Atch_7 _Pricing_Worksheets.xlsx

XLSX spreadsheet 39 KB Posted

Attached to
MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) Federal contract opportunity
Solicitation number
FA8601-14-R-0007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Atch 7 Pricing Worksheets

View the file

Other files for this federal contract opportunity

Other files attached to MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC), newest first.
File Type Posted
Question_ _Response__83_-_85.pdf PDF
Seed_Proj_071930 _Addendum_002 _24_Jul_14.pdf PDF
Seed_Project_071930 _Addendum_002 _Attachment_4 2 .pdf PDF
NOTICE_TO_OFFERORS__2.pdf PDF
Atch_7 _Pricing_Worksheets_(v2)_Jul_14.xlsx XLSX spreadsheet
Atch_5 _Wage_Decision_OH140016_Mod_16 _18_July_14.pdf PDF
Atch_14 _Sample_Proj_-_Addendum_0002.pdf PDF
Question_ _Response__60_-_61.pdf PDF
Atch_10 _Seed_Project_-_Addendum_0001.pdf PDF
Atch_11 _Seed_Project_-_Addendum_001 _Atch_3.pdf PDF
Atch_13 _Sample_Project_-_Addendum_001.pdf PDF
FA8601-14-R-0007-0001.pdf PDF
Atch_12 _20255_02.dwg DWG drawing
Atch_5 _DBA_Wage_Decision_OH140016 _Modification_15_4_July_14.pdf PDF
Atch_12 _20255_01.dwg DWG drawing
2nd_Site_Visit_Posting.pdf PDF
30_June_2014_Site_Visit_Information.pdf PDF
Site_Visit_Sign-In_Sheet_-_30_June_2014.pdf PDF
Rules_of_Engagement.pdf PDF
Atch_1 _Appendix_D_Tobacco_Use_Policy.pdf PDF
Atch_9 _Sample_Proj_Drawings_-_9_Mar_11.pdf PDF
Atch_1 _MAC_SOW_-_Revised_21_Feb_14.pdf PDF
Atch_2_(Atch_1 _App_A)_WPAFB_BFS_and_Appendicies_Mar_2014.pdf PDF
FA8601-14-R-0007_-_18_June_2014.pdf PDF
Atch_5 _-_DBA_Wage_Decision _OH14016_13_June_2014.pdf PDF
Atch_1 _Appendix_F_Activity_Hazard_Analysis.pdf PDF
Atch_1 _Appendix_I_AF_Sustainable_Design_and_Development_Guide.pdf PDF
Atch_1 _Appendix_G_AF_Form_3000_Material_Submittal.pdf PDF
Atch_1 _Appendix_J_AF_3064_Construction_Progress_Schedule.pdf PDF
Questions_ _Responses__7-8.pdf PDF
Atch_1 _Appendix_J_AF_3064_Construction_Progress_Schedule.pdf PDF
Atch_5 _-_DBA_Wage_Decision _OH14016_2_May_14_-_Notepad.pdf PDF
Info_for_Industry_-_Draft__2.docx DOCX document
Atch_1 _Appendix_E_2008-EM-385-1-1_Safety_and_Health_Manual.pdf PDF
Atch_3 _(Atch_1 _App_C)_WPAFB_Master_Specs_-_6_May_14.pdf PDF
Atch_6 _Section_L _PZIOC_L-004_Atch_1_Solicitation-Cross_Ref_Matrix.docx DOCX document
Atch_9 _Sample_Proj_Drawings_-_9_Mar_11.pdf PDF
Atch_7 _Pricing_Worksheets.xlsx XLSX spreadsheet
Atch_2_(Atch_1 _App_A)_WPAFB_BFS_and_Appendicies_Mar_2014.pdf PDF
DRAFT__2_-_FA8601-14-R-0007.pdf PDF
Atch_1 _Appendix_K_AF_Form_103_Dig_Permit.pdf PDF
Atch_4 _Seed_Project_SOW_-_10_Oct_13.pdf PDF
Atch_1 _Appendix_B_AF_Form_3065_Contract_Progress_Report.pdf PDF
Atch_1 _Appendix_D_Tobacco_Use_Policy.pdf PDF
Delay_in_Issuance_of_MACC_RFP_-_13_Dec_13.pdf PDF
Question__Response__4-6.pdf PDF
Info_for_Industry_-_6_Nov_13.pdf PDF
Atch_2 _Base_Facility_Standard _WPAFB_-_May_2013.pdf PDF
Atch_4 _Seed_Project_071930.pdf PDF
DRAFT_FA8601-14-R-0007.pdf PDF
Show all 50

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Non-DBA Labor Rate Matrix

BINDING NOT TO EXCEED HOURLY LABOR RATE MATRIX

FOR

NON-DAVIS BACON ACT (DBA) LABOR CATEGORIES

REQUIRED BY THE STATEMENT OF WORK (SOW)

Note: Offeror is required to complete the following:

All Blue Cells All other cells will self-populate

Required Non-DBA Labor Category
(Reference SOW Paragraph 3)Ordering Period
Hourly Rates for Ordering Period 1Hourly Rates for Ordering Period 2Hourly Rates for Ordering Period 3Hourly Rates for Ordering Period 4Hourly Rates for Ordering Period 5*Hourly Rates for Potential

6-Month Option Extension

Contract Manager (CM)$ - 0
Project Superintendent (PS)$ - 0
Design Quality Control Manager (DQCM)$ - 0
Contract Quality Control Manager (CQCM)$ - 0
Site and Health Officer (SSHO)$ - 0
Environmental Manager (EM)$ - 0
* Offerors are to assume (for evaluation purposes only) the total 6-month extension shall be incorporated after Ordering Period 5 has expired. However, IAW FAR 52.217-8, Extension of Services (up to six months), the Government reserves the right to exercise this clause during any ordering period. If the clause is exercised, pricing will be determined at the time of exercise, based upon current unit pricing.

FA8601-14-R-0007

Multiple Award Construction Contract (MACC)

Attachment 7 For Evaluation and Award Purposes Binding NTE Non-DBA Labor Rate Matrix

TO Pricing for Seed Project

MACC TASK ORDER PRICING WORKSHEET

FOR SEED PROJECT

(FOR EVALUATION AND AWARD PURPOSES)

Note: Offeror is required to complete the following:

All Blue Cells All other cells will self-populate.

PROJECT NUMBER071930 (MACC Seed Project)
MAGNITUDE OF CONSTRUCTION (Per FAR 36.204)Between $100,000 and $250,000
PROJECT TITLE/DESCRIPTIONUpgrade Fire Alarm Systems 20255 - To furnish all materials and perform all labor required to Upgrade Fire Alarm Systems for Facility 20255, including associated architectural, civil, structural, mechanical, plumbing, electrical and miscellaneous work as shown on the project drawings and described in the specifications.
FACILITY NUMBER20255
PERIOD OF PERFORMANCE180Calendar Days
SECTION I
DescriptionQtyU/IUnit PriceTotal
Davis-Bacon Act (DBA) Labor, Material, Subcontractor, Equipment Rental, etc (Direct Costs associated with the performance of this project other than those listed below)1Project$ - 0
SECTION II
Non-DBA Labor Applicable to this Project (Reference SOW Paragraph 3)
DescriptionQtyU/IUnit PriceTotal
Contract Manager (CM)Hour$ - 0$ - 0
Project Superintendent (PS)Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)Hour$ - 0$ - 0
Site and Health Officer (SSHO)Hour$ - 0$ - 0
Environmental Manager (EM)Hour$ - 0$ - 0
Section II Total$ - 0
Subtotal of Section I & II$ - 0
Indirect Markup Factor0.0%$ - 0
Task Order Total
(For Evaluation and Award Purposes)$ - 0

Contractor Certification: By submission of this proposal, I hereby certify that the hourly rates for the professional labor categories cited above as well as the Indirect Markup Factor do not exceed the rates proposed and incorporated into the basic contract.

Signature: __________________________________________

Title: ______________________________________________

Date:_______________________________________________

FA8601-14-R-0007

Multiple Award Construction Contract (MACC)

Attachment 7For Evaluation & Award of
Seed Project PurposesTask Order Pricing for Seed Project

TO Pricing for Sample Project

MACC TASK ORDER PRICING WORKSHEET

FOR SAMPLE PROJECT

(FOR EVALUATION PURPOSES ONLY)

Note: Offeror is required to complete the following:

All Blue Cells All other cells will self-populate

PROJECT NUMBER000077 (MACC Sample Project)
MAGNITUDE OF CONSTRUCTION (Per FAR 36.204)Between $500,000 and $1,000,000
PROJECT TITLE/DESCRIPTIONRenovate/Reconfigure PAX Terminal - to furnish all materials and equipment and to perform all labor and secure all permits required to Renovate/ Reconfigure PAX Terminal, Facility 30206 including all required demolition, site preparation, civil, architectural, structural, mechanical, electrical, and miscellaneous associated incidental work at adjacent areas, as shown on the project drawings and described in the specifications.
FACILITY NUMBER30206
PERIOD OF PERFORMANCE240Calendar Days
SECTION I
DescriptionQtyU/IUnit PriceTotal
Davis-Bacon Act (DBA) Labor, Material, Subcontractor, Equipment Rental, etc (Direct Costs associated with the performance of this project other than those listed below)1Project$ - 0
Section II
Non-DBA Labor Applicable to this Project (Reference SOW Paragraph 3)
DescriptionQtyU/IUnit PriceTotal
Contract Manager (CM)Hour$ - 0$ - 0
Project Superintendent (PS)Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)Hour$ - 0$ - 0
Site and Health Officer (SSHO)Hour$ - 0$ - 0
Environmental Manager (EM)Hour$ - 0$ - 0
Section II Total$ - 0
Subtotal of Section I & II$ - 0
Indirect Markup Factor0.0%$ - 0
Task Order Total
(For Evaluation Purposes Only)$ - 0

Contractor Certification: By submission of this proposal, I hereby certify that the hourly rates for the professional labor categories cited above as well as the Indirect Markup Factor do not exceed the rates proposed and incorporated into the basic contract.

Signature: __________________________________________

Title: ______________________________________________

Date:_______________________________________________

FA8601-14-R-0007

Multiple Award Construction Contract (MACC)

Attachment 7 For Evaluation Purposes Only Task Order Pricing for Sample Project

Non-DBA Pricing Scenario

NON-DBA PRICING SCENARIO

(FOR EVALUATION PURPOSES ONLY)

NOTE: The offeror is NOT to manually complete this worksheet. The Binding Non-DBA Labor Rates for each ordering period column will self-populate from the rates entered by the offeror on the Non-DBA Labor Rate Matrix. The Total column has been preformatted to automatically total.

Ordering Period 1 Non-DBA Labor Applicable to this Scenario (Reference SOW Paragraph 3)

Required Non-DBA Labor CategoryQty*U/IBinding Non-DBA Labor Rate from Matrix (Ordering Period 1)Total
Contract Manager (CM)420Hour$ - 0$ - 0
Project Superintendent (PS)1040Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)80Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)580Hour$ - 0$ - 0
Site and Health Officer (SSHO)360Hour$ - 0$ - 0
Environmental Manager (EM)280Hour$ - 0$ - 0
Non-DBA Labor Total for Ordering Period 1
(FOR EVALUATION PURPOSES ONLY)$ - 0

*Qty (e.g., number of hours per labor category) are set numbers provided by the Government for the purposes of this evaluation only.

Ordering Period 2 Non-DBA Labor Applicable to this Scenario (Reference SOW Paragraph 3)

Required Non-DBA Labor CategoryQty*U/IBinding Non-DBA Labor Rate from Matrix (Ordering Period 2)Total
Contract Manager (CM)420Hour$ - 0$ - 0
Project Superintendent (PS)1040Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)80Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)580Hour$ - 0$ - 0
Site and Health Officer (SSHO)360Hour$ - 0$ - 0
Environmental Manager (EM)280Hour$ - 0$ - 0
Non-DBA Labor Total for Ordering Period 2
(FOR EVALUATION PURPOSES ONLY)$ - 0

*Qty (e.g., number of hours per labor category) are set numbers provided by the Government for the purposes of this evaluation only.

Ordering Period 3 Non-DBA Labor Applicable to this Scenario (Reference SOW Paragraph 3)

Required Non-DBA Labor CategoryQty*U/IBinding Non-DBA Labor Rate from Matrix (Ordering Period 3)Total
Contract Manager (CM)420Hour$ - 0$ - 0
Project Superintendent (PS)1040Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)80Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)580Hour$ - 0$ - 0
Site and Health Officer (SSHO)360Hour$ - 0$ - 0
Environmental Manager (EM)280Hour$ - 0$ - 0
Non-DBA Labor Total for Ordering Period 3
(FOR EVALUATION PURPOSES ONLY)$ - 0

*Qty (e.g., number of hours per labor category) are set numbers provided by the Government for the purposes of this evaluation only.

Ordering Period 4 Non-DBA Labor Applicable to this Scenario (Reference SOW Paragraph 3)

Required Non-DBA Labor CategoryQty*U/IBinding Non-DBA Labor Rate from Matrix (Ordering Period 4)Total
Contract Manager (CM)420Hour$ - 0$ - 0
Project Superintendent (PS)1040Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)80Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)580Hour$ - 0$ - 0
Site and Health Officer (SSHO)360Hour$ - 0$ - 0
Environmental Manager (EM)280Hour$ - 0$ - 0
Non-DBA Labor Total for Ordering Period 4
(FOR EVALUATION PURPOSES ONLY)$ - 0

*Qty (e.g., number of hours per labor category) are set numbers provided by the Government for the purposes of this evaluation only.

Ordering Period 5 Non-DBA Labor Applicable to this Scenario (Reference SOW Paragraph 3)

Required Non-DBA Labor CategoryQty*U/IBinding Non-DBA Labor Rate from Matrix (Ordering Period 5)Total
Contract Manager (CM)420Hour$ - 0$ - 0
Project Superintendent (PS)1040Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)80Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)580Hour$ - 0$ - 0
Site and Health Officer (SSHO)360Hour$ - 0$ - 0
Environmental Manager (EM)280Hour$ - 0$ - 0
Non-DBA Labor Total for Ordering Period 5
(FOR EVALUATION PURPOSES ONLY)$ - 0

*Qty (e.g., number of hours per labor category) are set numbers provided by the Government for the purposes of this evaluation only.

Potential 6-Month Option Extension Non-DBA Labor Applicable to this Scenario (Reference SOW Paragraph 3)

Required Non-DBA Labor CategoryQty*U/IBinding Non-DBA Labor Rate from Matrix (Potential 6-Month Option Extension)Total
Contract Manager (CM)420Hour$ - 0$ - 0
Project Superintendent (PS)1040Hour$ - 0$ - 0
Design Quality Control Manager (DQCM)80Hour$ - 0$ - 0
Contract Quality Control Manager (CQCM)580Hour$ - 0$ - 0
Site and Health Officer (SSHO)360Hour$ - 0$ - 0
Environmental Manager (EM)280Hour$ - 0$ - 0
Non-DBA Labor Total for Potential 6-Month Option Extension
(FOR EVALUATION PURPOSES ONLY)$ - 0

*Qty (e.g., number of hours per labor category) are set numbers provided by the Government for the purposes of this evaluation only.

Non-DBA Labor Total for:

Ordering Period 1 + Ordering Period 2 + Ordering Period 3 + Ordering Period 4 + Ordering Period 5 + Potential 6-Month Option Extension

(FOR EVALUATION PURPOSES ONLY) $ - 0

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

Attachment 7 For Evaluation Purposes Only Non-DBA Pricing Scenario

Total Evaluated Price Calc

TOTAL EVALUATED PRICE (TEP) CALCULATION FOR THE

MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)

Note: Offeror is required to complete the following cells on this worksheet:

All Blue Cells. Additionally, the offeror shall provide a separate detailed summary of how they arrived at their NTE Indirect Markup Factor Rate. This information must be provided in Volume III, Price/Contract Documentation - not as part of this matrix attachment.

All other cells will self-populate.

Offeror's Name:
Product or Service DescriptionGovernment Provided EstimateOfferor's Proposed NTE Indirect Markup Factor Rate (Binding)Total Price Element
CLIN 0001 - Ordering Period 1 Cost Estimate$ 18,184,000X$ - 0
CLIN 0002 - Ordering Period 2 Cost Estimate$ 18,184,000X$ - 0
CLIN 0003 - Ordering Period 3 Cost Estimate$ 18,184,000X$ - 0
CLIN 0004 - Ordering Period 4 Cost Estimate$ 18,184,000X$ - 0
CLIN 0005 - Ordering Period 5 Estimate$ 18,184,000X$ - 0
CLIN 0006 -
Potential 6-Month Option Extension Cost Estimate$ 9,080,000X$ - 0
Subtotal:$ - 0
Offeror's Proposed Price for Seed Project
(For Award and Evaluation Purposes)$ - 0
Offeror's Proposed Price for Sample Project
(For Evaluation Purposes Only)$ - 0
Offeror's Proposed Price for Non-DBA Pricing Scenario for Ordering Periods 1, 2, 3, 4, 5 and the Potential 6-Month option Extension (Binding Rates - But For Evaluation Purposes Only)$ - 0
Total Evaluated Price:$ - 0

Multiple Award Construction Contract (MACC)

Attachment 7 For Evaluation and Award Purposes Total Price Evaluation (TEP) Calculation

File details come from the government source that posted it. Updated .