This document provides a timeline and testing schedule for the Ground Power Modernization program. It outlines the key milestones for the 72kW Ground Power Units solicitation, including a contract award date within 30 days of the pre-award conference. First article testing is required to begin no later than 330 days after award and be completed within 850 days, with monthly interim reports. Final testing reports are due 940 days after award. The schedule also specifies prerequisite and phase testing requirements for the 72kW and 144kW Ground Power Units as well as 144kW Unit Load Banks to be conducted at various military bases between 330 to 850 days after award. The soliciting agency is the Department of the Air Force Materiel Command Lifecycle Management Center located at Robins Air Force Base.
View the file
Other files for this federal contract opportunity
Show all 50
72kW Ground Power Units (GPU) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ground Power Modernization (GPM) Pre-Solicitation Conference Attachment 2
25-26 Aug 21
Controlled by: AFLCMC/WN Controlled by: AFLCMC/WNZ CUI Category: CUI PROCURE Distribution/Dissemination Controls: FEDCON POC: Brandi Owens, (478) 222-1910
Relious “Rick” Grant Program Manager/AFLCMC/WNZ Brandi Owens Contracting Officer/AFLCMC/WNKAA
CUI
AFLCMC… Providing the Warfighter’s Edge
GPM Basic Contract Period of Performance
CUI
CUI
SOW 3.3.2, 3.5.1 and 3.5.2.1
SOW 3.3.3.2
SOW 3.2.4, monthly status reporting begins 5th day of the first month ARO
Multiple CDRLs due 30 and 15 days prior to PDR, with updates required for all future design and readiness reviews
SOW 3.3.4, Program Management Reviews to be held quarterly, at a minimum
SOW 3.6.2.1
SOW 3.3.3.2
SOW 3.6.2.2
Contract Award
PAC, TO Guidance Conference, Provisioning Guidance Conference (NLT 30 days ARO)
PDR (90 days ARO)
CDR (180 days ARO)
CDRL E002 First Article Test Plan (120 days ARO)
CDRL E002 First Article Test Procedures (240 days ARO)
CUI
SOW 3.6.2.3.1, the contractor shall notify the procuring activity of the date, time, and location of testing 21 days prior to the start of any formal (non-preliminary) testing
SOW 3.6.2.4 Monthly Interim First Article Testing Reporting begin 360 days ARO
SOW 1, the Government intends to issue initial production orders within the basic contract period that will begin Low-Rate Initial Production (LRIP). Anticipated to occur after successful production readiness review(s)
SOW 3.6.2.3
SOW 3.6.2.3
and all subparas
SOW 3.6.2.4
SOW 3.8
SOW 1
GPM Basic Contract Period of Performance, con’t
Phase One DT&E TRR (300 days ARO)
First Article Testing Begin (NLT 330 days ARO)
First Article Testing End (NLT 850 Days ARO)
Final First Article Test Report Delivered (NLT 940 days ARO)
Basic Contract Period End (1,095 days ARO)
Production Readiness Review (w/in 30 days FA unit approval)
LRIP Period
CUI
SOW 3.6.2.4 Monthly Interim First Article Testing Reporting begin 360 days ARO
SOW 3.6.2.3.5. Procuring activity approved 75-percent technical manuals are required to accompany phase three OT&E
SOW 3.6.2.3.7 and 3.6.2.3.7.1: All remaining Phase One DT&E, Environmental and Mobility testing can be conducted anytime between 330 days ARO and 850 days ARO; keep in mind, all testing is to be complete no later than 850 days ARO!
Phase Two B DT&E is combined with Phase Three OT&E
Tinker AFB location must be first location testing is started; other locations can be staggered 10 days apart (if testing done semi- concurrently) or 55 days apart (if testing done sequentially) SOW 3.6.2.3.1.1, 3.6.2.3.1.1.2, 3.6.2.3.4 and 3.6.2.3.4.2 SOW 3.6.2.3.3 and 3.6.2.3.3.2
SOW 3.6.2.3.3.2, 3.6.2.3.5 and 3.6.2.3.5.2
SOW 3.6.2.4
144 kW GPU Testing Schedule
First Article Testing Start (330 days ARO)
Phase One Prerequisite Testing Report Due; Phase Three Prerequisite Testing Complete (522 days ARO)
Phase Two B Testing Start; Phase Three Testing Start (580 days ARO)
First Article Testing End (850 days ARO)
Final First Article Report Due (940 days ARO)
CUI
72 kW GPU Testing Schedule SOW 3.6.2.4 Monthly Interim First Article Testing Reporting begin 360 days ARO
SOW 3.6.2.3.5. Procuring activity approved 75-percent technical manuals are required to accompany phase three OT&E
SOW 3.6.2.3.7 and 3.6.2.3.7.1: All remaining Phase One DT&E, Environmental and Mobility testing can be conducted anytime between 330 days ARO and 850 days ARO; keep in mind, all testing is to be complete no later than 850 days ARO!
Joint Base Charleston must be first Phase Three OT&E testing location; other locations can be staggered 10 days apart (if testing done semi-concurrently) or 55 days apart (if testing done sequentially) SOW 3.6.2.3.1.1 and 3.6.2.3.1.1.1
SOW
3.6.2.3.2 SOW 3.6.2.3.3.1 3.6.2.3.4 and 3.6.2.3.4.1 SOW 3.6.2.3.5 and 3.6.2.3.5.1
SOW
3.6.2.4
Phase One Prerequisite Testing Report Due (400 days ARO)
Phase Two B Testing End; Phase Three Prerequisite Testing End (522 days ARO)
Phase Two A Testing End (457 days ARO)
Phase Three Testing Begin (580 days ARO)
CUI
144 kW ULB Testing Schedule SOW 3.6.2.4 Monthly Interim First Article Testing Reporting begin 360 days ARO
SOW 3.6.2.3.5. Procuring activity approved 75-percent technical manuals are required to accompany phase three OT&E
SOW 3.6.2.3.7 and 3.6.2.3.7.1: All remaining Phase One DT&E, Environmental and Mobility testing can be conducted anytime between 330 days ARO and 850 days ARO; keep in mind, all testing is to be complete no later than 850 days ARO!
One way to look at testing schedule for the 144 kW ULB: Each testing location for the two GPUs will also have ULBs onsite!
Phase Three OT&E testing schedule aligns with both 144 kW GPU and 72 kW GPU testing schedules on previous slides, even with the legacy testing requirements Only difference is the addition of Barksdale AFB for testing with the B-52 aircraft; this can be accomplished anytime after Phase Three OT&E TRR
SOW 3.6.2.3.1.1
3.6.2.3.1.1.3 SOW 3.6.2.3.3, 3.6.2.3.3.3, 3.6.2.3.4, and 3.6.2.3.4.3 SOW 3.6.2.3.5, 3.6.2.3.5.3, 3.6.2.3.5.3.1 and 3.6.2.3.5.3.2
SOW 3.6.2.4
Phase One Prerequisite Testing Report Due (400 days ARO)
Phase Two B Testing End; Phase Three Prerequisite Testing End (522 days ARO)
Phase Three Testing Begin (580 days ARO) image7.png image3.jpeg image6.jpeg image4.png image1.jpeg image2.png image5.gif