PD003_300psi_Air_System_3_May_2018.pdf

PDF 69 KB Posted

Attached to
Air Turbine Starter Test Stands
Solicitation number
FA8224-18-R-0020
Issued by

About this file

PD #003 update; note that revisions have been made, including but not limited to, 3.4 Piping, and 3.9, Life Cycle Sustainment.

View the file

Other files

File Type Posted
J-4_SOW.v2.1_Nov_2018.pdf PDF
FA8224.18.R.0020_Amendment_3.pdf PDF
ATS_Questions_and_Answers_1_Nov_2018.pdf PDF
ATS_Section_L_Instructions_18_Oct_2018.pdf PDF
J-7_CDRL_A007.v2.pdf PDF
FA8224-18-R-0020_Amendment_2.pdf PDF
ATS_Section_M_Evaluation_Factors_18_Oct_2018.pdf PDF
TO_00-5-3.dated_4_June_2018.pdf PDF
Amend2.Questions.18Oct.pdf PDF
FA8224-18-R-0020_Ammendment_1.pdf PDF
ATS_Section_M_Evaluation_Factors_15_Oct_2018.pdf PDF
ATS_Section_L_Instructions_15_Oct_2018.pdf PDF
TM.86.01P_for_A007_and_A018.pdf PDF
ATS_Questions_and_Answers_17_Sept_2018.pdf PDF
J-4_SOW.pdf PDF
J-6_CDRL_A009.pdf PDF
FA8224.18.R.0020.pdf PDF
ATS_Section_M_Evaluation_Factors_14_Sep_2018.pdf PDF
J-3_PD003.pdf PDF
J-7_CDRL_A007.pdf PDF
J-2_PD002.pdf PDF
J-9_Drawing_9579776_98752_N.pdf PDF
J-8_Government_Furnished_Equipment_List.pdf PDF
J-10_Drawing_9579777_98752_B.pdf PDF
ATS_Section_L_Instructions_14_Sep_2018.pdf PDF
J-5_NSP_CDRLs.pdf PDF
ATSTS_SOW_20_June_18.pdf PDF
CDRL_A017_Mishap_Notification_and_Reporting_2Feb2018.pdf PDF
CDRL_A014_Physical_Configuration_Audit_(PCA)_Report_2Feb2018.pdf PDF
CDRL_A013_Physical_Configuration_Audit_(PCA)_Plan_2Feb2018.pdf PDF
CDRL_A015_Automated_Computer_Program_ID_Number_(ACPIN)_Data_and_Control_Record__2Feb2018.pdf PDF
CDRL_A016_Safety_and_Health_Plan_2Feb2018.pdf PDF
CDRL_A009_Engineering_Drawings_Air_Turbine_Starter_2Feb2018.pdf PDF
CDRL_A003_Test_Plan_(Factory_Acceptance_Test_(FAT)_2Feb2018.pdf PDF
PD003.ATSTS.05072018.pdf PDF
CDRL_A018_Commercial_Off-The-Shelf_(COTS)_Manual_and_Supplemental_Data_2Feb2018.pdf PDF
PD002.ATSTS.05072018.pdf PDF
SectionM.06112018.pdf PDF
ATSTS_Draft_Model_Contract.docx DOCX document
ATS_SOW_20_June_2018.docx DOCX document
CDRL_A001_Contractor's_Progress,_Status_and_Management_Report__2Feb18.pdf PDF
CDRL_A010_Calibration_and_Measurement_Requirements_Summary_(CMRS)_2Feb2018.pdf PDF
CDRL_A014_Physical_Configuration_Audit_(PCA)_Plan_2Feb2018.pdf PDF
CDRL_A012_Acceptance_Test_Report_(ATR)_2Feb2018.pdf PDF
CDRL_A002_Conference_Minutes_(Post_Award_Conference)_2Feb2018.pdf PDF
CDRL_A008_Conference_Agenda_2Feb2018.pdf PDF
CDRL_A011_Acceptance_Test_Plan_(ATP)_2Feb2018.pdf PDF
ATS_Questions_and_Answers_11_June_2018.pdf PDF
PD002_Process_Air_System_3_May_2018.pdf PDF
ATS_Section_L_28_Feb_2018_Track_Changes.pdf PDF
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3 May 2018

DISTRIBUTION STATEMENT A. Approved for public release: Distribution is unlimited.

PD #003

Purchase Description (PD) for

300 PSIG NOMINAL COMPRESSED AIR SYSTEM

Prepared by:

COMMODITIES SUPPORT MAINTAINENCE GROUP

309TH CMXG

HILL AFB UT 84056

PD003 2

THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK

PD003 3

TABLE OF CONTENTS

1. SCOPE

1.1. Scope Statement

2. APPLICABLE DOCUMENTS

2.1. Government Documents

2.2. General Industry Regulations

3. REQUIREMENTS

3.1. General

3.2. Compressors

3.3. Air Quality

3.4. Piping

3.5. Storage

3.6. Safety

3.8. Hose Requirements

3.9. Life Cycle Sustainment

Appendix A

PD003 4

1. SCOPE

1.1. Scope Statement. The purpose of this Purchase Description (PD) is to define the technical requirements for the 300psig nominal compressed air system.

2. APPLICABLE DOCUMENTS

2.1. Government Documents. The following specifications, standards, and handbooks of the exact revision listed below form a part of this specification to the extent specified herein.

2.1.1. Technical Orders. None.

2.1.2. Department of Defense Standards. None.

2.2. General Industry Regulations. Test stand design shall conform to the following:

2.2.1. NFPA 70: National Electric Code (NEC), latest edition

2.2.2. 29 CFR 1910 Occupational and Health Administration (OSHA) General Industry Regulations

3. REQUIREMENTS

3.1. General. The air system shall connect to the three existing pneumatic component test stands in Room 112 and the existing test stand connection on the south wall of Room 106. The air system design shall consist of new piping from the location of the compressors up to the test stand connection points. The design shall include isolation valves close to each test stand.

3.2. Compressors. The air system shall include a minimum of two (2) compressors, each capable of producing a minimum of 0.5 pounds per minute @ 300 ± 20 psig nominal pressure. The compressors shall be staged with pressure switches so that they run on demand. The compressor controller shall allow the compressors to alternate being the primary supply to keep operating hours more even. Each compressor shall have the ability to be isolated for maintenance while the other(s) remain in operation.

3.3. Air Quality. The air system shall be clean, oil free (<4ppm), and dry (<0°F dew point.) The system shall include a 25 micron or better air filter that can be isolated and depressurized for maintenance.

PD003 5

3.4. Piping. Air supply piping, and valves, shall be non-corrosive material (e.g. stainless steel, anodized aluminum IAW the latest revision of ASME B31.3) rated for all expected temperatures and pressures. Piping shall be sized to match the existing line sizes of the existing pneumatic component test stands.

3.5. Storage. The air system shall include a minimum 50 gallon storage tank. The storage tank shall have an automatic adjustable condensate drain valve.

3.6. Safety. The air system shall conform to the General Industry Requirements listed in paragraph 2.2. The system shall have a safety relief valve.

3.7. Energy Efficiency. To fullest extent possible, the contractor shall incorporate energy efficiencies into the test system design and function (e.g. expected process time, pre-heat, state of equipment during idle time, etc.).

3.8. Hose Requirements. The air system shall not utilize hoses.

3.9. Life Cycle Sustainment. The overall system design (e.g. components, hardware, software, etc.) shall be reliable, accessible, and maintainable and also allow the Government to competitively select service providers for all future repairs without involving the original manufacturer of the system. Wherever possible, the contractor shall use components that are commercially available, commonly used in comparable industry equipment, interchangeable with other brands, and competitively priced. The ATS system design shall not force the Government into a sole-source condition with the original manufacturer of the system when repairs or replacement parts are required. The system design shall not require the Government or a Government contractor to perform any reverse engineering in order to make system repairs.

PD003 6

APPENDIX A. ACRONYMNS AND ABBREVIATIONS

NEC National Electric Code OSHA Occupational and Health Administration

PD Purchase Description PSIG Pounds per Square Inch – Gauge

1. SCOPE
3. REQUIREMENTS