Statement_of_Work,_Addendum_2_6_Jun_17.pdf

PDF 294 KB Posted

Attached to
Design-Build for Building 673 Federal contract opportunity
Solicitation number
FA8501-17-R-0005
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Statement of Work, Addendum 2

View the file

Other files for this federal contract opportunity

Other files attached to Design-Build for Building 673, newest first.
File Type Posted
FA8501-17-R-00050006.pdf PDF
FA8501-17-R-00050005.pdf PDF
160050_-_Contractor_RFI_Responses_(20170609).pdf PDF
FA8501-17-R-00050004.pdf PDF
Statement_of_Work,_Addendum_1.pdf PDF
Contractor_RFI_Responses_(20170524).pdf PDF
Contractor_RFI_Responses_(20170504).pdf PDF
160050_-_Contractor_RFI_Responses_(20170412).pdf PDF
FA8501-17-R-000503.pdf PDF
Contractor_RFI_Responses_(20170504).pdf PDF
FA8501-17-R-000502_(FINAL).docx DOCX document
FA8501-17-R-000501_(FINAL).docx DOCX document
Site_Visit_sign_in_sheet.pdf PDF
NOTE_TO_OFFERORS.pdf PDF
FA8501-17-R-0005,_Solicitation_(Final).docx DOCX document
Special_Warranty_Requirements_Letter.pdf PDF
App_C,_Industrial_Safety_and_Health_Requirements_14_Dec_16.pdf PDF
Base_Facility_Standards_23_Jun_14.pdf PDF
Submittal_Register.xlsx XLSX spreadsheet
B673_Utilities_Map.pdf PDF
Statement_of_Work_19_Jan_17.pdf PDF
Procedural_Guide_for_Designers_29_May_15.pdf PDF
B673_Drawings_10_Nov_16.pdf PDF
DBA_Wage_Determination_27_Jan_2017.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISION NO. 2 (ADDENDUM)

TO

PROJECT UHHZ160050

RPR/RENOV INTERIOR, SHED SUP EQUIP DEP, B/673

6 JUN 2017

Revision No. 2 consists of a revision to identify the equipment to be installed by the Govt.

(sanding booth and vacuum) requiring electrical and HVAC support. Specifically, incorporate the items listed below:

Item No. 1: Remove Section 01005 from the Specifications and replace with the attached revised section 01005 dated 9 Jun 2017.

END OF ADDENDUM

UHHZ160050 ___ STATEMENT OF WORK - 01005

Addendum 1, 5 May 2017

Addendum 2, 9 Jun 2017

Statement of Work

PART 1 – GENERAL

1.01 STATEMENT OF WORK: This is a general overview of the Design-Build project. Also see

Section 01020, Construction Design and Performance Requirements, and 01030, Design after Award.

A. Location: Accomplish work at Robins AFB, Georgia

B. Price: The original contracted price shall include special work times for utility outages and repair of damages.

C. Contract Documents: Follow details shown by the specifications and drawings, current version of the Robins AFB Facility Standards, UFCs, ETLs, applicable UFGS sections and building code requirements.

D. Liquidated Damages will be applicable for this task order. If the contractor fails to complete the work within the time specified in the contract, the Contractor shall pay Liquidated Damages to the Government in the amount of $332.99 for the first day of delay, and $269.02 per day for each subsequent calendar day of delay until the work is completed or accepted.

E. Design Phase Requirement: North wing of building will be vacated during construction, but south wing shall be in full operation. Contractor shall identify all hazards during the design phase that may have an adverse effect on building occupants, equipment, building systems, etc.

in the south wing during the construction phase. (For example: Project that includes working on roof over occupied space: cutting insulation, replacement of existing screws can cause dust particulates and other airborne particles that may be a hazard for personnel and/or equipment below.) Contractor shall provide design to contain all hazards to building occupants, equipment, building systems, etc. for contractor to utilize during the construction phase.

F. Project Scope, Objectives and Criteria: This is a Design-Build contract for both Design and

Construction. The general scope of the work includes the following:

1. Scope:

a. General Scope: Renovate north section of Bldg. 673 to accommodate C5 noseplug workload. No renovations are required for the south end except for tie-ins and lightning protection. Roof and wall panel work shall be limited to the north section with transitions as required to tie into the south section. Lightning protection work shall be for the entire building. Work requiring utility outages shall be confined to non-standard working times (nights and/or weekends) to prevent disruptions to flash jet operations. Provide all additional work as required for a functional usable facility.

b. Existing Conditions: Bldg. 673 is a pre-engineered metal building consisting of two wings. The north wing, constructed in 1999 (Star Building Systems), is

UHHZ160050 ___ STATEMENT OF WORK - 01005

currently used as a warehouse and is the area for renovation. The south wing, later constructed in 2012 (manufacturer unknown), is currently used as a production area for flash-jet operations. The roofs are nominal 3” high trapezoidal standing seam roof (mechanically seamed) with vinyl faced batt insulation. Both roofs have different pitches. Walls are metal PBR panels with vinyl faced batt insulation. The south wall (common wall with flashjet) consists of the original metal girts with metal wall panels. The overhead doors in the south wall have been removed and filled with plywood and battens.

Roof and wall insulation at the north wing has sustained water damage (with mold) primarily at the eaves and needs to be removed. Roof panels on the north wing have probably also been damaged (hidden) as a result.

c. Abatement of Hazardous Materials: North end of building has been used for storage since originally constructed. No asbestos is expected due to the age of the building (built 1999). Mold has visually been identified in some of the insulation.

Although not expected, there may also be small traces of heavy metals. For this reason, wipe samples will be performed within the renovation area, tested for heavy metals and a report provided. Perform mold removal when removing insulation and cleaning the steel. Contractor shall take necessary precautions for worker protection during construction. Heavy metal abatement, if identified as required during the renovation by the report, shall be considered as unforseen conditions and negotiated accordingly.

d. Demolition:

1) Remove existing handicap ramp within the building and patch slab as required for a smooth surface.

2) Remove existing metal roof, roof accessories, roof insulation and lightning protection for the north wing. Remove lightning protection on the south wing. During design, test existing counterpoise to verify continuity and maximum resistance to ground for recertification. Issues in the existing counterpoise will be considered as unforseen conditions.

3) Remove north building exterior wall panels, exhaust fan, personnel door and one overhead door (northwest side). Remove north endwall structure and foundation as required to restructure for new overhead door and personnel door.

4) Remove wall insulation and wall panels for remaining walls on the renovation area (north section of building). This shall also include insulation on the south wall (common wall with flashjet area).

UHHZ160050 ___ STATEMENT OF WORK - 01005

5) Remove existing lighting. Remove existing electrical adjacent to the personnel door on the north endwall and relocate as necessary. Remove any other electrical that may interfere with the work and reinstall after work is completed. Remove any items that are not to be reused.

Contractor shall perform functional test of all circuits and components prior to removal. Components damaged during the work shall be replaced at no additional cost to the Govt.

6) Remove existing transformer and electrical feed from the air switch to the transformer. Outage for the removal and the installation of new transformer and feed shall not extend beyond 1 holiday weekend. The cost for this shall be separated out on the Bid Form. The old transformer will be delivered and unloaded at the CE electrical shop (coordinate with

CE inspector and CE electrical shop (Billy Bandy)).

7) Remove existing eyewash fountain/shower.

8) Remove sufficient existing floor slab and exterior pavements as required for the installation of new plumbing and sanitary sewer.

9) Remove existing pavements as required for new ramps. Remove tops of existing vehicle ramp retaining walls and railings as required to allow the new ramp surface to flush with the adjacent ramp surfaces. Clean surfaces of existing concrete ramps and abutting retaining walls to remain.

10) Remove existing sanitary sewer as required for the ramps.

11) Remove all existing intake louvers, exhaust fans and heaters. Close openings left from the removal of louvers and exhaust fan with metal wall panels, framing and insulation (provide all required flashings).

12) Clean existing structural components (both main and secondary structural steel members) in Production Area. Cleaning shall remove mold from steel components and residual dust, but shall not damage existing paint.

Method for cleaning shall be determined by the design AE and testing performed in an inconspicuous area to confirm method. Protect all existing work to remain from damage (method shall be determined by contractor). Contractor will touch-up small areas damaged with paint to match existing (not to exceed 10%).

13) Remove existing pavement on the east side as required to install new

Mechanical Room landing and steps. Removal shall include pavements requiring re-sloping to prevent ponding adjacent to new ramps and steps.

UHHZ160050 ___ STATEMENT OF WORK - 01005

14) Remove existing pavement on the west side of the building sufficient for installation of the new handicap ramp, canopy and north vehicle ramp.

15) Clean and remove paint at existing metal railings at vehicle ramps and all existing bollards adjacent to renovated area (interior and exterior).

Provide smooth surface properly prepared for repainting.

16) Provide all additional work required for demolition of miscellaneous items as shown on the drawings and in conjunction with the overall work scope.

Also include all work as required for Option 1.

e. New Work:

1) Construct new concrete vehicle ramp on north end of building (infill between two existing ramps). Surface of new ramp shall flush with surfaces of existing ramps on both sides.

2) Install new concrete handicap ramp with metal railings and awning on west side. Ramp and railings shall meet IBC and ABA codes. Awning shall meet the same requirements as the building structure and roof.

3) Install new concrete landing, steps and metal railings on east side of building at Mechanical Room.

4) Construct new PPE and Personal Locker rooms within the building. New rooms will include heat, cooling, lighting, electrical, plumbing

(w/fixtures), fire alarm (incl. strobes/horns) and fire suppression. Rooms will have lay-in ceiling with cleanable fiberglass panels. Roof of rooms shall be metal purlins with prefinished PBR metal roof panels and trim

(provide flashing for weathertight system). Paint all exposed surfaces.

Fire alarm and suppression shall be connected to existing system.

Construction shall be properly sealed to allow for required positive and/or negative pressures (see also Section 01020).

5) Install new fire suppression and fire alarm components as required for the work. Overall life safety design shall be performed by a registered Fire

Protection Engineer (FPE). Fire alarm and fire suppression systems shall be designed by a NICET IV professional.

6) Fire suppression pressure and flow rate are not available at this time.

Currently, a project is in process to install new holding tanks and pumps to supply this building and several others in the area. This will be complete

UHHZ160050 ___ STATEMENT OF WORK - 01005

within the next 2 months and these values will be available for design.

For bidding purposes, assume providing lines to the PPE room, Locker room and sanding booth directly from the sprinkler riser. Sprinkler line to the sanding booth will be stubbed and capped at the booth.

7) Install new overhead and underground plumbing as required to service new plumbing fixtures. Patch concrete slab and pavements as required to match existing.

8) Install new metal roof (approx. 6,000 sf), substructure (to match existing south roof slope), roof accessories and insulation. All roof insulation shall have exposed white PSKP scrim. Substructure shall be painted to match existing structural steel.

9) Install new wall panels and insulation on renovated north section of building (3 exterior walls). Install new wall insulation on south wall

(common wall with flashjet). All wall insulation shall have exposed white

PSKP scrim. Although not anticipated, contractor shall provide any additional elements required for the south wall for fire protection (to be determined by FPE). No fire rating is required for tenant separation.

10) Install complete lightning protection system for both the north and south wings. System shall comply with NFPA 780 and the BFS. Installation shall have 3rd party certification.

11) Install new north building exterior endwall components (structural, siding, insulation, trim, etc.) and footings to accommodate new overhead and personnel doors.

12) Install new overhead coiling door and personnel door on north end of building. Door shall have electric operator, safety devices, push-button

(momentary contacts) controller, hood and be factory prefinished.

13) Install new HVAC system for the Production Area. System shall be DX heat pump system with supplemental electric heating strips. Provide ductwork as required to evenly distribute conditioned air throughout the area.

Process equipment will consist of a sanding booth and vacuum system.

There will be no other equipment used other than standard handheld power tools. The vacuum system is rated at 21.7 A @ 120/208V 3ph.

The motor horsepower for the sanding booth heat load is not known, but the electrical requirements are shown in Item #14 below. The equipment

UHHZ160050 ___ STATEMENT OF WORK - 01005

consists of the following components: 7 compartment sanding booth with individual exhaust fans, 14 – fluorescent lights within the booth and 1 vacuum system for sanding.

14) Install new electrical as required for work scope. Electrical shall include, but not be limited to power, lighting (including new fixtures and lamps) and communications. Communications will include 1 phone and 2 data for 2 locations within the storage area (in the vicinity of the sanding booth).

Equipment to be installed will only include a sanding booth and vacuum system (Govt. furnished, Govt. installed (GFGI)). Sanding booth consists of 7 sections, each with a separate exhaust fan. Fans are supplied with 1 –

277/480V 3Ph circuit, 30A. Vacuum system (provides vacuum to interior of sanding booth for sanders) requires 277/480V 3ph 100A circuit supplying a 75KVA transformer. The transformer will be GFGI. Note that although the vacuum system only draws 21.7 A @ 120/208V, the circuit will be sized for the transformer. Contractor requirements will be to provide 2 circuits with circuit breakers and junction boxes to feed the sanding booth and vacuum system.

15) Install new transformer and electrical feed from the air switch to the transformer. Transformer shall be sized to handle both the existing and new building loads meeting the requirements of the National Electrical

Safety Code and NEC as applicable (minimum 750 KVA). Rework service entrance (including conductors and conduit) to provide a single feed from the transformer to a new main distribution panel with main breaker and subpanel breakers to feed the existing 2 main service panelboards (taps/wiring troughs not allowed). The cost for the transformer and air switch feeds shall be separated out on the Bid Form

(remainder of items will be in main work scope).

16) Relocate existing sanitary sewer as required for ramps. Provide manholes at each change of direction and at intervals required by the BFS and plumbing codes.

17) Install new emergency eyewash/shower. Unit shall be CSA certified to meet ANSI Z358.1 with water and drain connections.

18) Patch and repair all damage to existing pavements, including any re-sloping necessary to prevent ponding adjacent to new ramps and steps

(replace with like material).

UHHZ160050 ___ STATEMENT OF WORK - 01005

19) Install new bollards to protect HVAC equipment, awning supports and overhead door jambs. Bollards shall be painted 6” steel pipe, concrete filled.

20) Repaint existing interior (in Production Area) and exterior bollards and railings (adjacent to Production Area).

21) Painting shall be 3 coat systems, industrial alkyd enamel for steel and high performance acrylic enamel for CMU. Provide block filler for CMU.

22) Provide all additional work required for a complete renovation as shown on the drawings and in conjunction with the overall work scope. Also note items required for Option 1.

G. Bid Schedule and Options:

1. Base Bid: Provide all work listed. Cost of replacing the transformer and feed from air switch shall be listed separately on the Bid Form.

2. Option 1: Paint exposed existing primary and secondary structural components in the

Production Area. Perform proper surface preparation as required for the new coatings.

H. Project Requirements:

1. The contractor shall provide the technical knowledge and skill necessary to perform services to meet standards set forth in this Statement of Work for base facilities, equipment and systems and at a minimum meet manufacturer’s requirements. The A-E firm used will employ sufficient registered professional architects and engineers (registered in the State of Georgia) as required to cover disciplines needed for the project scope involved. Design professionals will attend the Kick-off Meeting, Preliminary Design (60%) and First Final Design meetings at a minimum.

2. All stored equipment shall be stored and protected in accordance with manufacturer’s printed instructions.

3. This project will require daily reports to be filled out daily and submitted to the project manager on a weekly basis. Daily reports at a minimum shall contain the following information, Amount and type of work accomplished

Materials delivered to the site

Weather conditions and impact to work and schedule

Labor workforces on site

Construction equipment on site

Safety inspection performed and violations noted

Any outstanding issues, i.e. delays, RFIs, etc.

UHHZ160050 ___ STATEMENT OF WORK - 01005

4. All items shall be installed in accordance with the manufacturer’s printed installation instructions unless the Base Facility Standards, specifications, drawings, contract clauses, schedule, attachments, manufacturer’s requirements, and other contract documents are more stringent. The most stringent requirement shall be met at no additional cost to the Government.

If meeting the more stringent requirement will void the manufacturer’s warranty the contractor shall notify the Contracting Officer and the inspector prior to voiding the warranty.

5. Coordination shall be required between different disciplines.

I. Evacuation: Before fencing off the construction area, notify the Contracting Officer in writing 30 days before ready to start so that Contracting Officer’s Representative and Project

Manager can notify appropriate personnel.

J. Physical Security:

1. The contractor shall be responsible for safeguarding all government personnel and property being modified or adjacent to the new work. The contractor shall identify any existing problems in writing prior to start work.

2. At the close of each work day, all government facilities, equipment, and materials shall be secured and back in operation unless agreed on prior to the work starting. The contractor shall be responsible for controlling access into an area that has been turn over to them for construction.

K. Contractor Operations: Comply with Occupational Safety and Health Administration

(OSHA), Corps of Engineers Safety Manual (EM 385-1-1), the contract safety provisions will be listed in the Appendix ‘C’, Air Force Occupational Safety and Health (AFOSH) Standards, and

National Fire Protection Association (NFPA) standards.

1. Contractor Employees:

a. Compliance with OSHA and other applicable laws and regulations for the protection of contractor employees is the obligation of the contractor.

b. The contractor shall furnish to each of his/her employees a place of employment that is free from recognized hazards.

c. The contractor shall brief his/her employees on the safety requirements of this contract and on hazards associated with prescribed tasks.

d. This contract shall in no way require persons to work in surroundings or under working conditions that are unsafe or dangerous to their health.

e. The contractor must coordinate and perform work so as not to impact the safety of government employees or cause damage to government property.

f. This requires providing personnel with protective equipment and associated safety equipment as may be necessary.

UHHZ160050 ___ STATEMENT OF WORK - 01005

g. The contractor must also protect government personnel from hazards generated by the work.

2. Contractor Badges: All employees to enter Robins AFB shall have government provided badges. Contact the Project Manager/Badging Agent for the current badge application form. Badge request shall be submitted a minimum of 10 days prior to the employee’s arrival.

All badges shall be returned to the Project Manager/Badging Agent at the end of the contract or pay a $50.00 fine.

3. Fire Reporting:

a. Brief all workers and subcontractors as to the location of telephone and fire alarm pull stations.

b. Report all fires as soon as discovered. The fire reporting number for on Base phones is 911. The fire reporting number for off Base phones is 478-222-2900. The caller should give his or her name and location of what is on fire. Also, give any other information that may be requested by the Fire Department dispatcher. Stay on the telephone until the dispatcher has obtained all necessary information.

4. Work shall be performed to, but not be limited to, the requirements set forth by the following:

a. Robins AFB – Base Facility Standards (last edition)

b. Occupational Safety and Health Administration (OSHA)

c. All other applicable federal, state and local codes to ensure the system(s) are installed in accordance with manufacturer’s specifications.

d. Air Force Occupational Safety and Health (AFOSH)

e. National Fire Protection Association

f. UFC 3-600-01 – Fire Protection Engineering for Facilities

g. The contractor shall perform all work to conform to the standards of the government listed in paragraph above and per manufacturer specifications/ requirements.

h. Equipment and materials provided by the contractor shall match/meet or exceed the specified equipment and material.

i. The contractor shall correct work not meeting these specifications at no additional expense to the government.

j. The contractor shall coordinate work between the different disciplines.

5. Permits & Utility Outages:

a. It shall be the contractor’s responsibility to attend permit and outage request meetings.

b. Before any “hot work” is performed on the job, an AF Form 592, USAF

Welding, Cutting, or Brazing Permit, must be obtained and displayed at the work site for the duration of the permit.

UHHZ160050 ___ STATEMENT OF WORK - 01005

c. Permits can be obtained by contacting the Civil Engineer Construction

Inspector/Army Corp Project Engineer assigned to the job. The Fire Alarm Dispatch Center can be reached at 478-926-3487 or 478-926-3488.

d. Permits will be returned to the fire department, Bldg. 377 Fire Station Number

1, on the day they expire.

e. Adequate number and type of portable fire extinguishers, supplied by the contractor, will be as close to the work as possible. At least a 10 lb ABC type fire extinguisher shall be located at close proximity to the work being performed. In certain circumstances, one or two 20 lb ABC type fire extinguishers will be required for hazardous locations. The fire inspector issuing the welding/burning permit will determine the required level of protection at the time of permit issuance.

f. A digging permit will be required before any digging, driving of stakes or post starts.

g. Digging Permits are obtained on Monday at 0800 hours of each week at building 1555 break area. If Monday falls on a holiday, the permits will be issued on Tuesday following that Monday.

h. Utility Outages will be signed off on during the weekly outage meeting held on Wednesdays at 1000 hours in building 1555. Request utility outages in writing to the Base

Civil Engineer, with a copy to the Contracting Officer a minimum of 21 days before the proposed outage.

i. Outages shall be scheduled at the Government’s convenience and may be at times other than normal working hours. For example, the times may be on weekends or during the second and third shifts (including holidays, holiday weekends, and work curtailment days).

These are at no additional cost to the Government.

j. These hours are subject to change.

6. Superintendent: A full time Superintendent is required for this delivery order.

a. The Superintendent shall be a non-working superintendent. The superintendent shall be on site at all times when any contractor or subcontractor personnel are on site. The superintendent must be on site at all times and available to the Government and be totally aware all aspects of the project.

b. The contractor shall provide the Contracting Officer a letter designating a competent person as site superintendent. The letter shall state that the superintendent has full authority to act for the Contractor and will be the primary Point of Contact for the Government.

The Government reserves the right to disapprove the proposed superintendent.

c. The Government through the Contracting Officer or Technical Representative of the Contracting Officer (CEA Project Manager) reserves the right to shut down all Contractor site activities if the superintendent is not on site at such times. Site work shall not resume until the superintendent has returned to the site. Several violations of this requirement are cause for termination for default.

UHHZ160050 ___ STATEMENT OF WORK - 01005

7. Site, Maintenance, Clean-up and Restoration:

a. Maintain the work site in a neat, orderly and safe manner.

b. Remove scrap, waste and excess materials promptly. Provide signs, barricades and lights as required to protect base personnel.

c. Do not allow trash and debris to accumulate and become unsightly. Sweep up and collect in contractor-maintained disposal containers daily. Dispose of collected debris weekly as a minimum.

d. Restore the project site to its final condition as required by the contract as soon as possible.

e. After Beneficial Occupancy acceptance, cut all grassed areas a minimum of

(1) one time.

8. Rejected Work: If work performed by the contractor or a subcontractor does not meet the plans, specifications, national standards, Base Standards, applicable codes, industry standards, or acceptable workmanship the contractor shall accomplish the rework at no additional cost to the government. Rework will be rescheduled for the next normal workday.

9. Equipment Damaged by Contractor: The contractor shall take before and after photographs of the work site. If project site is located on the Airfield, the Contractor must obtain from the Project Manager an Airfield Photo Authorization Letter. Prior to starting work the contractor shall photograph, annotate, and bring to the attention of the inspector any noticeable damage to equipment, ceilings, walls, doors and frames, furniture, floors etc. The location of the annotated and photographs shall be well defined. If the damage is not documented then the contractor shall be responsible for the repairs. The contractor shall jointly verify the status of the fire alarm panel with the inspector prior to work starting. The contractor shall be responsible for the repair of any of the above damaged in the process of performing their work. The repairs shall utilize original manufacturer’s approved parts and comply with manufacturer’s printed instructions/specifications. When the contractor finishes the repair, the equipment shall function within acceptable manufacturer’s printed instructions/specifications. This shall be accomplished at no cost to the Government.

10. Contract Qualifications: The contractor shall ensure that all employees performing work under this contract have all applicable licenses and certification to work on the item(s) in question. At a minimum, the contractor shall hold all applicable license(s) required by the state for the type of work being accomplished. Supporting documentations shall be provided if requested. At any time, work performed by a non-qualified person(s) may be rejected as noncompliance and may not be acceptable.

1.02 CONTINUED OCCUPANCY:

A. Access: Building 673, north wing is vacated. However, the south wing (flash-jet shop) is occupied and shall remain in full operation during the entire duration of the project. The contractor will be given full access to the project area (north wing).

UHHZ160050 ___ STATEMENT OF WORK - 01005

B. The work area is not in a restricted area.

C. Beneficial Occupancy: The Government reserves the right to take beneficial occupancy of parts of the project area before the total project completion date. This is not final acceptance, and identified deficiencies must still be corrected.

1.03 HOURS OF OPERATION:

A. Standard Work Hours: The contractor shall perform the services required under this contract during the following hours: MON – FRI, 0730 –1600, except federal holidays and as noted herein. The contractor may be allowed to work, with prior approval of the contracting officer representative, extended hours to ensure timely completion of work at no additional cost to the government. Permission to work extended/alternate hours shall be requested in writing a minimum of 5 days prior to when the alternate work hours are desired. The Government reserves the right to deny the contractor’s request.

B. Holidays: The contractor is not required to work on the following days without written approval: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence

Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day. If the holiday falls on a Saturday, it is observed on Friday. If the holiday falls on Sunday, it is observed on Monday.

Permission to work on holidays shall be requested in writing a minimum of 5 days prior to when the alternate work hours are desired. The Government reserves the right to deny the contractor’s request.

C. All references to days mean consecutive calendar days unless otherwise noted.

1.04 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section

01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s data in lieu of the required certificate of compliance if he desires. The government requires manufacturer’s data if an “X” appears under the “Mfg. Data Required” column.

B. All materials required for this delivery order shall be submitted as required per Section

01300. Form 66, in coordination with the final approved specifications, shall be completed by the

Design/Build A-E and included with the Final Design.

1.05 GOVERNMENT FURNISHED PROPERTY: Will not be provided in this project.

1.06 GOVERNMENT REPRESENTATIVES:

A. The contractor shall not make any changes to or deviate from the requirements listed in the

SOW unless approved in writing by the Contracting Officer.

UHHZ160050 ___ STATEMENT OF WORK - 01005

B. The government project manager (PM) for the contract is David Trescott, 78 CEG/CENMP, 478-926-8838. The government construction inspector for the contract is Don Green, 78 CEG/CENME, 478-926-6960.

PART 2 - PRODUCTS

A. Sole Source Products - No sole source products are required.

B. Design Basis

1. Roof System: MBCI, Double Lok (3” trapezoidal standing seam (mechanically field seamed), double lock).

2. Overhead Coiling (rolling steel service) Door: Overhead Door Co., Model 625.

3. Emergency eyewash/shower: Haws Drench Shower with Face/Eyewash.

PART 3 – EXECUTION

3.01 COMMENCEMENT OF WORK

A. Construction Prohibition: Do not order any materials or start any construction until the

Contracting Officer has approved all related submittals.

B. Noncompliance Impacts: Any contractor costs resulting from noncompliance with these requirements are the sole expense of the contractor. Noncompliance shall not be cause for contract extensions or other considerations, but they may be cause for the Government to charge the contractor for liquidated damages for all negative impacts upon the Government.

3.02 COORDINATION: The superintendent (or contractor on-site project manager) shall coordinate work between different disciplines.

A. Avoid conflicts between new mechanical, electrical, architectural, and civil systems. Also, avoid conflicts between new work and existing structural or physical aspects or features of the facility.

Request guidance from the Contracting Officer, and then perform such work at no additional cost to the

Government.

B. Locations shown are approximate and may be moved if approved in writing by the

Contracting Officer. Show such variations on as-built drawings and do them at no additional cost to the Government.

C. Manufacturers' recommendations and/or requirements, if more stringent than the specifications and drawings, shall be followed at no additional cost to the Government.

UHHZ160050 ___ STATEMENT OF WORK - 01005

3.03 AS-BUILTS: Also see Section 01300 (01310) for submittal items such as As-Builts that apply to all projects.

<<<<< END OF SECTION >>>>>