This document contains a question and answer set regarding an amendment to a solicitation for F-16 depot maintenance services in Europe. Key details include that the amendment clarifies pricing for wing modification clinical line items to specify that pricing for CLIN 0059 should include completion of all aspects of technical order 16W9-13-501 on a full set of wings, including removal and reinstallation as part of CLIN 0058. Additionally, CLIN 0058 and 0059 will only be completed once per SLEP aircraft. A related federal contract opportunity provides additional context, seeking contractor-operated depot maintenance and repair services for USAFE F-16s, including core and programmatic depot work, through an IDIQ contract with a potential period of performance from April 2020 through March 2030 and ceiling of $250 million. Services may also be performed by contractor field teams as needed excluding combat zones.

View the file

Other files for this federal contract opportunity

Other files attached to USAFE F16 DEPOT, newest first.
File Type Posted
Amendment 5 Question set 9.pdf PDF
Amendment 5 Attachment_1_USAFE_Pricing_Table_2_Apr_20.xlsx XLSX spreadsheet
Amendment_4_Attachment_2_-_PWS_USAFE_F-16_Depot_31_Mar_20.pdf PDF
Amendment_4_Attachment_1_USAFE_Pricing_Table_31_Mar_20.xlsx XLSX spreadsheet
Amendment_4_Question and Answer Set 6 Amendment 4.pdf PDF
Amendment_4_Attachment_4_USAFE_Section_L_31_Mar_20.pdf PDF
Amendment_4_Attachment_1_USAFE_Pricing_Table_31_Mar_20.pdf PDF
Amendment_4_Attachment_16_-_PWS_Attachment_6_-_Unclassified_OCONUS_Engine_Runs_31_Mar_20.pdf PDF
Amendment_4_Attachment_5_USAFE_Section_M_31_Mar_20.pdf PDF
FA823220R0002_______0005.pdf PDF
Amendment_3_Attachment_1_USAFE_Pricing_Table_17_Mar_20.xlsx XLSX spreadsheet
Amendment_3_CLIN_0074_0075_stock_number_prices_19_March_20.xlsx XLSX spreadsheet
Amendment_3_Attachment_6_Attachment_L-1_past_performance_information.pdf PDF
Amendment_3_FA823220R0002_______0003.pdf PDF
Amendment_3_Attachment_2_-_PWS_USAFE_F-16_Depot_18_Mar_20.pdf PDF
Amendment_3_Attachment_17_-_GFP_17_Mar_20.pdf PDF
Amendment_3_Question_Set_5_Tool List.xlsx XLSX spreadsheet
Amendment_3_Question_set_5_USAFE_17_March_20.docx DOCX document
Amendment_3_Attachment_4_USAFE_Section_L_17_Mar_20.pdf PDF
FA823220R0002_______0002.pdf PDF
Attachment_2_-_PWS_USAFE_F-16_Depot_6_Mar_20.pdf PDF
Amendment_1_Question_set_3_USAFE_6_Mar_20.docx DOCX document
Amendment_1_Question Set 2 - 27_Feb_20 USAFE.pdf PDF
Amendment_1_Attachment_1_-_USAFE_Pricing_Table_19_Feb_20.xlsx XLSX spreadsheet
Amendment_1_Attachment_5_USAFE_Section_M_19_Feb_20.pdf PDF
Amendment_1_FA823220R0002_______0001_20_Feb_20.pdf PDF
Depot_Requirements_Matrix.xlsx XLSX spreadsheet
Amendment_1_Attachment_2_-_PWS_USAFE_F-16_Depot_19_Feb_20.pdf PDF
Amendment_1_Question Set 1 - USAFE_19_Feb_20.pdf PDF
Attachment_7_-_Attachment_L-2_-_Cover_Letter_Template.pdf PDF
Attachment_15_-_PWS_Attachment_5_-_Contractor_Provided_Tooling.xlsx XLSX spreadsheet
Attachment_13_-_PWS_Attachment_3_-_SLEP_Tool_Replacement_List.xlsx XLSX spreadsheet
Attachment_9_-_Attachment_L-4_-_Client_Authorization_Letter_sample.pdf PDF
Attachment_16_-_PWS_Attachment_6_-_Unclassified_OCONUS_Engine_Runs.pdf PDF
Attachment_8_-_Attachment_L-3_-_Sample_Consent_Letter.pdf PDF
Attachment_4_USAFE_Section_L_24_Jan_20.pdf PDF
Attachment_14_-_PWS_Attachment_4_-_Required_Wing_Tooling.xlsx XLSX spreadsheet
Attachment_3a_USAFE_CDRLs.pdf PDF
Attachment_2_-_PWS_USAFE_F-16_Depot.pdf PDF
Attachment_5_USAFE_Section_M_24_Jan_20.pdf PDF
Attachment_11_-_PWS_Attachment_1_-_USAFE_USG_Provided_Materials.xlsx XLSX spreadsheet
Attachment_17_-_GFP.pdf PDF
Attachment_3b_USAFE_CDRLs_Option_CLINs.pdf PDF
Attachment_6_-_Attachment_L-1_-_Past_Performance_Information_Sheet.pdf PDF
Attachment_1_-_USAFE_Pricing_Table.xlsx XLSX spreadsheet
Attachment_10_-_Attachment_L-5_-_Past_Performance_Questionnaire.pdf PDF
FA823220R0002.pdf PDF
Attachment_12_-_PWS_Attachment_2_-_Additional_SLEP_Modification_Tooling.pdf PDF
FA823220R002_Synopsis.docx DOCX document
Attachment_1.docx DOCX document
Show all 50

USAFE F16 DEPOT has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-16 OCONUS Depot Solicitation: Question and Answer set 7

1. Question and Answer set 6 has an error. Question and answer 4 should state the following:

CLIN 0058 / 0059

A similar situation as to CLIN 0033 / 0035 / 0037 is applicable to CLIN 0058 / 0059 Question and Answer Last Set for Draft states;

Q: Is it correct that for both CLINs we have to include in our price the work on one wing excluding wing removal and reinstallation?

A: Yes, this is for one wing only. Price should include wing removal and reinstallation

This is incorrect – both wings is the correct answer.

Q: TCTO 2726 para 3 mentions the work required by this technical order will be accomplished concurrently with the work required by depot level T.O. 16W9-13-501. Can we combine CLIN 0058 and CLIN 0059 into one CLIN or can TO 16W9-13-501 be performed as standalone from TCTO 2726?

If you have to perform CLIN 0059, you always have to perform CLIN 0058 first. And for SLEP you have to perform CLIN 0058 twice: LH and RH. Therefore no removal or reinstallation work is priced in CLIN 0059. Is that correct?

A: Correct, no removal or reinstallation work should be priced in CLIN 0059. CLIN 0058 and CLIN 0059 are for completing the SLEP wing modifications on a set of wings (one left hand and one right hand). The position has evolved over the course of this solicitation and the previous guidance requires additional clarification. The offeror should price CLIN 0059, as a 1400 hr task over 100 calendar days to accomplish all aspects of 16W9-13-501 on a full set of wings (one left hand and one right hand). For the purpose of this pricing estimate both a left wing and right wing will be removed as part of 0058, modified as a set under CLIN 0059 and reinstalled under the original CLIN 0058. Both CLIN 0058 and 0059 will be completed only once for every one SLEP aircraft.