FORCE QA 2 Mar.doc

DOC document 27 KB Posted

Attached to
Fuels Operational Readiness Capability Equipment (FORCE) Federal contract opportunity
Solicitation number
FA8533-11-R-32637
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Question and Answer dated 2 March 2012

View the file

Other files for this federal contract opportunity

Other files attached to Fuels Operational Readiness Capability Equipment (FORCE), newest first.
File Type Posted
FORCE QA 1 Mar.doc DOC document
FORCE QA 24 Feb.doc DOC document
PD10WRGBGBEC14 Plumbing Assembly Rev B 9 February 2012.doc DOC document
PD10WRGBGBEC15 Filter Separator Rev A 14 February 2012.doc DOC document
PD10WRGBGBEC13 Servicing Platform Rev C 15 February 2012.doc DOC document
FA853311R32637______0003.pdf PDF
FORCE Q A.doc DOC document
Questions and Answers on RFP FA8533-11-R-32637 2-2-12.doc DOC document
SOW_Rev_1.doc DOC document
FA853311R32637_______0002.pdf PDF
FA8533-11-R-32637 Amend 0001 Package.pdf PDF
Questions and Answers on RFP FA8533-11-R-32637 1-26-12.pdf PDF
FA853311R32637_A005_Instructional_Media_Package.pdf PDF
FA853311R32637_F002_Supplemental_Data_for_Provisioning.pdf PDF
FA853311R32637_FORCE_Appendix_B.doc DOC document
FA853311R32637_F001_Logistics_Management_Information_Data_Products.pdf PDF
FA853311R32637_Engineering_Data_List_NSN4930015436231.pdf PDF
FA853311R32637_PD10WRGBGBEC13_Rev_A.doc DOC document
FA853311R32637_Engineering_Data_List_NSN4930015734818.pdf PDF
FA853311R32637_FA_158.pdf PDF
FA853311R32637_C001_Management_Plan.pdf PDF
FA853311R32637_PD10WRGBGBEC11.doc DOC document
FA853311R32637_Engineering_Data_List_NSN4930015731370.pdf PDF
FA853311R32637_C006_Status_of_Government_Furnished_Equipment.pdf PDF
FA853311R32637_Attachment_2_Questionnaire.pdf PDF
FA853311R32637_F003_Logistics_Management_Information_Summaries.pdf PDF
FA853311R32637_B001_System_Safety_Program_Plan.pdf PDF
FA853311R32637_C005_Conference_Minutes.pdf PDF
FA853311R32637_Engineering_Data_List_NSN4320015442959.pdf PDF
FA853311R32637_PD10WRGBGBEC14_Rev_A.doc DOC document
FA853311R32637_Attachment_4_Client_Authorization_Ltr.doc DOC document
FA853311R32637_TMCR.doc DOC document
FA853311R32637_Attachment_1_FACTS_Sheet.pdf PDF
FA853311R32637_D001_Product_Baseline_Index.pdf PDF
FA853311R32637_A001_Test_Procedures.pdf PDF
FA853311R32637_B003_Corrosion_Prevention_and_Control_Plan.pdf PDF
FA853311R32637_PD10WRGBGBEC12_Rev_A.doc DOC document
FA853311R32637_A002_Test_Inspection_Report_FA.pdf PDF
FA853311R32637_Engineering_Data_List_NSN4930015734819.pdf PDF
FA853311R32637_A004_Technical_Report_Study_Services.pdf PDF
FA853311R32637_Attachment_3_Transmittal_Letter.doc DOC document
FA853311R32637_Engineering_Data_List_NSN4930015434717.pdf PDF
FA853311R32637_C003_Contractor_Progress_Status_and_Management_Report.pdf PDF
FA853311R32637.RTF RTF text file
FA853311R32637_C002_Integrated_Master_Schedule.pdf PDF
FA853311R32637_B002_System_Safety_Hazard_Analysis_Report.pdf PDF
FA853311R32637_D002_Engineering_Change_Proposal.pdf PDF
FA853311R32637_C004_Conference_Agenda.pdf PDF
FA853311R32637_PD10WRGBGBEC15.doc DOC document
QA response to FA8533-11-R-32637 Synopsis.doc DOC document
Show all 50

Fuels Operational Readiness Capability Equipment (FORCE) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Fuels Operational Readiness Capability Equipment (FORCE)

Request for Proposal (RFP) FA8533-11-R-32637

2 Mar 2012

The following questions have been received in the WR-ALC/GRVKBB, Major Programs Contracting Office on the above FORCE requirement. The questions as well as the applicable answers are provided below for assistance to all potential offerors for the greater understanding of the Government’s requirement.

Question 1: Paragraph 3.5.6.3 of the Statement of Work requires production acceptance testing of hydrant plumbing assemblies to be in accordance with (IAW) paragraph 4.5 of PD10WRGBGBEC14.

Paragraph 4.5 of PD10WRGBGBEC14 states in its entirety “4.5 Test Methods.”

Is it the Government’s intention that there shall be no production testing, some amount of testing, or is it the Government’s intention that the production testing shall include all subparagraphs of 4.5?

Government Response: Testing shall be in accordance with PD10WRGBGBEC14, subparagraph 4.5.1, Examination of product.

Question 2: Will the Government consider an extension of the bid date from March 8, 2012, to March 23, 2012.

Government Response: The Government will not extend the closing date of 8 March 2012 at this time as no requirements have changed.

Matlock/WR-ALC/GRVKBB

File details come from the government source that posted it. Updated .