GPM Draft CLIN Schedule.xlsx
XLSX spreadsheet 33 KB Posted
- Attached to
- 72kW Ground Power Units (GPU) Federal contract opportunity
- Solicitation number
- FA8532-21-R-72GPU
About this file
This document outlines a draft contract line item number (CLIN) schedule for a 72kW Ground Power Unit (GPU) contract opportunity with the Department of the Air Force Materiel Command Lifecycle Management Center. The CLIN schedule includes line items for development, production, and sustainment of 144kW GPUs, 72kW GPUs, and universal load banks over multiple contract periods and option years. Key requirements include first article units and non-recurring engineering for development in the basic contract period, low-rate initial production lots in Option Period I, and full-rate production in Option Periods II through VII with quantities ranging from 63 to 480 units per CLIN. Supporting CLINs cover data, travel, conferences, spare parts and engineering changes.
View the file
Other files for this federal contract opportunity
Show all 50
72kW Ground Power Units (GPU) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Draft CLIN Schedule CLIN Description QTY/BEQ Unit of Issue (U/I Notes
OWENS, BRANDI R GS-13 USAF AFMC AFLCMC/WNKAA: OWENS, BRANDI R GS-13 USAF AFMC AFLCMC/WNKAA:
First submittal OWENS, BRANDI R GS-13 USAF AFMC AFLCMC/WNKAA: OWENS, BRANDI R GS-13 USAF AFMC AFLCMC/WNKAA:
This is the time we have to send approval or disapproval with comments to the contractor.
OWENS, BRANDI R GS-13 USAF AFMC AFLCMC/WNKAA: OWENS, BRANDI R GS-13 USAF AFMC AFLCMC/WNKAA:
| This is how long the contractor will have to resubmit based on disapproval comments | BASIC CONTRACT PERIOD (24 MONTHS) | ||||
| Group A | |||||
| 0001 | 144kW GPU First Article | ||||
| 0001AA | First Article Units | 6 | EA | ||
| 0001AB | NRE against CLIN 0001AA, to include testing costs | 1 | LO | ||
| 0002 | 72kW GPU First Article | ||||
| 0002AA | First Article Units | 6 | EA | ||
| 0002AB | NRE against CLIN 0002AA, to include testing costs | 1 | LO | ||
| 0003 | Universal Load Bank First Article | ||||
| 0003AA | First Article Units | 8 | EA | ||
| 0003AB | NRE against CLIN 0003AA, to include testing costs | 1 | LO | ||
| 0004 | DATA | ||||
| 0004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | NSP | |||
| 0004AB | CONFERENCE AGENDA (A002) | NSP | |||
| 0004AC | CONFERENCE MINUTES (A003) | NSP | |||
| 0004AD | TECHNICAL REPORT-STUDY SERVICES (B001) | ||||
| 0004AE | SYSTEM SAFETY PROGRAM PLAN (C001) | NSP | |||
| 0004AF | SYSTEM SAFETY HAZARD ANALYSIS REPORT (C002) | NSP | |||
| 0004AG | CORROSION PREVENTION AND CONTROL PLAN (C003) | NSP | |||
| 0004AH | COUNTERFEIT PROTECTION PLAN (C004) | NSP | |||
| 0004AJ | TECHNICAL REPORT - STUDY SERVICES (CYBERSECURITY ANALYSIS) (C005) | NSP | |||
| 0004AK | RISK MANAGEMENT FRAME (RMF) (C006) | NSP | |||
| 0004AL | SOFTWARE ASSURANCE EVALUATION REPORT (SAER) (C007) | NSP | |||
| 0004AM | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | NSP | |||
| 0004AN | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | NSP | |||
| 0004AP | LOGISTICS PRODUCT DATA (C010) | ||||
| 0004AQ | ENGINEERING DATA FOR PROVISIONING (C011) | ||||
| 0004AR | AIR FORCE TECHNICAL MANUAL CONTRACT REQUIREMENTS - Group A (D001) | ||||
| 0004AS | TRAINING MATERIAL (D002) | ||||
| 0004AT | PACK-UP DATA (D003) | ||||
| 0004AU | TECHNICAL REPORT - STUDY SERVICES (DESIGN ANALYSIS) (E001) | ||||
| 0004AV | FIRST ARTICLE TEST PLAN (E002) | ||||
| 0004AW | FIRST ARTICLE TEST PROCEDURE (E003) | ||||
| 0004AX | TEST-INSPECTION REPORT (FIRST ARTICLE TEST REPORT) (E004) | ||||
| 0004AY | TEST-INSPECTION REPORT (72kW FIRST CONNECT TEST REPORT) (E005) | ||||
| 0004AZ | TEST-INSPECTION REPORT (144kW FIRST CONNECT TEST REPORT) (E006) | ||||
| 0004BA | TEST-INSPECTION REPORT (ULB FIRST CONNECT TEST REPORT) (E007) | ||||
| 0004BB | PRODUCTION ACCEPTANCE TEST PROCEDURE (E008) | NSP | |||
| 0004BC | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | NSP | |||
| 0004BD | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | TBN | |||
| 0004BE | NOTICE OF REVISION (NOR) (F002) | NSP | |||
| 0004BF | REQUEST FOR VARIANCE (RFV) (F003) | NSP | |||
| 0005 | Travel | 1 | LO | ||
| 0006 | Post Award Conference, to Include Provisioning Guidance Conference, Technical Order Guidance Conference | 1 | LO | ||
| Group B | |||||
| 0007 | 72kW GPU First Article | ||||
| 0007AA | First Article Units | 6 | EA | ||
| 0007AB | NRE against CLIN 0001AA, to include testing costs | 1 | LO | ||
| 0008 | DATA | ||||
| 0008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP | |
| 0008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP | |
| 0008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP | |
| 0008AD | TECHNICAL REPORT-STUDY SERVICES (TRR) (B001) | 1 | LO | NSP | |
| 0008AE | SYSTEM SAFETY PROGRAM PLAN (C001) | 1 | LO | NSP | |
| 0008AF | SYSTEM SAFETY HAZARD ANALYSIS REPORT (C002) | 1 | LO | NSP | |
| 0008AG | CORROSION PREVENTION AND CONTROL PLAN (C003) | 1 | LO | NSP | |
| 0008AH | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP | |
| 0008AJ | TECHNICAL REPORT - STUDY SERVICES (CYBERSECURITY ANALYSIS) (C005) | 1 | LO | NSP | |
| 0008AK | RISK MANAGEMENT FRAMEWORK (RMF) (C006) | 1 | LO | NSP | |
| 0008AL | SOFTWARE ASSURANCE EVALUATION REPORT (SAER) (C007) | 1 | LO | NSP | |
| 0008AM | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP | |
| 0008AN | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP | |
| 0008AP | LOGISTICS PRODUCT DATA (C010) | 1 | LO | ||
| 0008AQ | ENGINEERING DATA FOR PROVISIONING (C011) | 1 | LO | ||
| 0008AR | AIR FORCE TECHNICAL MANUAL CONTRACT REQUIREMENTS - Group B (D001) | 1 | LO | ||
| 0008AS | TRAINING MATERIAL (D002) | 1 | LO | ||
| 0008AT | PACK-UP DATA (D003) | 1 | LO | ||
| 0008AU | TECHNICAL REPORT - STUDY SERVICES (DESIGN ANALYSIS) (E001) | 1 | LO | ||
| 0008AV | FIRST ARTICLE TEST PLAN (E002) | 1 | LO | ||
| 0008AW | FIRST ARTICLE TEST PROCEDURE (E003) | 1 | LO | ||
| 0008AX | TEST-INSPECTION REPORT (FIRST ARTICLE TEST REPORT) (E004) | 1 | LO | ||
| 0008AY | TEST-INSPECTION REPORT (72kW FIRST CONNECT TEST REPORT) (E005) | 1 | LO | ||
| 0008AZ | PRODUCTION ACCEPTANCE TEST PROCEDURE (E008) | 1 | LO | ||
| 0008BA | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | ||
| 0008BB | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN | |
| 0008BC | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP | |
| 0008BD | REQUEST FOR VARIANCE (RFV) (F003) | NSP | |||
| 0009 | Travel | 1 | LO | ||
| 0010 | Post Award Conference, to Include Provisioning Guidance Conference, Technical Order Guidance Conference | 1 | LO |
| OPTION PERIOD I (12 MONTHS) LRIP | ||||
| Group A | ||||
| 1001 | 144kW GPU Production Units | 63 | EA | |
| 1002 | 72kW GPU Production Units | 120 | EA | |
| 1003 | Universal Load Bank Production Units | 59 | EA | |
| 1004 | DATA | |||
| 1004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 1004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 1004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 1004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 1004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 1004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 1004AG | PACK-UP DATA (D003) | 1 | LO | |
| 1004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 1004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 1004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 1004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 1005 | Travel | 1 | LO | |
| 1006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 1007 | 72kW GPU Production Units - LRIP | 120 | EA | |
| 1008 | DATA | |||
| 1008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 1008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 1008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 1008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 1008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 1008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 1008AG | PACK-UP DATA (D003) | 1 | LO | |
| 1008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 1008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 1008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 1008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 1009 | Travel | 1 | LO | |
| 1010 | LRU Spares | 1 | LO | TBN |
| OPTION PERIOD II (12 MONTHS) Full-rate | ||||
| Group A | ||||
| 2001 | 144kW GPU Production Units | 63 | EA | |
| 2002 | 72kW GPU Production Units | 480 | EA | |
| 2002AA | Option Period Guarantee Qty | 120 | EA | |
| 2002AB | Option Period Competitive Qty | 240 | EA | |
| 2003 | Universal Load Bank Production Units | 59 | EA | |
| 2004 | DATA | |||
| 2004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 2004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 2004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 2004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 2004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 2004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 2004AG | PACK-UP DATA (D003) | 1 | LO | |
| 2004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 2004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 2004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 2004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 2005 | Travel | 1 | LO | |
| 2006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 2007 | 72kW GPU Production Units | 480 | EA | |
| 2007AA | Option Period Guarantee Qty | 120 | EA | |
| 2007AB | Option Period Competitive Qty | 240 | EA | |
| 2008 | DATA | |||
| 2008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 2008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 2008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 2008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 2008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 2008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 2008AG | PACK-UP DATA (D003) | 1 | LO | |
| 2008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 2008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 2008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 2008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 2009 | Travel | 1 | LO | |
| 2010 | LRU Spares | 1 | LO | TBN |
| OPTION PERIOD III (12 MONTHS) | ||||
| Group A | ||||
| 3001 | 144kW GPU Production Units | 63 | EA | |
| 3002 | 72kW GPU Production Units | 480 | EA | |
| 3002AA | Option Period Guarantee Qty | 120 | EA | |
| 3002AB | Option Period Competitive Qty | 240 | EA | |
| 3003 | Universal Load Bank Production Units | 59 | EA | |
| 3004 | DATA | |||
| 3004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 3004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 3004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 3004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 3004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 3004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 3004AG | PACK-UP DATA (D003) | 1 | LO | |
| 3004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 3004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 3004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 3004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 3005 | Travel | 1 | LO | |
| 3006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 3007 | 72kW GPU Production Units | 480 | EA | |
| 3007AA | Option Period Guarantee Qty | 120 | EA | |
| 3007AB | Option Period Competitive Qty | 240 | EA | |
| 3008 | DATA | |||
| 3008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 3008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 3008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 3008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 3008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 3008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 3008AG | PACK-UP DATA (D003) | 1 | LO | |
| 3008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 3008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 3008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 3008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 3009 | Travel | 1 | LO | |
| 3010 | LRU Spares | 1 | LO | TBN |
| OPTION PERIOD IV (12 MONTHS) | ||||
| Group A | ||||
| 4001 | 144kW GPU Production Units | 55 | EA | |
| 4002 | 72kW GPU Production Units | 480 | EA | |
| 4002AA | Option Period Guarantee Qty | 120 | EA | |
| 4002AB | Option Period Competitive Qty | 240 | EA | |
| 4003 | Universal Load Bank Production Units | 59 | EA | |
| 4004 | DATA | |||
| 4004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 4004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 4004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 4004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 4004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 4004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 4004AG | PACK-UP DATA (D003) | 1 | LO | |
| 4004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 4004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 4004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 4004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 4005 | Travel | 1 | LO | |
| 4006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 4007 | 72kW GPU Production Units | 480 | EA | |
| 4007AA | Option Period Guarantee Qty | 120 | EA | |
| 4007AB | Option Period Competitive Qty | 240 | EA | |
| 4008 | DATA | |||
| 4008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 4008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 4008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 4008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 4008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 4008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 4008AG | PACK-UP DATA (D003) | 1 | LO | |
| 4008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 4008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 4008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 4008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 4009 | Travel | 1 | LO | |
| 4010 | LRU Spares | 1 | LO | TBN |
| OPTION PERIOD V (12 MONTHS) | ||||
| Group A | ||||
| 5001 | 144kW GPU Production Units | 0 | EA | |
| 5002 | 72kW GPU Production Units | 480 | EA | |
| 5002AA | Option Period Guarantee Qty | 120 | EA | |
| 5002AB | Option Period Competitive Qty | 240 | EA | |
| 5003 | Universal Load Bank Production Units | 56 | EA | |
| 5004 | DATA | |||
| 5004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 5004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 5004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 5004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 5004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 5004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 5004AG | PACK-UP DATA (D003) | 1 | LO | |
| 5004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 5004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 5004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 5004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 5005 | Travel | 1 | LO | |
| 5006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 5007 | 72kW GPU Production Units | 480 | EA | |
| 5007AA | Option Period Guarantee Qty | 120 | EA | |
| 5007AB | Option Period Competitive Qty | 240 | EA | |
| 5008 | DATA | |||
| 5008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 5008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 5008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 5008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 5008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 5008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 5008AG | PACK-UP DATA (D003) | 1 | LO | |
| 5008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 5008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 5008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 5008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 5009 | Travel | 1 | LO | |
| 5010 | LRU Spares | 1 | LO | TBN |
| OPTION PERIOD VI (12 MONTHS) | ||||
| Group A | ||||
| 6001 | 144kW GPU Production Units | 0 | EA | |
| 6002 | 72kW GPU Production Units | 480 | EA | |
| 6002AA | Option Period Guarantee Qty | 120 | EA | |
| 6002AB | Option Period Competitive Qty | 240 | EA | |
| 6003 | Universal Load Bank Production Units | 0 | EA | |
| 6004 | DATA | |||
| 6004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 6004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 6004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 6004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 6004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 6004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 6004AG | PACK-UP DATA (D003) | 1 | LO | |
| 6004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 6004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 6004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 6004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 6005 | Travel | 1 | LO | |
| 6006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 6007 | 72kW GPU Production Units | 480 | EA | |
| 6007AA | Option Period Guarantee Qty | 120 | EA | |
| 6007AB | Option Period Competitive Qty | 240 | EA | |
| 6008 | DATA | |||
| 6008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 6008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 6008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 6008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 6008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 6008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 6008AG | PACK-UP DATA (D003) | 1 | LO | |
| 6008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 6008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 6008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 6008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 6009 | Travel | 1 | LO | |
| 6010 | LRU Spares | 1 | LO | TBN |
| OPTION PERIOD VII (12 MONTHS) | ||||
| Group A | ||||
| 7001 | 144kW GPU Production Units | 0 | EA | |
| 7002 | 72kW GPU Production Units | 276 | EA | |
| 7002AA | Option Period Guarantee Qty | 69 | EA | |
| 7002AB | Option Period Competitive Qty | 138 | EA | |
| 7003 | Universal Load Bank Production Units | 0 | EA | |
| 7004 | DATA | |||
| 7004AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 7004AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 7004AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 7004AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 7004AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 7004AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 7004AG | PACK-UP DATA (D003) | 1 | LO | |
| 7004AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 7004AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 7004AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 7004AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 7005 | Travel | 1 | LO | |
| 7006 | LRU Spares | 1 | LO | TBN |
| Group B | ||||
| 7007 | 72kW GPU Production Units | 276 | EA | |
| 7007AA | Option Period Guarantee Qty | 69 | EA | |
| 7007AB | Option Period Competitive Qty | 138 | EA | |
| 7008 | DATA | |||
| 7008AA | CONTRACTOR'S PROGRESS, STATUS AND MANAGEMENT REPORT (A001) | 1 | LO | NSP |
| 7008AB | CONFERENCE AGENDA (A002) | 1 | LO | NSP |
| 7008AC | CONFERENCE MINUTES (A003) | 1 | LO | NSP |
| 7008AD | COUNTERFEIT PROTECTION PLAN (C004) | 1 | LO | NSP |
| 7008AE | COMPUTER PROGRAM IDENTIFICATION NUMBER CATALOG INFORMATION (C008) | 1 | LO | NSP |
| 7008AF | COMPUTER SOFTWARE PRODUCT END ITEMS (C009) | 1 | LO | NSP |
| 7008AG | PACK-UP DATA (D003) | 1 | LO | |
| 7008AH | TEST-INSPECTION REPORT (PRODUCTION ACCEPTANCE TEST REPORT) (E009) | 1 | LO | NSP |
| 7008AJ | ENGINEERING CHANGE PROPOSAL (ECP) (F001) | 1 | LO | TBN |
| 7008AK | NOTICE OF REVISION (NOR) (F002) | 1 | LO | NSP |
| 7008AL | REQUEST FOR VARIANCE (RFV) (F003) | 1 | LO | NSP |
| 7009 | Travel | 1 | LO | |
| 7010 | LRU Spares | 1 | LO | TBN |
Acronym List
| Acronym | Spelled out |
| BEQ | Best Estimated Quantity |
| EA | Each |
| GPU | Ground Power Unit |
| kW | kilo-Watt |
| LO | Lot |
| LRIP | Low-Rate Initial Production |
| LRU | Line Replaceable Unit |
| QTY | Quantity |
| NRE | Non-Recurring Engineering |
| NSP | Not Separately Priced |
| TBN | To Be Negotiated |
File details come from the government source that posted it. Updated .