Attached is Amendment 0004, all changes are described in block 14. Please note change in CLIN Structure.

View the file

Other files for this federal contract opportunity

Other files attached to Design-Build for Building 673, newest first.
File Type Posted
FA8501-17-R-00050006.pdf PDF
FA8501-17-R-00050005.pdf PDF
Statement_of_Work,_Addendum_2_6_Jun_17.pdf PDF
160050_-_Contractor_RFI_Responses_(20170609).pdf PDF
Contractor_RFI_Responses_(20170524).pdf PDF
Statement_of_Work,_Addendum_1.pdf PDF
Contractor_RFI_Responses_(20170504).pdf PDF
160050_-_Contractor_RFI_Responses_(20170412).pdf PDF
FA8501-17-R-000503.pdf PDF
Contractor_RFI_Responses_(20170504).pdf PDF
FA8501-17-R-000502_(FINAL).docx DOCX document
FA8501-17-R-000501_(FINAL).docx DOCX document
Site_Visit_sign_in_sheet.pdf PDF
NOTE_TO_OFFERORS.pdf PDF
FA8501-17-R-0005,_Solicitation_(Final).docx DOCX document
Special_Warranty_Requirements_Letter.pdf PDF
App_C,_Industrial_Safety_and_Health_Requirements_14_Dec_16.pdf PDF
Base_Facility_Standards_23_Jun_14.pdf PDF
Submittal_Register.xlsx XLSX spreadsheet
Procedural_Guide_for_Designers_29_May_15.pdf PDF
B673_Drawings_10_Nov_16.pdf PDF
DBA_Wage_Determination_27_Jan_2017.pdf PDF
B673_Utilities_Map.pdf PDF
Statement_of_Work_19_Jan_17.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE SCHEDULE UHHZ160050

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Update CLIN Structure in Blocks 10 and 21.

2. Extend offer due date from 23 May 2017 to 9 June 2017.

3. Include Statement of Work, Addendum 1 and attachments (665 pages).

4. Update Price Evaluation information and CLIN Schedule in Section B.

5. Include Proposal Submission information in Section L.

6. RFI deadline for Statement of Work, Addendum 1 is Tuesday, 30 May 2017 at 4:00 p.m.

NOTE: Attachments for changes identif ied on page 1 of the SOW, Addendum 1 is included in the same package. The attachments w ill be separated accordingly upon aw ard. Item 5, is not a separate document and is in the CLIN Schedule annotated in the solicitation.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-May-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA850117R0005

X 9B. DATED (SEE ITEM 11)

15-Mar-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-May-2017

CODE

AFSC/PZIOC - FA8501

INFRASTRUCTURE SUPPORT

375 PERRY STREET

BLDG 255

ROBINS AFB GA 31098-1672

FA8501 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA850117R0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 23-May-2017 04:00 PM to 09-Jun-2017 04:00 PM.

The required performance has changed from Design-Build project for Building 673This requirement is solicited as a Small Business set-aside for SDOVSB.Provide all work IAW Statement of Work and Specifications dated 19 January 2017.Disclosure of Magnitude: Between $1,000,000 and $5,000,000CLIN 0001 - Design CLIN

0002 - Repair/Renovate InteriorCLIN 0003 - Upgrade Electrical ServiceCLIN 0004 - Alternate 1, Ventilation and

HeatCLIN 0005 - Alternate 2, Heating and CoolingA site visit has been scheduled for 07 Apr 2017 at 9:00 AM EST.

If you will be attending the site visit, e-mail your information (name of attendees, contact information, company, and state) to MSgt Tracie Sowels & Angela Whitley at the e-mail listed in Clause 52.236-27 NLT 12:00 PM, 23

March 2017. A maximum of TWO representatives per company will be allowed. A criminal and background check shall be conducted before allowing visitors access to the installation. Upon receipt of your e-mail we will request additional information and a response will be required ASAP. Approved participants shall meet at the

Museum of Aviation (right outside Robins AFB, GA), B-1 static display for sign-in and SHALL NOT proceed on their own to the site visit. IF YOUR NAME IS NOT ON THE SITE VISIT LIST, YOU WILL NOT BE

PERMITTED TO ATTEND. to Design-Build project for Building 673This requirement is solicited as a Small

Business set-aside for SDOVSB.Provide all work IAW Statement of Work and Specifications dated 19 January

2017.Disclosure of Magnitude: Between $1,000,000 and $5,000,000CLIN 0001 - Design CLIN 0002 -

Repair/Renovate InteriorCLIN 0003 - Upgrade Electrical ServiceCLIN 0004, Option 1 - PaintingCLIN 0005 -

RESERVEDA site visit has been scheduled for 07 Apr 2017 at 9:00 AM EST. If you will be attending the site visit, e-mail your information (name of attendees, contact information, company, and state) to MSgt Tracie Sowels &

Angela Whitley at the e-mail listed in Clause 52.236-27 NLT 12:00 PM, 23 March 2017. A maximum of TWO representatives per company will be allowed. A criminal and background check shall be conducted before allowing visitors access to the installation. Upon receipt of your e-mail we will request additional information and a response will be required ASAP. Approved participants shall meet at the Museum of Aviation (right outside Robins AFB, GA), B-1 static display for sign-in and SHALL NOT proceed on their own to the site visit. IF YOUR NAME IS

NOT ON THE SITE VISIT LIST, YOU WILL NOT BE PERMITTED TO ATTEND..

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

Design project UHHZ160050, Repair/Renovate Interior, B673, IAW the Statement of Work, dated 19 January 2017

(164 pages)

To:

Design project UHHZ160050, Repair/Renovate Interior, B673, IAW the Statement of Work, dated 19 January 2017

(164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

CLIN 0002

Repair/Renovate Interior, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages)

Repair/Renovate Interior, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

CLIN 0003

Upgrade electrical service, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages)

Upgrade electrical service, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

CLIN 0004

The CLIN description has changed from Alternate 1, Ventilation and Heat to Option 1, Painting.

Upgrade Ventilation and Heating, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages)

Paint existing primary and secondary structural members in theProduction Area, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

CLIN 0005

The CLIN description has changed from Alternate 2, Heating and Cooling, to CLIN has been cancelled.

Upgrade Heating and Cooling, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages)

The pricing detail quantity has decreased by 1.00 from 1.00 to 0.00.

The unit of issue Lot has been deleted.

The following have been added by full text:

CLIN SCHEDULE

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot Design

FFP

Design project UHHZ160050, Repair/Renovate Interior, B673, IAW the Statement of Work, dated 19 January 2017 (164 pages) and Addendum 1, dated 5 May 2017

(665 pages)

FOB: Destination

PURCHASE REQUEST NUMBER: F3QCCL6335A004

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Lot Repair/Renovate Interior

FFP

Repair/Renovate Interior, B673 IAW the Statement of Work, dated 19 January

2017 (164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

PURCHASE REQUEST NUMBER: F3QCCL6335A003

0003 1 Lot Upgrade Electrical Service

FFP

Upgrade electrical service, B673 IAW the Statement of Work, dated 19 January

2017 (164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

PURCHASE REQUEST NUMBER: F3QCCL6335A003

0004 1 Lot Option 1, Painting

FFP

Paint existing primary and secondary structural members in the

Production Area, B673 IAW the Statement of Work, dated 19 January 2017 (164 pages) and Addendum 1, dated 5 May 2017 (665 pages)

CLIN has been cancelled

FFP

The following have been modified:

PRICE EVALUATION

BASIS FOR AWARD: Award will be made to the offeror with the lowest Total Evaluated Price (TEP) who meets the requirements of the RFP. CLIN 0004 is an Option and the TEP is the sum of CLINS 0001, 0002, 0003, and

0004.

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule for CLIN 0005 has been deleted:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

07-OCT-2018 1 568 EMXG/MXDXAP - F3QCCL

TECH ROAD, BLDG. 639

ROBINS AFB GA 31098

(478)327-9883

F3QCCL

SECTION I - CONTRACT CLAUSES

The following have been modified:

NOTE FOR INSURANCE MINIMUMS

NOTE: Reference clause 52.228-5 – In accordance with Para. (“A”) therein, the minimum amounts of insurance required are as follows:

Employers Liability: $100,000

General Liability: Bodily injury liability coverage written on the comprehensive form of the policy: $500,000 per occurance.

Automotive liability: Automobile liability insurance written on the comprehensive form of the policy – The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies of at least $200,000 er person and $500,000 per occurance for bodily injury and $20,000 per occurance for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Statement of Work 164 19-JAN-2017

Attachment 2 Appendix C, Industrial

Safety & Health

Requirements

14 14-DEC-2016

Attachment 3 B673 Drawings 3 10-NOV-2016

Attachment 4 B673 Utilities Map 1 19-JAN-2017

Attachment 5 Base Facility Standards 440 23-JUN-2014

Attachment 6 Procedural Guide for

Designers

20 29-MAY-2015

Attachment 7 Special Warranty

Requirements

2 19-JAN-2017

Attachment 8 Submittal Register 2 19-JAN-2017

Attachment 9 Wage Determination 5 27-JAN-2017 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Statement of Work 164 19-JAN-2017

Attachment 10 Statement of Work, Addendum #1

665 05-MAY-2017

Attachment 2 Appendix C, Industrial

Safety & Health

Requirements

14 14-DEC-2016

Attachment 3 B673 Drawings 3 10-NOV-2016

Attachment 4 B673 Utilities Map 1 19-JAN-2017

Attachment 5 Base Facility Standards 440 23-JUN-2014

Attachment 6 Procedural Guide for

Designers

20 29-MAY-2015

Attachment 7 Special Warranty

Requirements

2 19-JAN-2017

Attachment 8 Submittal Register 2 19-JAN-2017

Attachment 9 Wage Determination 5 27-JAN-2017

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been added by full text:

PROPOSAL SUBMISSION

Proposal Submission shall be submitted electronically, however, the original/hard-copy Bid Bond must be submitted to the Contracting office by the proposal due date and time. If the original/hard-copy Bid Bond is not received by the proposal due date and time, the proposal shall be considered non-responsive. Proposals shall be submitted electronically to Tracie.Sowels@us.af.mil and Brian.Mittelbach@us.af.mil.