databases, support equipment and documentation required to support the simulation of the JTAC environment. The contractor shall provide system assembly and checkout at the delivery site. Preservation, packaging, packing and marking of the supplies and data called for hereunder shall be in accordance with the Contractor's standard commercial practices and ASTM D3951-10.

The contractor shall also provide operational training for designated JTC TRS operators at each site as part of initial system production and delivery in accordance with Section J, Attachment 1 - Performance Work Statement Sections 4.1 and 4.2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2000 1 __________ Each __________ Noun: AFSOC EME PACKAGE - BASIC - CY 2021

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2001 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 1 - CY 2022

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2002 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 2 - CY 2023

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2003 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 3 - CY 2024

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2004 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 4 - CY 2025

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2005 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 5 - CY 2026

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2006 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 6 - CY 2027

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2007 OPTION CLIN __________

Noun: AFSOC EME PACKAGE - OPTION YEAR 7 - CY 2028

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2100 1 __________

Noun: ACC EME PACKAGE - BASIC - CY2021

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2101 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 1 - CY2022

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2102 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 2 - CY2023

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2103 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 3 - CY2024

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2104 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 4 - CY2025

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2105 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 5 - CY2026

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2106 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 6 - CY2027

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2107 OPTION CLIN __________

Noun: ACC EME PACKAGE - OPTION YEAR 7 - CY2028

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2200 1 __________

Noun: SOCOM EME PACKAGE - BASIC - CY2021

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount

2201 OPTION CLIN __________

Noun: SOCOM EME PACKAGE - OPTION YEAR 1 - CY2022

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

2202 OPTION CLIN __________

Noun: SOCOM EME PACKAGE - OPTION YEAR 2 - CY2023

PSC:

NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION

FOB: DESTINATION

Descriptive Data:

EME Packages will be delivered with the JTC TRS training system as a basic package for unit production in accordance with the Performance Work Statement, Section J, Attachment 1 and Performance Specification, Section J, Attachment 2.

Delivery/Acceptance is complete upon execution of DD Form 250 for each article; at which time, the ACO is authorized to approve the invoice for payment.

Q…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .