View the file

Other files

File Type Posted
Safety Health Plan Requirement —
FFPAddendum.doc DOC document
Section 01 33 00.pdf PDF
Amendment 4.doc DOC document
Section 01 01 50.pdf PDF
Question 4.doc DOC document
Amendment 3.doc DOC document
Amendment 2.doc DOC document
Question 2.doc DOC document
Site Visit Sign in Sheet - 17 FEB 2010.pdf PDF
Question 1.doc DOC document
Site Visit 2 - 17 Feb 2010 - 1400.doc DOC document
Wage Decision 2.docx DOCX document
Amendment 1.doc DOC document
Site Visit Sign in Sheet - 2 FEB 2010.pdf PDF
Wage Decision.docx DOCX document
Solicitation.doc DOC document
STATEMENT OF WORK.pdf PDF
Drawings.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION

At the walk through it was discussed that the carpet was to be replaced therefore it did not make sense for us to re-install base if the carpet was to be replaced. Could you please clarify this for bidding purposes?

ANSWER

Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If changes are made to the requirements after award they will come in the form of a change order.