About this file

This document contains questions and answers regarding an amendment to a solicitation for depot support services on United States Air Forces in Europe F-16 aircraft. The amendment provides clarification on pricing line item numbers for wing removal, replacement, and modification work. It specifies that line item numbers 58 and 59 should each include pricing for a pair of wings consisting of one left wing and one right wing. Additionally, line item numbers 35 and 37 are for generic wing replacement rather than SLEP work and should be priced separately per wing. Offerors should calculate pricing for line item numbers 58 and 59 according to the guidance provided to cover workscope from wing removal through reinstallation as described in the referenced technical instructions for one SLEP aircraft.

View the file

Other files for this federal contract opportunity

Other files attached to USAFE F16 DEPOT, newest first.
File Type Posted
Amendment_4_Attachment_2_-_PWS_USAFE_F-16_Depot_31_Mar_20.pdf PDF
Amendment_4_Attachment_1_USAFE_Pricing_Table_31_Mar_20.xlsx XLSX spreadsheet
Amendment_4_Attachment_1_USAFE_Pricing_Table_31_Mar_20.pdf PDF
Amendment_4_Attachment_16_-_PWS_Attachment_6_-_Unclassified_OCONUS_Engine_Runs_31_Mar_20.pdf PDF
Amendment_4_Attachment_5_USAFE_Section_M_31_Mar_20.pdf PDF
FA823220R0002_______0005.pdf PDF
Amendment_3_Attachment_1_USAFE_Pricing_Table_17_Mar_20.xlsx XLSX spreadsheet
Amendment_3_CLIN_0074_0075_stock_number_prices_19_March_20.xlsx XLSX spreadsheet
Amendment_3_Attachment_6_Attachment_L-1_past_performance_information.pdf PDF
Amendment_3_FA823220R0002_______0003.pdf PDF
Amendment_3_Attachment_11_-_PWS_Attachment_1_-_USAFE_USG_Provided_Materials_17_Mar_20.xlsx XLSX spreadsheet
Amendment_3_Attachment_1_USAFE_Pricing_Table_17_Mar_20.pdf PDF
Amendment_3_Question_Set_5_Tool List.xlsx XLSX spreadsheet
Amendment_3_Question_set_5_USAFE_17_March_20.docx DOCX document
Amendment_3_Attachment_4_USAFE_Section_L_17_Mar_20.pdf PDF
Amendment_2_Question_set_4_USAFE_9_March_20.pdf PDF
FA823220R0002_______0002.pdf PDF
Attachment_1_USAFE_Pricing_Table_6_Mar_20.pdf PDF
Attachment_17_-_GFP_6_Mar_20.pdf PDF
Attachment_11_-_PWS_Attachment_1_-_USAFE_USG_Provided_Materials_6_Mar_20.pdf PDF
Attachment_11_-_PWS_Attachment_1_-_USAFE_USG_Provided_Materials_6_Mar_20.xlsx XLSX spreadsheet
Attachment_1_USAFE_Pricing_Table_6_Mar_20.xlsx XLSX spreadsheet
Attachment_2_-_PWS_USAFE_F-16_Depot_6_Mar_20.pdf PDF
Amendment_1_Question_set_3_USAFE_6_Mar_20.docx DOCX document
Amendment_1_Question Set 2 - 27_Feb_20 USAFE.pdf PDF
Amendment_1_Attachment_1_-_USAFE_Pricing_Table_19_Feb_20.xlsx XLSX spreadsheet
Amendment_1_Attachment_2_-_PWS_USAFE_F-16_Depot_19_Feb_20.pdf PDF
Amendment_1_Question Set 1 - USAFE_19_Feb_20.pdf PDF
Amendment_1_Attachment_1_-_USAFE_Pricing_Table_19_Feb_20.pdf PDF
Depot_Requirements_Matrix.xlsx XLSX spreadsheet
Attachment_7_-_Attachment_L-2_-_Cover_Letter_Template.pdf PDF
Attachment_6_-_Attachment_L-1_-_Past_Performance_Information_Sheet.pdf PDF
Attachment_1_-_USAFE_Pricing_Table.xlsx XLSX spreadsheet
Attachment_10_-_Attachment_L-5_-_Past_Performance_Questionnaire.pdf PDF
FA823220R0002.pdf PDF
Attachment_12_-_PWS_Attachment_2_-_Additional_SLEP_Modification_Tooling.pdf PDF
Attachment_3a_USAFE_CDRLs.pdf PDF
Attachment_2_-_PWS_USAFE_F-16_Depot.pdf PDF
Attachment_5_USAFE_Section_M_24_Jan_20.pdf PDF
Attachment_11_-_PWS_Attachment_1_-_USAFE_USG_Provided_Materials.xlsx XLSX spreadsheet
Attachment_17_-_GFP.pdf PDF
Attachment_3b_USAFE_CDRLs_Option_CLINs.pdf PDF
Attachment_15_-_PWS_Attachment_5_-_Contractor_Provided_Tooling.xlsx XLSX spreadsheet
Attachment_13_-_PWS_Attachment_3_-_SLEP_Tool_Replacement_List.xlsx XLSX spreadsheet
Attachment_9_-_Attachment_L-4_-_Client_Authorization_Letter_sample.pdf PDF
Attachment_16_-_PWS_Attachment_6_-_Unclassified_OCONUS_Engine_Runs.pdf PDF
Attachment_8_-_Attachment_L-3_-_Sample_Consent_Letter.pdf PDF
Attachment_4_USAFE_Section_L_24_Jan_20.pdf PDF
FA823220R002_Synopsis.docx DOCX document
Attachment_1.docx DOCX document
Show all 50

USAFE F16 DEPOT has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 5: Question and Answer, set 8

1 – Can you confirm what you want to be included in CLIN 0058 & 0059?

• Even though the “Unit of Issue” in the latest pricing sheet is “EA”, you would like both the Left and Right Wing included in the pricing for CLIN 0058 “Remove/Replace of Wing Box (TCTO 2726)” and CLIN 0059 “Wing Box Modification and Upper Skin Replacement (16W9-13-501)”? So in effect, the quantity will be one (1) pair of SLEP Aircraft Wings (one left hand and one right hand)?

Correct. Per the guidance and clarification from Amendment 4 Q/A set 6, and Amendment 5 Q/A set 7, and Amendment 0005 of the solicitation, compute your price using TCTO 2726 for CLIN 0058 (price for both wings, Left & Right) and 16W9-13-501 for CLIN 0059 on 1 pair (price for both wings, Left & Right) of wings.

• You would also like the workscope for CLINS 0035 & 0037 “Wing Removal & Reinstallation” (Right Side & Left Side), included in the price for CLIN 0058 “Remove/Replace of Wing Box (TCTO 2726)” so that it covers one (1) pair of SLEP Aircraft Wings (one left hand and one right hand)?

Incorrect. Amendment 0005 of the solicitation uses different PWS references for CLINs 35 and 37 than it uses for CLINs 58 and 59, meaning the requirement is different. The references for 35 and 37 are 1.14.12, which are for generic wing replacement work. This is to be priced per wing, as directed in Amendment 0005 of the solicitation. CLINs 35 and 37 are not for SLEP.

Amendment 0005 of the solicitation references 1.3.5, 1.3.8 and 1.14.24 for CLINs 58 and 59. In the PWS, these references are for SLEP work.

Do not price CLINs 35 and 37 together with 58 and 59. They are different work.

• Please confirm that CLIN 0059 will only be executed in conjunction with CLIN 0058. The title of TCTO 2726 is “REPLACEMENT OF UPPER WING SKIN AND MODIFICATION OF LOWER WING

SKIN.”

As directed in Amendment 4 Q/A set 6, and Amendment 5 Q/A set 7: “For the purpose of this pricing estimate, both a left wing and right wing will be removed as part of 0058, modified as a set under CLIN 0059 and reinstalled under the original CLIN 0058. Both CLIN 0058 and 0059 will be completed only once for every one SLEP aircraft.” Compute your price in accordance with this guidance.

• When you total the pricing from CLIN 0058 and CLIN 0059 during your pricing evaluation, wii it cover the work-scope for each SLEP Aircraft from Removal of a pair of Wings through Re-installation of a pair of Wings with everything stated in TCTO 2726 and 16W9-13-501 included but not duplicated between the CLINS.

Price each CLIN separately. Per the guidance and clarification from Amendment 4 Q&A set 6, Amendment 5 Q&A set 7, and Amendment 0005 of the solicitation, compute your price using TCTO 2726 and 16W9-13-501 on 1 pair (price for both wings, Left & Right) of wings.