FOM_Answers.docx

DOCX document 16 KB Posted

Attached to
Facilitate Other Maintenance Federal contract opportunity
Solicitation number
FA8224-16-R-0021
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Answers to questions 1

View the file

Other files for this federal contract opportunity

Other files attached to Facilitate Other Maintenance, newest first.
File Type Posted
FA8224-16-R-0021-0003.pdf PDF
PWS_AMXG_FOM_27_Apr_16.docx DOCX document
FOM_Answers_(3).docx DOCX document
FA8224-16-R-0021-02.doc DOC document
PWS_AMXG_FOM_17_Mar_16.docx DOCX document
afman33-282.pdf PDF
afi33-115.pdf PDF
afi32-7086.pdf PDF
afi21-102.pdf PDF
FA8224-16-R-0021-01.doc DOC document
FOM_Answers_(2).docx DOCX document
afi31-501_afmcsup_i.pdf PDF
afman23-122.pdf PDF
AMXGOI 24-5.pdf PDF
afi10-701.pdf PDF
afh23-123v1.pdf PDF
afscman21-102.pdf PDF
afi32-7086_hillafbsup_i.pdf PDF
afpd24-3.pdf PDF
afi33-200.pdf PDF
AMXGOI 21-7.pdf PDF
AMXGOI 21-12.pdf PDF
afi23-101.pdf PDF
afi21-101_afmcsup_oo-alcsup.pdf PDF
afman33-152.pdf PDF
afi21-102_afmcsup.pdf PDF
AFI31-101.pdf PDF
CDRL_A002_Quality_System_Plan.pdf PDF
CDRL_A005_Management_Plan.pdf PDF
CDRL_A003_Safety_Program_Plan(SSPP).pdf PDF
CDRL_A004_Accident_Report.pdf PDF
PWS_AMXG_FOM_17_Feb_16.docx DOCX document
CDRL_A001_Status_Report.pdf PDF
FA8224-16-R-0021.doc DOC document
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The PWS for FA8224-16-R-0021 states a two shift operation in the scope (Para 1) but mentions The Contractor shall perform services required under this contract per the below 5/4/9 Alternating Week Work Schedule: Sunday 10 p.m. to Friday 12:15 a.m and the working “Friday” from Thursday 10:00 p.m. to Friday 11:15 p.m. (Para 10.1)

Question: It doesn’t seem possible to cover the full time between Sunday 10 p.m - Friday 12:15 a.m., with only two 9 hour shifts. Please confirm that it is a two shift maintenance (and please include the daily work hours) or if it is three shift to cover the entire time between Sunday and Friday.

The PWS is written incorrectly. Our intention is to work two-shift operations. Depending on which aircraft the contractor is supporting, the starting and finishing hours will differ. PWS Paragraph 10.1 has been rewritten and Appendix E (Work Schedule) has been added.

The PWS (para 2.2.3) states “The Contractor shall contact the Maintenance Operation Center (MOC), as applicable, to route FOM assets to or from storage to the aircraft maintenance dock and/or repair centers.

Question: Is the Contractor responsible for the physical delivery of the assets to the MOC, hence the need for GMV licenses? Or is there a delivery system on base utilized?

No, the items will be transferred by 309 AMXG drivers. The Contractor is not responsible to move assets.

The PWS (para 15) mentions the “In the event Contractor employees are required to operate GMVs…”

Question: In the event makes it sound like this is a rare requirement, but it greatly affects staffing if employees are driving. Can you give an estimated amount of driving requirement is needed?

You are correct that your employees would probably not be driving under this contract. The language was inserted into the PWS in case there was an incident where your employees needed to drive.

1.What is the required proposal response format (i.e. font size, margins, charts, and tables etc.)

2.Will charts and graphs count towards the page count?

3.Will the government supply a Bidders Library? If the referenced documents are not provided, contractors outside of the governments firewall will not able to obtain all referenced and/or required documents as listed in the PWS (Technical Orders, Local Operational Instructions, Air Force Instructions (AFI), and others listed).

Will provide a Bidders Library

4.The FAR Clause at 52.212-1 suggests the government is interested in receiving multiple offers from a single vendor (page 11 (e) of solicitations standard form 1449). Is this correct?

1. Is this new work? If not new work, who is the incumbent?

This is a new workload.

2. With the 2 operational shift requirement per Appendix D, this will put a burden on employees covering 12 hours per shift. Wouldn't a three-shift operation be more suitable?

The PWS is written incorrectly. The intention is to work a two-shift operation. Depending on which aircraft the contractor is supporting, the starting and finishing hours will differ. PWS Paragraph 10.1 has been rewritten and Appendix E (Work Schedule) has been added.

3. Please define Cat 1 and Cat 2 aircraft per paragraph 2.1.7

Cat refers to the length a C-130 aircraft will be in the depot.

Cat 1- the aircraft will be in the depot 117 days. Cat 2 – the aircraft will be in the depot 135 days.

4. Is the GMV requirement finalized per paragraph 15?

Yes, it is unlikely that the contractor will be driving under this contract. The language is inserted into the PWS if the Government asks the contractor to drive.

5. Will flightline driving be required and will the govt provide the training and qualification?

At this time no flight driving is required, but in the event the requirement does come up, the Government will provide the training and qualification.

Does the Combined Synopsis/Solicitation under solicitation number FA822416R0021 contain requirements similar to a current contract?

If possible, please provide the current contract number.

Or, is this a new requirement for the government?

This is a new requirement for the Government.

Can you tell me if there is an incumbent contractor currently performing work for this requirement? If so, could you please provide their company name and contract number?

Since this is a new requirement, there is no incumbent.