PDGU Questions & Answers Solicitation No. FA8232-16-R-3001
Questions 143 & 144
Question 143: Given that DoD 7000.14-R Vol 2A, Chapter 1, paragraph 010214 item c.
suggests that there is flexibility with appropriations over two years, is any of the FY16 funding ($4.48M) that is not spent in FY16 available for expenditure in FY17? For example: If the contract is not awarded until Sep 16, can we assume that $4.48M (FY16) plus $4.341M (FY17) = $8.821M total is available for expenditure during FY17?
Answer 143: No. Affordability caps will be enforced for the applicable FY regardless of FY funding.
Question 144: The 7 Jan version of the SOO removed the requirements to deliver TPS/ITAs and instead deliver data needed for TPS testing development. However, SOO paragraph 4.3 paragraph #3 still requires “Training shall include use and operation of Test Program Sets/Interface Test adapters (TPS/ITA).” Is this training requirement still required in spite of the change to the TPS/ITA design/hardware deletion?
Answer 144: No, the training identified in SOO paragraph 4.3 paragraph #3 is no longer required and will be removed from the SOO.