Procedural_Guide_for_Designers_29_May_15.pdf

PDF 246 KB Posted

Attached to
Design-Build for Building 673 Federal contract opportunity
Solicitation number
FA8501-17-R-0005
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Attachment 6, Procedural Guide for Designers

View the file

Other files for this federal contract opportunity

Other files attached to Design-Build for Building 673, newest first.
File Type Posted
FA8501-17-R-00050006.pdf PDF
FA8501-17-R-00050005.pdf PDF
Statement_of_Work,_Addendum_2_6_Jun_17.pdf PDF
160050_-_Contractor_RFI_Responses_(20170609).pdf PDF
FA8501-17-R-00050004.pdf PDF
Statement_of_Work,_Addendum_1.pdf PDF
Contractor_RFI_Responses_(20170524).pdf PDF
Contractor_RFI_Responses_(20170504).pdf PDF
160050_-_Contractor_RFI_Responses_(20170412).pdf PDF
FA8501-17-R-000503.pdf PDF
Contractor_RFI_Responses_(20170504).pdf PDF
FA8501-17-R-000502_(FINAL).docx DOCX document
FA8501-17-R-000501_(FINAL).docx DOCX document
Site_Visit_sign_in_sheet.pdf PDF
NOTE_TO_OFFERORS.pdf PDF
Submittal_Register.xlsx XLSX spreadsheet
B673_Utilities_Map.pdf PDF
Statement_of_Work_19_Jan_17.pdf PDF
B673_Drawings_10_Nov_16.pdf PDF
DBA_Wage_Determination_27_Jan_2017.pdf PDF
FA8501-17-R-0005,_Solicitation_(Final).docx DOCX document
Special_Warranty_Requirements_Letter.pdf PDF
App_C,_Industrial_Safety_and_Health_Requirements_14_Dec_16.pdf PDF
Base_Facility_Standards_23_Jun_14.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

29 May 2015

Robins Air Force Base

Procedural Guide for Designers

78ABW WR/ALC 78CEG

Prepared By: 78 CEG/CEN, Robins AFB, GA

May 2015

The requirements of this document are mandatory as stated herein for all facilities work at Robins

AFB

ROBINS AFB PROCEDURAL GUIDE FOR DESIGNERS

PROCEDURAL GUIDE

FOR DESIGNERS, INCLUDING ARCHITECT-ENGINEER (AE) CONTRACTORS

AT ROBINS AFB, GA

INDEX

1. General

2. Site Investigations

3. Design Analysis

4. Interior Design

5. Documentation Requirements – Other than Drawings

6. Documentation Requirements – Drawings

1. GENERAL: This is a mandatory guide for use with contracts managed by offices of the 78th Civil Engineer Group (CEG). This Guide shall be used in conjunction with the Robins Base Facility Standards (current edition). These types especially apply:

a. Open-end IDIQ Contracts with Architect-Engineer (AE) Firms

b. Designs performed under design-build contracts

c. Any other contracted services for design or consulting services

2. SITE INVESTIGATIONS

a. General:

(1) Check exterior utility connection points to insure they match record drawings. Utilize detection equipment to verify locations of existing utilities including electromagnetic detectors and ground penetrating radar. Where utilities cross (both new and existing), particularly where gravity utilities are involved, verify depth with potholing (use air equipment). Check with 78 CES shops for their experience at your particular site.

(2) Check above drop ceilings. Lift panels to check for a drop ceiling above ("Must be removed" - Fire Department), insulation, electrical conduit, HVAC ducts, roof material, etc.

(3) Make engineering judgments about concealed utilities. For example, assume electrical seal-offs must be replaced. Include these judgments in your analysis.

b. Architectural:

(1) Carefully examine exterior protective coatings, as follows:

(a) Examine present coating and determine type of coating material.

(b) Examine subsurface for potential problems in recoating.

(c) Advise proper surface preparation.

(d) Advise good protective coating system for application.

(2) Confirm existing building interior and exterior dimensions for repair/renovation projects, particularly if Govt. record drawings have been provided. Check clearances for handicap accessibility.

(3) Review existing door and hardware condition, including door swing, types of hardware, etc.

(4) Examine for any visible signs of previous stormwater damage. Ascertain the cause of the damage and advise corrective measures.

(5) Examine for any hazardous conditions for correction. These include protrusions, trip hazards, unsafe equipment, etc.

(6) Examine for hazardous materials that may be present including, but not limited to, lead based paint, asbestos containing materials and dust contaminated with heavy metals. Normally, the SOW for the project will contain scope for identifying and testing for these materials, but the designer should record any suspect materials during the inspection regardless.

(7) Examine existing structural components for any visible damage or possible overloading conditions.

c. Civil:

(1) Check existing grades such as invert elevation at manholes, drainage ditches, and culverts.

(2) Check existing trees, shrubs, etc., for location in reference to new building or addition. Work on trees and shrubs must be approved by 78 CEG/CEIER and shall be IAW with current Antiterrorism guidelines.

(3) Check existing pavements and foundations.

(4) Check location of existing roads, parking areas, etc.

(5) Check grades required for adequate drainage.

(6) Check details for patching pavement over new utilities, etc.

(7) Check sodding and seeding requirements.

(8) Soil borings are required on new building, building additions, and paved areas (such as aircraft aprons and equipment storage areas) for both structural and environmental conditions.

(9) Ground Penetrating Radar and “potholing” is required to locate existing underground utilities.

d. Mechanical:

(1) Check heating/cooling system: Natural gas, steam, chilled water, compressed air, etc. Locate nearest tap points if not presently in use.

(2) Get nameplate data on equipment to be reused such as air-handling units, chillers, compressors, etc.

e. Electrical:

(1) Check primary power and service entrance.

(2) Get nameplate data on equipment to be reused such as panelboards, transformers, etc.

(3) AE shall obtain and provide an energized work permit to 78 CEG/CEN electrical engineer prior to opening energized electrical equipments.

(4) Open switchboards, panelboards, etc., to check for spares and spaces. Put tags on them to prevent Base shop personnel from using them when needed for this project. Use PPE as per NFPA-70E shall be required when examining switchboards, panelboards, etc.

(5) Take voltage and amperage readings on existing equipment. Use PPE as per NFPA-70E.

(6) Generally, schedule the removal abandoned conduits and conductors.

f. Fire Protection:

(1) Check fire protection system: Fire water piping, fire hydrant, making water flow tests, fire pump tests, etc. Locate nearest tap points.

3. DESIGN ANALYSIS:

a. General

(1) IMPORTANT NOTE: Every Delivery Order or AE design requires a complete Design Analysis.

Follow the format shown below, and provide the technical information that is required. Failure to do this can result in a submittal being rejected in its entirety.

(2) Submit in accordance with statement of work. All sections must be included or noted as not applicable.

(3) As stated in the Memorandum for Distribution for Air Force Sustainable Design and Development (SDD) Implementing Guidance, dated 2 June 2011 (http://www.wbdg.org/ccb/AF/POLICY/af_sdd_impl_guidance.pdf), all Air Force Construction projects shall meet the following sustainability requirements:

(a) All new vertical construction and major renovations (Restoration & Modernization), meeting the USGBC LEED 2009 Minimum Program Requirements (MPR’s for facilities over 1,000 sf) shall fully incorporate Federal Requirements for High Performance and Sustainable Buildings (HPSB for facilities over 5,000 sf); shall be registered in USGBC Online; shall be formally certified to achieve a minimum LEED Silver certification; and shall achieve not less than 20 percent (40 percent of the Silver point threshold) dedicated toward energy efficiency and water conservation.

(b) All new vertical construction and major renovations (Restoration & Modernization), NOT meeting the USGBC LEED 2009 Minimum Program Requirements (MPR’s) shall fully incorporate Federal Requirements for HPSB’s and shall pursue LEED credits, relevant to the scope of the project, to the maximum extent practicable. The project types are defined in ETL 08-13, Incorporating Sustainable Design and Development (SDD) and Facility Energy Attributes in the Air Force Construction Program are:

1) Vertical – Includes typical building construction for which LEED-NC was developed as a metric

2) Horizontal – Includes site development, heavy earthwork, construct and repair roads, runways, taxiways, aircraft aprons, containments, sidewalks, parking lots, revetments, curbs and gutters

3) Utility – Includes electric, gas, water, steam and wastewater, including substations, lift stations, oil/water separators, storage tanks, petroleum, oil, lubricants (POL) lines, and transformers.

4) Industrial – Includes all enclosed facilities for which mechanical cooling/heating is provided for less than 50 percent of the building square footage

(4) As referenced in specification Section 01560 - Environmental Requirements:

(a) Plans for Post Construction Stormwater Management: Post Construction Stormwater Management Plan narrative and calculations for sizing of all post construction BMPs shall be submitted for all new development or redevelopment greater than 5,000 ft2 (of impervious area or land disturbance). This Plan typically includes a Hydraulic and Hydrology Report and EISA Compliance requirements, as well as related narrative, figures, and drawings. The design shall meet the minimum stormwater management standards of the GSMM and Section 438 of EISA. The Plan shall be submitted as part of the project design documents for the 60 percent design (i.e., intermediate design) submittal.

All stormwater management plans must be stamped by a registered civil engineer.

(b) Post Construction Stormwater Management Plan: The Contractor shall implement minimum control measures for stormwater runoff from new development and redevelopment projects that includes the creation or addition of 5,000 square feet or greater of new impervious surface area, or that involves land disturbing area activity of 5,000 square feet of land or greater in accordance with the: (i) Stormwater Local Design Manual for Houston County, Georgia (LDM); (ii) Georgia Stormwater Management Manual (GSMM); and (iii) Section 438 of the 2007 Energy Independence and Security Act (EISA) as specified in the 2010 Department of Defense Memorandum. Documentation of conformity will consist of inclusion of a Post Construction Stormwater Management Plan (i.e., Hydraulics and Hydrology Report, EISA 438 Design Narrative, etc., including required associated calculations). The Plan shall be submitted through the established design review process.

(5) Narrative description of approaches is needed just as much as strict calculations. We need to know what you are thinking to catch omissions and errors.

(6) Site visits and phone calls need to be recorded for the same purpose. If you put a panelboard on a wall, we want to know you looked at the wall first.

(7) Reference any codes, standards, articles, special investigations, and reports used in your decision-making process.

b. The Index after the title page shall list the following sections. NOTE: If any one of the nine major sections needs no analysis, indicate on the index that it was not required. The sections and areas to consider are as follows:

(1) Architectural

(a) Basic considerations/concept

(b) Physical security measures

(c) Noise reduction or sound attenuation for outside sources

(d) Architectural Compatibility - Base Comprehensive considerations

(e) Structural Interior Design (SID)

(f) Comprehensive Interior Design (CID)

(2) Civil

(a) Water Supply - quantity, quality, pressure

(b) Waste Water and Solid Waste Disposal - quantity, industrial, sanitary

(c) Storm Drainage - rainfall, runoff, pipe capacity

(d) Paving, Roads, Walks - loading, base, surfacing

(e) Fences

(f) Soil Tests, both structural and quality (contaminates)

(3) Structural

(a) In accordance with Robins AFB Base Facility Standards, Designer shall provide all the project items listed below:

(1) Structural Calculations - Show actual design calculations for the resulting design keyed to the structural elements referenced. If a computer program is used to calculate the loads, the design analysis shall contain clear and understandable descriptions of all input, output, and the mathematical process used by the program to compute the loads and size the members.

(2) Drawings

(3) Specifications

(4) Structural Tests & their Reports

(5) Special Inspections & their Reports

(6) Geotechnical Exploration Reports & Recommendation

(4) Mechanical

(a) Utility Plant (gas, steam, chilled water, compressed air, POL)

(b) HVAC - The AE shall perform heating and/or cooling load calculations in accordance with ASHRAE procedures under any DO/design which involves installation, replacement, or modification of heating and/or air conditioning systems. The designer shall provide complete load calculations with the preliminary design. The designer shall use a computer program to compute the loads, a description of the program and copies of all input/output data and the mathematical process which shall be included in the design analysis. Robins AFB Weather Data shall be used for all HVAC calculations.

(c) Plumbing: Plumbing systems shall be designed in accordance with the Georgia and International Plumbing Code. Any new construction project that requires the installation of urinals, lavatories, toilets, shower heads, and faucets must follow the standards related to high-efficiency plumbing fixtures

(d) Energy Efficiency - The AE shall demonstrate in the Design Analysis that energy using equipment specified has the lowest Life Cycle Cost compared to similar equipment with various efficiencies.

(5) Electrical

(a) Interior and Exterior Power - capacity calculations for unit substation, transformers, panelboards, switchgear, etc., considering loads, load factors, diversity, and future loads. Voltage drop calculations.

Time-current coordination studies with short-circuit calculations.

(b) Interior and Exterior Lighting - foot-candle calculations, light source types and mountings, and photometric curves (especially when photometrics influence the type of light fixture selected). Include floor plan with light levels (Four foot (4’-0”) above floor in foot candle or lux) for each type of fixture.

(c) Emergency Power - generators, automatic transfer switches

(d) Power Conditioning - UPS, harmonics (non-linear loads), and power conditioners

(e) Hazardous Areas - clarify classes needed

(f) Communications - telephone, LAN, CATV

(g) Lightning Protection - Evaluate need, especially on all new building construction, major building renovation projects, and roof repair projects

(6) Fire Safety (UFC 3-600-01, NFPA)

(a) Life safety

(b) Detection

(c) Suppression

(1) The designer shall provide sprinkler hydraulic calculations in the HASS format (by HRS Systems, Atlanta, GA) or other Base Approved agencies and is fully responsible for all water supply analyses required for each project, including making water flow tests, fire pump tests, etc.

(2) Design shall be IAW NFPA 13, Factory Mutual (FM), UL, UBC, Unified Facilities Criteria-

UFC 3-600-01 (Fire Protection Engineering for Department of Defense Facilities), Base Facility Standard, and the System Safety Analysis for each project.

(d) Notification

(e) Limiting

(7) Corrosion Control

(a) Material selection

(b) Protective coatings

(c) Industrial water treatment

(d) Cathodic protection

(8) Environmental Concerns - asbestos, lead paint, permits, disposal of hazardous waste, PCB’s

(9) Annotated Review Comments from previous submittal

c. Format: This analysis shall be on 8-1/2" x 11" (approximate) reproductive paper and will have standard headings to indicate the project, the type of computation, the name and date of the designer, and the checker. A one-inch binding margin is to be provided on the left side and on the top of the page.

The design analysis shall be bound and submitted in the number of copies designated in each DO/design. Each area in the analysis will include, but not be limited to, the following:

(1) Short description of the work involved.

(2) The designer's assumptions for the design.

(3) Listing the standard works or references used on computations as they occur.

(4) The equations, tables, or curves used or developed in all the detail needed to establish the design, with references cited where they are taken from non-standard sources.

(5) Suitable freehand sketches to illustrate the designer's intent, such as steel sizing and arrangement, pipe arrangement, beam layout, etc.

(6) Selected size of equipment even where computations are not involved. This may consist, for example, of a single statement to use a 60 HP Westinghouse piston compressor model XYZ. A few statements to show the basis for the selection shall be included.

(7) All calculations and sources of information shall be shown in an orderly and logical manner to permit review and final checking. Computer calculations shall be explained by a summary of input information, output information, and the calculation procedures the software uses to produce the results, and an analysis of the results.

(8) Economic Analysis: The AE shall make a comparative cost analysis during design phases on each DO/design to justify selections of type and source of utilities, major items of equipment, building components, materials, methods of construction, siting, plumbing, lighting, heating, air conditioning, building configuration, electrical systems, column spacing, roads, story heights, structural system, and interior and exterior finishes. The Analysis shall include cost of operation and maintenance over the expected life of the project. Such cost analysis shall consider the life cycle cost of the facility and other aspects needed to make value-engineering judgments. The cost analysis and decisions based upon it shall be documented in the design analysis submitted for approval.

(9) Product data sheets on all major items.

4. INTERIOR DESIGN

a. Policy: Air Force Policy stipulates that design services must include the following interior design provisions:

(1) Structural Interior Design is a standard requirement. These services will be accomplished as part of the basic facility design fee.

(2) Comprehensive Interior Design services are additional requirements and will be accomplished only if required in the DO/design.

b. Structural Interior Design (SID) shall consist of design and/or selection and color coordination of building surfaces, paint colors, floor covering, window covering, built-in furniture, and similar items which are integral to or attached to the structure.

(1) Finish schedule.

(2) Design and/or selection of decorative building surfaces.

(3) Floor and wall coverings.

(4) Window coverings.

(5) Built-in furniture and similar items which are integral to or attached to the structure.

(6) Preparation of presentation boards showing material and color samples for approval purposes.

(7) Early preliminary furniture placement plan or functional relationships.

(8) Consultation as required later for revision of selection due to unavailability of materials, analysis of substitutions, etc.

c. Comprehensive Interior Design (CID), when required, shall consist of structure-related services plus design, selection, arrangement, and color coordination of furnishings authorized by a table of allowances. These furnishings are funded from equipment funds and when authorized may include sofas, chairs, tables, desks, bookshelves, beds, chests, mirrors, lamps, rugs, carpeting, pictures, planters, decorative objects, etc.

(1) Selection of furnishings in accordance with applicable table of allowances. Furnishings shall be selected from Government sources to the maximum extent possible. When procurement from Non- Government sources if required, the justification for a waiver to source, purchase specifications, and any other data necessary for procurement, shall be provided.

(2) Furniture arrangement and preparation of placement plans.

(3) Preparation of furnishing procurement lists with source data, item identification and cost estimates.

Updating the list to reflect current item numbers, etc., for a period not to exceed one year from the date of submittal of the final drawings.

(4) Existing furnishings will be used to the maximum extent possible. Techniques such as the General Services Administration's electrostatic paint process to color-coordinate and upgrade existing office furniture will be used, when required. When new furniture must be procured to satisfy functional requirements, selection should be made by professional designers and color-coordinated with the environment.

d. CID Concept Development:

(1) Prior to development of the interior scheme, the designer is required to meet with the Facility managers, the Engineering and Services Office representative (having final functional approval authority), and the Contracting Officer for the purpose of discussing the design concept. The discussion shall include:

(a) Space planning and functional layout.

(b) Determination of atmosphere, decor and color scheme, and environmental conditions required in the facility based upon using agency needs, services provided, and other factors.

(c) The requirement for the designer to work within the budget.

(d) Time schedule for presentation.

(e) Identification of reusable furniture.

(2) With the concept report or preliminary design, as applicable, the designer shall submit a memorandum outlining the considerations and general concept to be followed.

5. DOCUMENTATION REQUIREMENTS – OTHER THAN DRAWINGS:

a. General

(1) Master transmittal letters and miscellaneous documents will be furnished with each DO/design and shall be tailored for use on each DO/design.

(2) Conferences and Meetings:

(a) Provide the Contracting Officer and the Base Project Manager a written record of all conferences and meetings (other than formal review conferences) held between the Government and the AE during which the technical design of the project is discussed. These records cannot constitute any "Notification of Change" as described by the changes clause of the contract.

(b) Provide each record within 2 workdays after the conference or meeting.

(c) Include these in the Design Analysis.

(3) Originals: Provide disk copies of word processing documents in Microsoft Word and PDF format as part of the Corrected Final package.

(4) Cost estimates shall be prepared using the latest version of RS Means Master Composite on the base’s latest Microsoft Excel version in the same format as AF Form 3052. The base version may include typical General Conditions that are often overlooked. Provide disk copies of the cost estimate files.

(5) If building will be occupied during construction, contractor shall identify all hazards during the design phase that may have an adverse effect on building occupants, equipment, building systems, etc.

during the construction phase. (For example: Project that includes working on roof over occupied space: cutting insulation, replacement of existing screws can cause dust particulates and other airborne particles that may be a hazard for personnel and/or equipment below.) Contractor shall provide design to contain all hazards to building occupants, equipment, building systems, etc. for contractor to utilize during the construction phase.

b. Specifications – General:

(1) Specifications shall be edited copies of the Robins Division 1 specifications maintained by 78 CEG/CENMP and Unified Facilities Guide Specifications (UFGS) found at the following link http://www.wbdg.org/ccb/browse_org.php?o=70. In additions, all specifications shall be in accordance with Robins AFB Base Facility Standards. The project manager will provide the Robins AFB Division 1 Specifications to be included in all projects. The project manager will work with the RFP A-E and Design-Build A-E to ensure that the Robins AFB Division 1 Specifications are included as part of the project.

(2) Edit out in each section any extraneous material that does not apply to the project.

(3) The design shall take into consideration that the specifications override drawings when a conflict arises between the two.

(4) When one manufacturer of an item of equipment is used as the design basis, clearly state the name, catalog numbers, etc. List all salient accessories, features and/or characteristics to be compared with other manufacturers' equipment. Do not use the clause "or equal." Ensure that items are not sole source.

If an item must be sole source (such as to match existing systems, etc.), detailed rationale must be provided in the design analysis and approved by the Base Project Manager.

c. Specifications – Quality Check Items: These are commonly found to be handled incorrectly or incompletely in many submittals and are provided to assist with the AE’s quality control methods.

(1) Date with the latest published date all referenced standards, codes, etc.

(2) Do not refer to sections that do not exist in the package.

(3) Provide with the Preliminary submittal marked up copies of the Specifications showing planned inserts and deletions.

(4) Section page numbers must be in index and on each page at the lower right, e.g. l5050-l thru l5050-5 and on lower right include - Section Name and then 15050 1-5 below.

(5) Provide project number at the beginning of each section.

(6) Do not use statements or clauses in the technical specifications that may conflict with standard FAR clauses. The following are mentioned in the AFSC/PZIO boilerplate:

(a) Methods of payments

(b) Guarantees

(c) Evaluation of bids

(d) Bidding procedures

(7) Do not use terminology that conflicts with standard Government terminology.

(a) Do not use the term "owner." Refer to Robins AFB as the "Government."

http://www.wbdg.org/ccb/browse_org.php?o=70

(b) The person in charge of the contract is the "Contracting Officer," not the AE, inspector, or architect.

(c) We only recognize the "Contractor," not any subs.

(8) Ensure specified equipment and materials are readily available, especially when renovating existing equipment.

(9) Use "shall" when describing a requirement that the Contractor must do. Use "will" when describing something the Government intends to do. (We prefer direct statements such as "Provide lights," over indirect statements such as, "The Contractor shall provide lights.")

(10) Include all forms mentioned in the body of the specification as submittals as attachments for contractors to pull off and submit.

(11) The AE may specify products by brand names. The following guidance must be followed.

(a) The Material and Workmanship Clause of the FAR included in all construction contracts, in brief, permits the contractor to use any American-made product which complies with the objectives of the Government as specified in the specifications and drawings. FAR 52.236.5(a) states . . . "The Contractor may, at its option, use any equipment material, article, or process that, in the judgment of the Contracting Officer is equal to that named in the specifications." Further, FAR 52.236-5(a) clearly states that mere reference "to equipment material, articles or potential processes by trade name, make or catalog number" establishes a standard of quality and does not limit competition. Consequently, merely stating a product without any restrictive modifiers will establish a standard. For example, "The fluorescent fixture in the specifications and drawings is a Lithonia XYZ."

(b) A problem arises when the specifications and drawings specifically limit the product to be utilized by the contractor. This undesirable end can be accomplished very simply. For example, the specifications and drawings could state, "The product shall be Lithonia," or "This product shall be manufactured by Lithonia." The word "shall" is, in the FAR, mandatory on the part of the reader. Other restrictive phrases are "Acceptable manufacturers are . . ." and "The only acceptable manufacturers are .

. .” By negative implication, no other manufacturers are acceptable.

(c) The rule of construction then to be followed is that neither the specifications nor drawings can limit the extent of competition directly or by inference. Some suggested and acceptable phrases are these:

"The design basis is . . .", "Some acceptable manufacturers are" or "Acceptable manufacturers include . .

....” Do not include both a design basis and acceptable manufacturers.

(d) Since a design basis establishes quality only, we need to specify those features and accessories that would make a product "equal." We have had problems in the past in failing to specify and obtain all accessories even when the design basis is used, so make sure they are called out for.

6. DOCUMENTATION REQUIREMENTS - DRAWINGS

a. General

(1) Copies: Provide electronic format documents in CADD and PDF formats of all drawings. Provide printed copy as required per Delivery Order.

(2) Originals: Provide electronic format of CADD files as part of the Corrected Final package.

(a) General:

(1) Provide on CD-ROM all CADD generated drawings in a format fully compatible with

AutoCAD 2010 (.dwg) system. Comply with all applicable requirements of the latest Robins AFB Civil Engineering CADD Standards.

(2) Transfer the electronic files with a transmittal note by certified mail or in person to the project manager for forwarding to appropriate CADD Manager.

(b) Develop project file names according to the Robins AFB Civil Engineering CADD Standards as follows:

(1) File-naming conventions are provided in the A/E/C CAD Standards version 4.0 for the DoD, (https://cadbim.usace.army.mil/CAD), which provides for “user” identifiers.

(2) Model Files:

(If these are master model files, use the building number as a prefix; this is still under development) First Character: Discipline (e.g., A, E, M, P, S, G, C) Second Character: “-” (don’t use second-level identifiers unless pre-approved) Third/Fourth Characters: Drawing Type (FP [floor plan or framing plan], PP [piping plan, plumbing plan or power plan], HP [HVAC Plan], etc.)

Fifth/Sixth Character: Project Code (e.g. “KO”, provided by Government) Seventh/Eighth Character: Sequence Number (01, 02, etc.)

Model Files shall be coordinated with each other so they overlay correctly, but shall not have any reference files when delivered.

(3) Sheet Files:

Sheet files shall be placed in PAPER space only. DO NOT PLACE IN MODEL SPACE!

First Character: Discipline Code Second Character: “-” Third Character: Sheet Type (0 for legend, symbols, notes; 1 for horizontal plans, 2 for elevations, 3 for sections, 4 for large scale [usually part plans], 5 for details, 6 for schedules/diagrams, 9 for photographs or 3D isometrics) Fourth/Fifth: Sheet Sequence Identifier (similar to numerical plate number) Sixth/Seventh: Project Code (e.g. “KO”, provided by Government) Eighth Character: Revision Number (always zero for final design, incremented as the sheet file is subject to contract amendments or modifications; as-builts will be coded “F”) Sheet files shall reference only model files. Also, remove any reference files that were “temporary”.

https://cadbim.usace.army.mil/CAD

(4) Refer to A/E/C CAD Standards version 4.0 for the DoD for additional information, including layering standards. Comply with the “simplified” layering standards (layer name/number, line weights, line styles, line colors).

(c) Project files shall be delivered to the Government in the project directory structure established by the Robins AFB Civil Engineering CADD Standards. This is currently a main directory named as the project number (such as 980213) and subdirectories as follows:

(1) Directory “dgn” includes all dgn files and an index in Microsoft Word format, as described in the Robins AFB Civil Engineering CADD Standards. All sheet files must be in this one common directory with all reference files in the “model” directory under the “dgn” directory.

(2) Directory “spec” includes all Specifications and their index.

(3) Directory “cost” includes all parts of the cost estimate.

(4) Directory “gov” includes all other required documents, such as letters, bid schedules, design analysis, etc.

(5) Mandatory CADD Files Format:

a) Direct design in .dwg AutoCAD 2010 or latest version. All CADD graphic files must be delivered to the Government in .dwg format and PDF format.

b) Do not submit multiple drawings in single AutoCAD drawing files. Each drawing file may contain a single drawing file only, unique to that file.

c) Ensure each drawing sheet prints out the CADD file name in the title block.

d) If you have questions or problems occur in the submittal of diskettes, contact the project manager or CADD System Manager.

b. Specifics for Different Types of Drawings:

(1) General: Final submittal shall be on CD including CADD and PDF drawings and one (1) hard copy drawing for sign-off by project manager. The project manager shall specify in the delivery order the additional number of hard copy drawings which shall be on Bond paper on size specified. All lettering shall be a minimum of 1/8 inch in height. All drawings for this contract shall use the same size sheets, scale layouts, symbols, and details as used in the standard format by the Office of the Civil Engineer.

(a) Cover Sheet/Location Plan: The AE will be furnished for each DO/design a cover sheet location plan which will be the first sheet of the project drawings. This location plan will be the base map or portion thereof which covers the general project location. The cover sheet containing the latest Robins AFB signature format will be used. The AE will show thereon the Project Location, Haul Route, Base Contracting – Bldg 255, Truck Gate No. 4, Visitors' Gate No. 3, Base Civil Engineer - Bldg 1555, Construction Management and Design - Bldg 280, and other facilities related to project management as directed.

(b) Design-Build Contracts: The Prime Contractor and AE firm shall be identified in the border of the cover sheet and all drawing sheets.

(2) Concept Plans: (When required.) Provide in format and detail to meet Base Project Manager requirements for the DO/design and as described for preliminary plans below.

(3) Preliminary Plans: Preliminary plans shall be prepared at working drawing scale and shall present sufficient detail to permit an adequate review as determined by the Office of the Civil Engineer. The AE is permitted to use the tracing of the preliminary drawings for working drawings through the addition of necessary details, if desired. Existing site conditions and demolition work will be shown in complete detail on separate sheets from construction drawings. Construction and relocation preliminary drawings will include, but are not limited to the following:

(a) Floor plans with functional arrangement of all areas, including corridors, exits, and utility spaces properly related to exterior access roads, parking and service areas, etc. Special emphasis shall be placed on indicating items involving special design and/or deviations from accepted standards. Gross floor areas shall be shown for the building. Floor and roof framing and loading shall be indicated.

Include Life Safety Code Analysis sheet including floor plan with travel distances, number of occupants, door capacity, fire extinguisher locations and all other required information. Show layout of furniture, office cubicles, equipment (including copiers, kitchen eqpt., etc.) to show space planning and allow for locating communications and utilities.

(b) Site and/or plot plans showing critical grades, contours, drainage requirements, and relation of structure and facilities to existing street systems, utilities, entrances, and finished grades. Present grades shall be indicated, where applicable. The location of new items of work shall be shown.

(c) A reflected ceiling plan showing all items of equipment which will be in the ceiling after completion of the work.

(d) Exterior utility layouts sufficiently detailed to show the system and the design proposed.

(e) Elevations to include story heights, fenestration, finish materials and site adaptation to finished grades.

(f) Heating, dehumidification, mechanical ventilation, refrigeration, and plumbing. Indicate the location and space requirements for all major items of mechanical equipment. Single line indications of ducts, pipes, and equipment and their approximate locations shall be shown, but only approximate size and capacity are required. Provide schedules, control diagrams, plan views, side views, and sections needed to clearly guide the construction contractor.

Specifications submitted with the drawings shall give approximate capacities of the major mechanical items with a brief description of their function and operation of the system.

(g) Electrical (including lights, power, communication, fire alarm and detection, grounding systems, generators, and UPS systems). For lighting, indicate typical arrangements, fixture types proposed, fixture schedules, general foot-candle levels (include photometric curves where photometrics influence the type of light fixture selected), emergency lighting systems, exit lights, and exterior and interior layouts. For power, show locations and descriptions of devices and loads, metering, raceways, underfloor systems, distribution panels, cables, switches, transformers, generators, and UPS equipment and Arc Flash Protection (short circuit studies and labeling). All communication equipment, raceways, panels, outlets, underfloor systems, rooms, and cables shall be shown. Show plans, sections, and details for lightning protection systems and other special grounding. Show fire alarm, detection, and notification systems in detail. Include single-line and riser diagrams for power, arc flash and lighting, communication, and fire alarm systems. Show significant short-circuit values and settings for adjustable protective devices.

(h) Plans and Sections of structures, including framing, major details, etc.

(i) Typical wall, roof, and partition sections generally at no less than 3/4" = 1'-0" scale to include material and thickness of facing and method of attachment, type of doors and other openings in supporting structural walls.

(j) All required controlling dimensions shall be clearly indicated.

(k) Identify sections or details by numbers within a circle which include consecutive detail numbers, the sheet on which the detail is referenced, and the sheet on which the section or detail is drawn. Include an example in the legend.

(l) Drawings shall contain sufficient detail to clearly indicate type and sizes of materials, utilities, etc., and specifically list separately all contractor-furnished equipment and all Government- Furnished equipment to be installed by the contractor.

(m) Structural Steel Connections: The design of all structural steel connections shall comply with the latest edition of the American Institute of Steel Construction Specifications. Design of structural connections is the responsibility of the AE. Details shall show the size of connecting members, size and length of welds, and number and size of bolts. Specifications shall cover all required materials, processes, and procedures. Minor details of dimensioning, etc., related to code compliance may be left to the fabricator. The Government will review shop drawings for conformity with the design, unless shop drawing review is contracted to the AE separately.

(4) Final Drawings: The AE shall not proceed with the final drawings until receipt of written review comments and/or approval of Phase I and II requirements from the Office of the Civil Engineer. Written review comments shall be annotated by the AE and submitted along with the next submission of documents. The first submission of final documents shall be a complete design needing only a few minor corrections or changes.

(5) Marking and Certification:

(a) Drawings in each submission are to be dated as appropriate and stamped as "Preliminary," "First Finals", or "Corrected Finals".

(b) The AE, or his authorized representative, shall sign the original drawings and the first page of all specifications, estimates, or similar documents under the AE contractor's printed name and over the affixed replica of his professional seal (or his registration certificate number and including the State of Georgia issuance).

(c) AE's name and address shall be printed on each sheet.

(6) Because the government will convert most drawings to a format suitable for electronic advertisement, raster images that are used to create drawings must be handled in a special manner. They must be attached as raster reference files rather than being imported directly into the design file.

c. Drawings - Quality Check Items: These are commonly found to be handled incorrectly or incompletely in many submittals and are provided to assist with the AE’s quality control methods.

(1) The types of information required on each submittal are clearly stated in the Statement of Work. Follow closely, or you may be required to resubmit.

(2) Title sheet must have a drawing index.

(3) Provide a key plan for each sheet where a part plan is shown.

(4) Provide separate demolition and installation plans for all work, unless specifically waived by our project manager. Use l" = l00' on utilities if enough detail can be shown. Include topography if applicable.

(5) Use as large a drawing scale as practical. Use at least l/8" = l'-0" on layout plans, building elevations and building sections, and 3/4" = l'-0" on wall sections and 1-1/2”=1’-0”on details.

These drawings may be reduced to half-size in the future. Where multiple floor plans of the same level are required, use key plans and match lines on each plan sheet.

(6) Do not show too much on each floor plan. For example, showing ductwork, chilled water lines, hot water lines, and steam lines on the same floor plan results in confusion. It is necessary to use separate floor plans for each system.

(7) All originals (drawings) shall be stamped with the Architect/Engineer seal prior to Corrected Final submission and have AE name and address.

(8) The use of schedules for all energy consuming or distribution equipment is required. Provide all pertinent characteristics of the utility involved, e.g., voltage, phase, and power for electrical equipment. Fans and other mechanical equipment using motors shall have electrical characteristics specified by the electrical engineer and scheduled on electrical drawings, regardless of who supplies them. Specify who provides (Div. l5 or l6).

(9) Provide a reflected ceiling plan on Architectural Drawing which coordinates all electrical and mechanical systems.

(10) Provide controls, schematics, and ladder diagrams for mechanical systems.

(11) On new construction, show on the drawings the design structural loads and the strength of all structural materials used in the project.

(12) Provide scale and title for each detail and part plan.

(13) Notes: indicate whether "General," "This Sheet Only," "This Detail Only," etc.

(14) Do not crowd work. Use extra sheets and allow for additional details, sections, notes, etc.

Although the preliminary submittal will not have all the details shown, please indicate where and what you intend to section or detail. This may be a list included as part of the design analysis.

(15) Project title appears in title block of each sheet. Then, in smaller letters, title for the individual sheet. Describe sheet as clearly as possible: e.g. instead of "New Work" use "Electrical New Work, Second Floor, East Wing".

(16) Date all referenced standards, codes, etc.

(17) HVAC and Electrical work must comply with Base Facility Standards.

(18) Plans and details should be oriented so that "North" is toward the top or left side (nine o’clock position) of the sheet, whichever is most practical. Each detail and the key plan shall have a north arrow.

(19) Use size "ANSI D" drawings instead of "E", unless totally impractical. Notify Project Manager when “D” size drawings are totally impractical.

(20) Notes on Drawings - Need them. It is not sufficient to put in an insulation spec on what and how to insulate and then not tell them to do it (either in spec or on drawings, whichever is clearer).

(21) Photo drafting is often helpful in demolition and renovation.

(22) Use separate floor plans for lighting, power, lightning protection, telephone, security, and fire safety.

(23) Provide one-line diagrams for power, fire safety, security, and telephone.

(24) List nameplate data on reused existing equipment.

(25) Final Drawings. These drawings should be in a 100% complete design that is ready to "put on the street." All review comments should be incorporated. Complete all schedules, plans, etc., for each discipline. Provide additional notes on the drawings to insure quality construction.

<<<<< END OF GUIDE>>>>>

(1) Specifications shall be edited copies of the Robins Division 1 specifications maintained by 78 CEG/CENMP and Unified Facilities Guide Specifications (UFGS) found at the following link http://www.wbdg.org/ccb/browse_org.php?o=70. In additions, all...