Appendix C.docx

DOCX document 24 KB Posted

Attached to
Versatile Depot Automatic Test Station (VDATS) Performance Based Acquisition
Solicitation number
FA8535-09-R-0001(RFP_FINAL)
Issued by

About this file

Appendix C

View the file

Other files

File Type Posted
FA8535-09-R-0001-0005.pdf PDF
VDATS_PWS_14-Jan-10_Final.docx DOCX document
VDATS_PWS_4 Dec 09.docx DOCX document
H-901 Revised 8 Dec 09.docx DOCX document
FA853509R0001_______0004.pdf PDF
FA853509R0001_______0003.pdf PDF
FA853509R0001_______0002.pdf PDF
A006.pdf PDF
VDATS_PWS_30-Oct-09.pdf PDF
A009.pdf PDF
VDATS Pricing Matrix RFP Attachment--FINAL--30 Oct 09.xls XLS spreadsheet
Final Industry RFP QAs - 30 Oct 09.pdf PDF
A006.pdf PDF
Industry RFP QAs - 9 Oct 09.pdf PDF
FA853509R0001_______0001.pdf PDF
AFMC Form 158.pdf PDF
AFMC IMT 260s.pdf PDF
260 PN200625750-10(1375).xfdl XFDL file
260 PN200625700-10(4490).xfdl XFDL file
A001.pdf PDF
AFMC Form 158.xfdl XFDL file
A008.pdf PDF
A005.pdf PDF
A002.pdf PDF
Atch 12 Subcontractor-Teaming Partnerner Consent Form.docx DOCX document
Atch 15 Client Authorization Letter.docx DOCX document
Atch 14 Transmittal Letter for Government Sources.docx DOCX document
VDATS_PWS_2-Sep-09(final).pdf PDF
260 PN200625631-10(0693).xfdl XFDL file
A003.pdf PDF
AppendixB.docx DOCX document
DD254 - VDATS —
A004.pdf PDF
260 PN200625650-10 —
260 PN200625631-20(1534).xfdl XFDL file
Atch 11 FACTS Sheet Attachment.docx DOCX document
Atch 16 Past Performance Questionnaire Tracking Record.docx DOCX document
Atch 13 PCAG Questionnaire.docx DOCX document
A006.pdf PDF
A007.pdf PDF
FA853509R0001_4 Sep 09.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HQ WARNER ROBINS AIR LOGISTICS CENTER (AFMC)

ROBINS AIR FORCE BASE, GEORGIA

PURCHASE REQUEST: FD2060-09- 22600 DATE: 27 Aug 09

APPENDIX “C”

FOR

Performance-Based Work Statement

Versatile Depot Automatic Test Station

(VDATS)

PREPARED BY: Clyde L. Turner/78th ABW/SEG/Robins AFB GA/(478) 926-6271

SECTION I - GENERAL REQUIREMENTS

A. Safety Program Requirements:

VOLUNTARY PROTECTION PROGRAM (VPP). The Air Force (AF) is an active participant in the Occupational Safety and Health (OSHA) Voluntary Protection Program (VPP) in accordance with OSHA’s Instruction, CSP 03-01-003, Voluntary Protection Programs (VPP) Policies and Procedures Manual. We recommend all contractors become familiar with VPP. Information on VPP can be accessed at: http://www.osha.gov/dcsp/vpp/index.html. The AF’s intent in this participation is to ensure the safety and health of all employees, including contractors, and communicate our safety and health expectations with contractors. The AF’s interest is to protect AF personnel working in or around contractor operations and to protect AF equipment and property. In the event an unsafe condition is discovered with AF provided facilities or equipment, the contractor shall immediately notify the Contracting Officer and Safety Office associated with that Delivery/Task Order (D/TO) for evaluation. This requirement applies to on and off base D/TOs.

The contractor will implement a safety program that ensures the protection of Government personnel and property. In addition, the contractor must comply with all the applicable Occupational Safety and Health Administration (OSHA) Standards and National Fire Protection Association (NFPA) Standards at their facilities. The contractor must have a Safety Plan and submit it to the contracting officer for approval by 78th ABW/SEG (Safety Office) prior to commencement of any work described in this contract. The contractor’s Safety program will consist of the following:

1. A Safety Plan that addresses, as a minimum, the subjects listed in Section II (Specific Requirements), which is to be used during the performance of work described in this contract.

2. Mishap reporting procedures as defined in paragraph B1 below.

3. Conduct routine and recurring surveillance to ensure the safety requirements of this contract are enforced and complied with.

4. Competent personnel shall be used to perform the surveillance.

5. The contractor shall include a clause in all subcontracts requiring the subcontractors to comply with the safety provisions of this contract, as applicable.

6. All contractor personnel shall be trained and qualified to perform their job safely.

7. The contractor must identify segregated work-site locations for operations that cannot be co-mingled with general industrial operations.

B. Mishap Notification:

1. The contractor shall incorporate the following mishap notification procedures into their safety plan prior to submitting it to the government for review:

The contractor shall notify 78th ABW/SEG (Safety Office) telephonically at (478)926-6271 during normal duty hours, (478)327-2612 after duty hours, within one (1) hour after initial notification of all mishaps or incidents at or exceeding $2,000 (material + labor) in damage to DOD property entrusted by this contract. A follow-up (written or e-mail) of this mishap/incident notification shall be sent within three calendar days to 78th ABW/SEG (Safety Office) at the address below:

ATTN: Clyde Turner
659 Seventh St, Ste 707
RAFB, GA 31098

The information that is not available at the time of the initial notification shall be provided within 20 calendar days after the mishap. Mishap notification shall contain, as a minimum, the following information:

(a)Contract, Contract Number, Name and Title of Person(s) Reporting
(b)Date, Time and exact location of mishap/incident
(c)Brief Narrative of mishap/incident (Events leading to accident/incident)
(d)Cause of mishap/incident, if known
(e)Estimated cost of mishap/incident (material and labor to repair/replace)
(f)Nomenclature of equipment and personnel involved in mishap/incident
(g)Corrective actions (taken or proposed)
(h)Other pertinent information.

2. If requested by Government Personnel (PCO/ACO), the contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by the 78th ABW/SEG (Safety Office). The contractor and subcontractors shall cooperate fully and assist government personnel until the investigation is finalized and closed out.

3. Safety requirements listed in this package that do not relate to the contractor’s operations or services under this contract shall be considered self-deleting as mutually agreed upon by the contractor and the ACO.

SECTION II – SPECIFIC REQUIREMENTS

The contractor’s prepared Safety Plan shall clearly define procedures, personnel qualifications, facilities, required equipment and any other items necessary to fulfill the following elements for the protection of government personnel and property. The contractor’s safety plan shall meet or exceed the referenced standards below.

ELEMENT REQUIRED REFERENCED STANDARD

Mishap Notification Requirements This document, Section I, para B

Grounding and Bonding TO 00-25-234

Batteries 29 CFR 1910.178 and 29 CFR 1910.305

System modifications, which alter form, MIL Standard 882D, AFI 91-202 fit or function

Housekeeping 29 CFR 1910.141

Cleaning/corrosion control/treatment TO 00-25-234 and TO 1-1-689-3 for Avionics and Electronics

Soldering TO 00-25-234

Electronic/Electrostatic DischargeMIL HDBK 263B, TO 00-25-234
Sensitive (ESD) ComponentsMIL-STD-1686C

Traffic Safety AFI 91-207

FD2060-09- 22600